to 1. create a new capital scheme within the council’s approved capital programme to refurbish the dry side toilets at Thame Leisure Centre; 2. vire £22,135 from the existing Thame wet side changing room refurbishment budget into that new capital budget; 3. create a new capital scheme within the council’s approved capital programme to refurbish dry side changing rooms at Henley Leisure Centre; and 4. vire £19,271 from the existing wet side changing room refurbishment budget into that new capital budget.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Report of Head of Community Services Author: Chris Webb Telephone:01235 422202 Textphone: E-mail: [email protected] Wards affected: Henley and Thame Cabinet member responsible: Lynn Lloyd Tel: 01844 354313 E-mail: [email protected] To: CABINET Date: 18/12/2018
Virement of surplus capital budgets for refurbishment works at Henley and Thame Leisure Centres Recommendations Recommend to council to approve:
(a) The creation of a new capital scheme within the councils approved capital programme to refurbish the dry side toilets at Thame Leisure Centre.
(b) The virement of £22,135 from the existing Thame Wet side changing room refurbishment budget into that new capital budget.
(c) The creation of a new capital scheme within the councils approved capital programme to refurbish dry side changing rooms at Henley Leisure Centre.
(d) The virement of £19,271 from the existing wet side changing room refurbishment budget into that new capital budget.
Purpose of Report 1. To seek approval from cabinet to use surplus budget for the refurbishment of the dry side facilities at Thame and Henley Leisure Centres. Making improvements to these areas will bring them in line with the recently improved wet side change
Page 91 Agenda Item 12
facilities and in doing so, improve the user experience at the centres and extend the life of the facilities.
Corporate Objectives 2. Deliver high performing services with emphasis on achieving excellent levels of recycling, keeping streets and public spaces clean and attractive, and ensuring good quality sports and leisure provision.
Background 3. During 2018 the leisure client team undertook the refurbishment of the wet side changing rooms at both Thame and Henley leisure centres. Capital budgets were approved and subsequently tendered through the Capita Portal. Tenders were obtained from the open market which were within the available budget. Orders and contracts were placed, and works were completed to time. Having now completed both projects to the required standards, officers have identified that additional planned improvements could be delivered using the underspend from these budgets.
4. Cabinet is requested to consider whether to undertake further refurbishment works at the two centres to enhance the service to customers and maintain the asset, or to return the balances to the main capital budget.
5. Customers made both verbal and written complaints to the press regarding the condition at Henley Leisure Centre where the wet side improvements have taken place on how much better those facilities are compared to the dry side. And that they would wish to see the dry side facilities match the wet side. This has been repeated for Thame but without the press engagement.
6. The dry side toilet facilities at Thame are in a poor state decoratively and are the original cubicles and fittings from when the centre was built in the 1980’s. There is an opportunity to refurbish the toilet facilities at Thame which are in a poor condition thereby improving the overall customer experience consistent with other areas of the centre.
7. The dry side changing facilities at Henley were refurbished in 2004/5 but have left several on-going issues. Most importantly water from the dry side showers is seeping into the sports hall from adjoining walls and degrading the structure of those walls and possibly the sports hall floor. This is due to the poor laying of the floor tiles and the grout used to waterproof the area. There is an opportunity to resolve the failing dry side facilities at Henley.
Options 8. Approval of the virement of surplus budgets into two new capital budgets, which will allow the procurement of suitable contractors to refurbish the dry side toilets at Thame and dry side changing rooms at Henley Leisure Centres.
9. These works are unlikely to be funded from the general repairs and maintenance budget as this budget is being prioritised for major roof and boiler replacements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
South and Vale Local Development Schemea) To approve the revised Local Development Scheme, June 2026. b) To delegate the making of minor updates to the Join...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.