CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
South Oxfordshire District Council
Joint Audit and Governance Committee, Monday 15 October 2018 at 6.30pm

Internal audit management report quarter two 2018/2019

Noted Finance 5 papers

Joint Audit and Governance Committee noted this item on Monday 15 October 2018. Below is the council's own wording, with the papers it was decided on.

Item29

Resolved

to note the internal audit management report for the second quarter of 2018/19.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Joint Audit and Governance Committee

Purpose of report

1. The purpose of this report is:

 to report on management issues within internal audit;

 to summarise the progress against the 2018/2019 audit plan up to 30 September 2018; and

 to summarise the priorities for quarter three 2018/2019.

Page 20 Agenda Item 7

2. The contact officer for this report is Victoria Hughes, Internal Audit Manager for South Oxfordshire District Council (SODC) and Vale of White Horse District Council (VWHDC), telephone 01235 422430.

Strategic objectives

3. Delivery of an effective internal audit function will support the councils in meeting their strategic objectives.

Background

4. The Public Sector Internal Audit Standards (PSIAS) from 1 April 2017 states that the head of internal audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the resource requirements to deliver the plan, for audit committee approval. The joint committee approved the 2018/2019 annual internal audit plan on 26 March 2018.

5. The PSIAS also states that the head of internal audit must periodically report on performance relative to the plan.

Management issues

6. The internal audit manager joined the councils on 18 September at which point the interim manager resumed the role of auditor. The audit team is now fully resourced having carried a vacancy for five and a half months.

Progress against the 2018/2019 audit plan

7. Progress against the approved audit plan has been calculated for the quarter and year to date and is summarised in appendix 1 attached.

8. Performance figures to date are as follows:

Actuals by Quarter Q1 Q2 Q3 Q4 Target YTD 18/19 18/19 18/19 18/19 Chargeable 74% 76.5% 78% 76% - - (identifiable client and/or specific IA deliverable) Non-Chargeable 9% 6.5% 4.5% 9% - - (corporate, not IA deliverable) Planned Lost 15% 15.5% 16% 13.5% - - (i.e. leave) Unplanned Lost 2% 1.5% 1.5% 1.5% - - (i.e. study, sickness)

9. As at 30 September 2018 the status of audit work against the 2018/2019 audit plan is as follows:

Planned

Strategic, operational and financial assurance work known and approved by the joint audit and governance committee.

Page 21 Agenda Item 7

In progress

commence 2018/2019

Complete Planned

Draft

To PLANNED 24 2 1 6 15 Joint 24 2 1 6 15 SODC 0 0 0 0 0 VWHDC 0 0 0 0 0

Adhoc

Unplanned project work based on agreed terms of reference with the audit manager (i.e. implementation of new systems) and responsive work issued and agreed by the section 151 officer, members or senior management team (i.e. investigations).

In progress 2018/2019

commence Requested

Complete

Draft

To ADHOC 0 0 0 0 0 Joint 0 0 0 0 0 SODC 0 0 0 0 0 VWHDC 0 0 0 0 0

Follow up

Work undertaken to ensure that agreed recommendations have been implemented. The number of follow-up audits is a rolling number, all internal audit reports are followed up after six months unless the area is subject to an annual review. In progress

commence Requested

2018/2019 Complete

Draft

To

FOLLOW-UP 3 3 0 0 0 Joint 3 3 0 0 0 SODC 0 0 0 0 0 VWHDC 0 0 0 0 0

Page 22 Agenda Item 7

Priorities for 2018/2019 quarter three (Oct 2018 - Dec 2018)

10. The priorities for quarter three are to:

 Review and update the internal audit strategy.  Review and update the internal audit charter.  Agree revised approach to risk reporting for internal audit recommendations.

11. Remaining 2018/2019 planned audit work can be reviewed in appendix 2.

Financial implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IA Mgt reprt App 1a: Planned Audits A3Appendix 80 KB Download
PDF
IA Mgt reprt App 1b: Follow up AuditsAppendix 78 KB Download
PDF
IA Mgt reprt App 1c: Unplanned AuditsAppendix 80 KB Download
PDF
IA Mgt rprt App 2: Audit Plan Schedule 2018-2019Appendix 106 KB Download
PDF
Internal audit management report quarter two 2018/2019Report 171 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
MB
Mike BadcockCommittee Member, present
YC
Yvonne Cutler-GreavesOfficer, expected
VH
Victoria HughesOfficer, expected
SH
Simon HewingsOfficer, expected
DH
Dudley HoddinottCommittee Member, apologies, sent representative
SH
Simon HowellCo-Chair, present
WJ
William JacobsOfficer, expected
TN
Toby NewmanCommittee Member, apologies
CP
Chris PalmerCommittee Member, present
AP
Adrianna PartridgeOfficer, expected
JR
Judy RobertsSubstitute, present as substitute
RS
Ron SchrieberOfficer, expected

All 15 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Internal audit management report quarter two 2018/2019This decision
  2. Internal audit annual report 2025/2026Noted
  3. Internal Audit Report Q1 2026/27Decided
  4. Internal audit plan 2026/27Approved
  5. Internal audit update report Q3 2025/26Decided
  6. New Global Internal Audit Standards in the UK Public Sector & Updated Internal Audit CharterNoted

More from South Oxfordshire Joint Audit and Governance Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Annual Review of Complaints 2025/26That the committee noted: (a) the formal complaints received in 2025-26 and the councils’ performance in responding t... Noted Open
7 Jul 2026 Statement of accounts 2025/26 updateThat the committee (a) Noted progress on completing the 2025/26 Statement of Accounts and on the external audit build... Noted Open
7 Jul 2026 Internal audit annual report 2025/2026That the committee considered and noted the annual internal audit opinion and report. Noted Open
7 Jul 2026 Internal Audit Report Q1 2026/27RESOLVED : That the committee reviewed the results of recent internal audit work and monitored progress of management... Decided Open
7 Jul 2026 Internal audit plan 2026/27RESOLVED : That the committee approved the internal audit plan 2026/27. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies