Resolved
to approve the internal audit plan 2019/20.
Joint Audit and Governance Committee approved this item on Monday 25 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
to approve the internal audit plan 2019/20.
4. The Public Sector Internal Audit Standards (PSIAS) from 1 April 2017 states that the head of internal audit should prepare a risk-based audit plan, which should outline the assignments to be carried out and the resource requirements to deliver the plan, for audit committee approval.
5. The PSIAS also states that the audit committee should approve the annual internal audit plan and monitor progress against the plan.
Audit Allocation
6. The resources available to deliver the internal audit annual plan 2019/2020 are arrived at by starting with the number of days available for all internal audit posts within the team. This is then reduced by the estimated numbers of days lost through annual leave, bank holidays (planned) and sickness absence (unplanned). Allowance has been made within the available time for the two auditor vacancies, following the internal promotion of two auditors in January 2019. The remaining days available are then allocated between the various elements of work which are expected to be carried out in the year in order to deliver an effective internal audit service.
7. The calculation of days available and the allocation of days between different categories of work is attached as appendix 1. The different categories of work are classed as either chargeable or non-chargeable. Chargeable means the work has an identifiable client or is directly linked to the delivery of internal audit services. Non-chargeable means any other work which is not directly linked to the delivery of internal audit services (for example: admin, corporate responsibilities, training, staff briefings).
8. The calculation of days for next year is lower than the previous year as it assumes a vacancy of two months for the two vacant auditor posts. An explanation of the individual variances against the previous year allocated days is provided after the calculation in appendix 1.
Schedule of Auditable Activity (SAA)
9. The SAA attached as appendix 2 lists every possible audit area at both or either South Oxfordshire District Council and the Vale of White Horse District Councils. Each audit has been rated by the internal audit manager and critically reviewed by the head of finance (section 151 officer) on a number of key factors to give a priority score, and this assists in the assessment of what should be placed in the annual audit plan. Although scoring is subjective and no two people would score alike the process attempts to introduce a degree of objectivity into the assessment process. The key at the bottom of the spreadsheet explains the scoring and provides risk definitions.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
IA annual plan Appendix 1Appendix | 97 KB | Download |
PDF |
IA annual plan Appendix 2 SAAAppendix | 136 KB | Download |
PDF |
IA annual plan Appendix 2 SAA notesAppendix | 84 KB | Download |
PDF |
IA annual plan Appendix 3Appendix | 89 KB | Download |
PDF |
Internal audit annual plan 2019/20Report | 164 KB | DownloadRead as text |
Follow Joint Audit and Governance Committee at South Oxfordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Jul 2026 | Annual Review of Complaints 2025/26That the committee noted: (a) the formal complaints received in 2025-26 and the councils’ performance in responding t... | Noted | Open |
| 7 Jul 2026 | Statement of accounts 2025/26 updateThat the committee (a) Noted progress on completing the 2025/26 Statement of Accounts and on the external audit build... | Noted | Open |
| 7 Jul 2026 | Internal audit annual report 2025/2026That the committee considered and noted the annual internal audit opinion and report. | Noted | Open |
| 7 Jul 2026 | Internal Audit Report Q1 2026/27RESOLVED : That the committee reviewed the results of recent internal audit work and monitored progress of management... | Decided | Open |
| 7 Jul 2026 | Internal audit plan 2026/27RESOLVED : That the committee approved the internal audit plan 2026/27. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.