AI summarySouth Oxfordshire Scrutiny Committee supports Cabinet recommendations to transfer £2.1m S106 funding and £335,470 Garden Town funding for the 116-120 Broadway, Didcot redevelopment, subject to Homes England funding being secured.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedIncludes delegated contract award authority and two budget transfers
Money£2.1m and £335,470S106 funding for Phase 2 and Didcot Garden Town funding for community space
What happens nextCabinet meeting 16 April 2026To seek approval to proceed with delegated authority for contract award
Who it affectsNot stated
What was decided
The committee noted and supported the Cabinet report, delegating authority to the Director of Development and Corporate Landlord and/or Director of Finance to award the JCT Design and Build Contract once project funding is secured. Report P7, P8
The committee supported the transfer of £2.1m S106 funding from provisional to approved capital budget for Phase 2 works. Report P9
The committee supported the transfer of £335,470 from Didcot Garden Town capital funding to the Broadway project for community space works, and asked that risks and a lessons learned review be considered. Report P10
Why
The site at 116-120 Broadway has been underused and derelict since 2020, and the council wants to provide affordable housing and community space in Didcot town centre. Report P28, P38
The development is intended to meet Passivhaus and EnerPHit energy efficiency standards and serve as a benchmark for future council projects. Report P38, P44, P45
Didcot Garden Town plans accommodate over 15,000 new homes and 20,000 new jobs, and this scheme helps meet the council's housing targets with car-free, high-quality affordable homes. Report P38, P43
What happens next
The Homes England Social and Affordable Homes Programme funding decision is expected by 29 May 2026, after which a contract award notification could be issued on 15 June 2026. Report P19, P20
If funding is secured, JCT Design and Build Contracts would be signed on 30 June 2026, with site mobilisation on 14 September 2026 and start on site on 30 September 2026. Report P21, P23
Practical completion is scheduled for 14 October 2027, with a member site visit planned for May 2027; members will continue to be updated through the DCL Members Update. Report P23, P24, P53
The money
£2.1m S106 funding transfer from provisional to approved capital budget for Phase 2 works Report P9
£335,470 Didcot Garden Town capital funding transferred to the Broadway project for community space works Report P10
Implications
Financial: The project depends on securing Homes England Social and Affordable Homes Programme funding; if not secured, officers will present alternative options including borrowing, scope reduction, or alternative development strategies. Report P32, P28
Risk: Design may come in over budget in tender returns, which the Homes England funding bid is intended to mitigate. Other risks include inadequate tenant handover for Passivhaus systems, possible EnerPHit shortfalls at 120 Broadway, ground floor voids, and conflicts between community and residential uses. Report P32, P33, P34, P35
Climate: The development targets Passivhaus standards for the new build at 116-118 and EnerPHit standards for the retrofit of 120, using timber construction, fabric-first design, airtightness strategy, and individual exhaust-air heat pumps. Report P45, P46, P47, P48
Legal: Site considerations include restricted access, an adjacent occupied property at 122 Broadway, party wall matters with 114 Broadway, drainage access through the shopping centre service road, and planning permission conditions. Report P41
Other: A formal management model for the building will need to be developed alongside Phase 2, and officers will provide tenant guides, training, and maintenance programmes for the Passivhaus and EnerPHit systems. Report P33, P35
Who and where
Future residents of nine affordable units (one 2-bedroom and eight 1-bedroom car-free homes) at 116-120 Broadway, Didcot Report P43
Didcot community and local groups who may use the flexible ground floor community or retail space Report P33, P43
Occupiers of 122 Broadway, which is attached to 120 Broadway and remains occupied during the works Report P41
Builders working at 114 Broadway, due to party wall and adjacent construction considerations Report P41
Wider Didcot residents, given the scheme supports town centre regeneration and Didcot Garden Town growth plans for over 15,000 new homes Report P38
Timeline
23 March 2026: Homes England funding bid submitted under the Social and Affordable Homes Programme 2026-2036 Report P17, P32
10 April 2026: Homes England IPQ's submission, with funding decision process expected to take around 6 weeks Report P17
16 April 2026: Cabinet meeting to seek approval to proceed with delegated authority for issuing contract award notification if funding bid is successful Report P19
29 May 2026: Earliest expected date for the Homes England funding decision Report P19
12 June 2026: Delegated authority to approve issuing notification of contract award, if funding decision is positive and received by 29 May 2026 Report P20
15 June 2026: Notification of award, conditional on funding being secured Report P20
29 June 2026: Standstill period ends after 8 working days Report P20
30 June 2026: JCT Design and Build contracts signed at end of extended tender period Report P21
14 September 2026: Site mobilisation, lasting around 2 weeks Report P23
25 September 2026: Main contractor completes RIBA Stage 4 design (around 8-12 weeks) Report P21
30 September 2026: Start on site, with a circa 45-week programme excluding Christmas and Easter shutdowns Report P23
May 2027: Member site visit to review progress and meet the contractor Report P23
14 October 2027: Practical completion, with 7 weeks of float and contingency built in Report P24
Plain English for the jargon
JCT Design and Build Contract: A standard construction contract issued by the Joint Contracts Tribunal under which a contractor designs and builds the project.
S106: Section 106 planning obligation, a developer contribution secured through the planning system and used by the council to fund infrastructure or other project costs.
Passivhaus and EnerPHit: Energy efficiency standards: Passivhaus applies to new build, while EnerPHit is the equivalent standard for retrofit of existing buildings.
RIBA Stage 4: Royal Institute of British Architects work stage covering technical design, where detailed design and specifications are completed before construction.
SAHP: Homes England Social and Affordable Homes Programme 2026-2036, the funding stream the council has applied to for this scheme.
EAHP: Exhaust-air heat pump, a low-carbon heating solution recommended for each dwelling by the project's services engineer.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item147
Resolved
Committee agreed to note and support the Cabinet report's recommendations as follows: Delegates to, the Director of Development and Corporate Landlord and/or Director of Finance, the award of the JCT Design and Build Contract subject to project funding being secured. Approves the transfer of £2.1m S106 funding from provisional to approved capital budget for Phase 2 works. Approves the transfer of £335,470 from Didcot Garden Town capital funding to the Broadway project in respect of the community space works. Scrutiny committee acknowledged the efforts of the officers involved and made the following suggestions: · that risks related to this particular scheme including potential delays in receiving funding are considered · that a lessons learned review takes place.
Word for word from the decision South Oxfordshire published for this meeting.Source: democratic.southoxon.gov.uk
Report of the Director of Development and Corporate Landlord Author: Andrea Bridgeman – Project Manager Construction and Asset Management Telephone: [phone removed]
E-mail: [email protected] Cabinet member responsible: Cllr Tony Worgan Deputy Leader, plus Housing and Planning Development Management
116 –120 Broadway, Didcot – Cover Note for Scrutiny Committee Recommendation: That Scrutiny Committee:
1. Notes and supports the Cabinet report attached as confidential Appendix 2 that outlines for the following:
a. delegates to, the Director of Development & Corporate Landlord and/or Director of Finance, the award of the JCT Design and Build Contract subject to project funding being secured.
b. approves the transfer of £2.1m S106 funding from provisional to approved capital budget for Phase 2 works.
c. approves the transfer of £335,470 from Didcot Garden Town capital funding to the Broadway project in respect of the community space works.
1 Page 118 Agenda Item 11
Purpose of This Note 1. The report for 116-120 Broadway Redevelopment Project has been added to the Scrutiny Committee workplan. This cover report has been prepared in response to the request for further information.
2. Scrutiny Committee asked for an update on four points as set out in bold text below. Each point is followed by an officer response. In support of the responses the proposed confidential Cabinet report is attached as Appendix 2. The appendix is confidential as the tender process and Homes England bid are live.
3. Point 1 – Broadway development timeline
Please see table 1 for the breakdown of project milestones that have some contingency/float built into the dates outlined.
Table 1
Milestone Programme Caveat/Notes Submission of Homes 23 March 2026 Investment Partner information England Funding Bid required before decision can be made but review of bid content can begin Submission of Homes 10 April 2026 Funding decision process circa 6weeks England IPQ’s
Submission of 27 March 2026 Requested 24 and 25 March 2026 supporting information 2 April 2026 Requested 30 March 2026 requested
Cabinet Meeting 16 April 2026 Seeking approval to proceed with a Delegated Authority for issuing Notification of Contract Award if funding bid successful Homes England 29 May 2026 Earliest date expected Funding Decision
DA to Approve issuing 12 June 2026 If funding decision is positive and Notification of Contract received by 29 May 2026. Award Cannot proceed with DA until funding secured Notification of Award 15 June 2026 Cannot issue notification of award without funding secured Standstill Period Ends 29 June 2026 8 Working days
JCT Design & Build 30 June 2026 Once standstill period is complete Contracts Signed 30 June is the end of extended tender period Main contractor RIBA 25 September Circa 8-12 weeks Stage 4 Design 2026
2 Page 119 Agenda Item 11
Site Mobilisation 14 September Circa 2 weeks 2026 Start on Site 30 September Circa 45-week programme 2026 (excluding 2 weeks and Christmas and 2 weeks at Easter) Member site visit May 2027 Site visit to review progress, meet contractor
Practical Completion 14 October 2027 7 weeks float/contingency has been provided on the programme inclusive of Easter/Christmas shutdowns
4. Point 2 – Reasons the project has taken time to reach this stage
Works undertaken between 2019 and 2021 focused on identifying potential options for the site and securing the initial funding approval in February 2021 to procure the required specialist consultant professional services team.
Between 2021 and 2023 concept design options were developed and presented as part of the of the project brief that was finalised in April 2024 following Cabinet’s approval of Option 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.