Scrutiny Committee noted this item on Tuesday 2 October 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
to note the report.
Agenda Item 10
Scrutiny Committee
Report of Head of Planning Author: Cathie Scotting Telephone: 01235 422600 E-mail: [email protected] Cabinet member responsible: Felix Bloomfield Tel: 01491 832690 E-mail: [email protected] To: Scrutiny Committee DATE: 2 October 2018
S106 Planning Obligations Monitoring Report 2017/2018 Recommendation To receive an update on the S106 planning obligations 2017/18 and to provide any feedback to the Cabinet member for planning.
Purpose of Report 1. This report aims to provide councillors with a summary of financial sums secured, received and spent in relation to Section 106 agreements for the financial year 2017/18.
Strategic Objectives 2. The section 106 monies contribute to our objective to invest in the district’s future by creating the right conditions for economic growth so that businesses, residents and workers can prosper by directly addressing matters in our control that fetter growth, such as housing supply and provision of affordable housing. We will work with partners to seek to overcome infrastructure bottlenecks that impact adversely on business competitiveness.
Background 3. Planning obligations under Section 106 of the Town and Country Planning Act 1990 are commonly known as S106 agreements. They provide a formal legal mechanism to secure measures that help make development proposals Page 47 Agenda Item 10
acceptable in planning terms. Since the council implemented the Community Infrastructure Levy (CIL) Charging Schedule; 1 April 2016, Section 106 agreements have to be considered in the context of CIL to avoid ‘double dipping’. To address this, a S106 Supplementary Planning Document was published and effective from 1 April 2016 to compliment CIL.
4. Under S106 agreements developers and landowners are legally obliged to make the required contributions. The agreement sets out the obligations on the developer in terms of what contributions are to be made and at what stage (triggers) of the development they are required. For the council, the agreement sets out what the contribution is to be spent on and the timeframe for it to be delivered.
5. Under S106 agreements developers are normally required to notify the council when they reach key stages of a development and in response, where these stages trigger a financial obligation, we will invoice for the due amount (index linked).
6. The signing of an agreement does not guarantee the funds. As S106 agreements are to mitigate impacts of development they are only paid if a development occurs and the triggers have been reached. A proportion of planning permissions are never implemented. As a result a proportion of expected contributions agreed never come to fruition. Where a development does proceed contributions will be paid at key stages such as a certain level of occupation, e.g. the 50th dwelling. On large developments these triggers may not occur for several years, which impact on infrastructure delivery.
Monies secured and received 7. During the financial year 2017/18, a total of £52,782,441.19 (£41,284,870 OCC, £11,497,517.19 SODC) was secured in S106 agreements from new development, see Appendix 1 for a breakdown. The collection and spending of County Council contributions is not monitored by us.
8. A total of £1,447,374.51 was collected during the 2017/18 financial year from sites such as
- Former Cement Works, Land at Kiln Lane Chinnor - Hithercroft Industrial Estate, Wallingford - Siareys Yard Station Road, Chinnor - Thame Service Station 67-68 Park Street, Thame - Land North of London Road, Wheatley - Land East of Thame Park Road, Thame
9. The table below shows the total sums received by infrastructure type (including monitoring fees).
Infrastructure type S106 Amount Received (£) Affordable housing 430,786.60 Car parks 10,450.82 Cemetery 2,348.81 Community Buildings 60,229.62 Countryside 21,238.86 Page 48 Agenda Item 10
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
S106 Planning Obligations Monitoring Report 2017/2018Report | 185 KB | DownloadRead as text |
Follow Scrutiny Committee at South Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Minutes of the last meetingDecision (ICMD) relating to a contract extension, which due to timing meant that calling-in the decision would not be... | Agreed | Open |
| 21 Sep 2026 | Work schedule and dates for all South Scrutiny meetingsCommittee noted the work programme with the additional comments. | Noted | Open |
| 21 Sep 2026 | Financial Outturn 2025/26to note the overall outturn position of the council as well as the outturn of individual service areas. | Noted | Open |
| 21 Sep 2026 | Berinsfield Garden Village - Update and next stepsa) Scrutiny Committee supported the corporate position for Berinsfield Garden Village and the draft Berinsfield Garde... | Decided | Open |
| 15 Jun 2026 | Work schedule and dates for all South scrutiny meetingsCommittee noted the work programme with the additional comments. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.