Annual Delivery Plan Performance Report 2025/2026

Decided Scrutiny 3 papers

AI summaryScrutiny Committee reviewed the emerging Annual Delivery Plan End of Year Report 2025-26, covering 1 July 2025 to 31 March 2026. A fuller draft goes to Cabinet on 2 July 2026, with a designed public report due by September 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedScrutiny reviewed the emerging 2025-26 report
MoneyNo financial implicationsReport says no immediate financial implications
What happens nextCabinet review on 2 July 2026Designed public version due by September 2026
Who it affectsAll wardsReport covers council-wide delivery plan

What was decided

The committee reviewed the emerging Annual Delivery Plan End of Year Report for 2025-26, supported by two appendices of slides and itemised progress. Report P5, P39, P40

The committee considered slides and a data table summarising progress against the four strategic priorities, with a fuller narrative draft to follow. Report P23, P24

Why

The Annual Delivery Plan is the council's way of turning the Council Plan 2025-29 into concrete activity and outcomes, and the end of year report shows progress against it. Report P11, P12, P14

The 2025-26 reporting period was shortened to 1 July 2025 to 31 March 2026 so future plans can align with the budget setting cycle from 1 April. Report P16

A new Microsoft 365 based performance dashboard was introduced to track 96% of measures, with outstanding data expected from external sources. Report P20, P21

What happens next

A more developed draft report with full narrative will be submitted to South Cabinet for review on 2 July 2026. Report P24, P38

A fully designed public version of the report, with infographics, is intended for internal and public distribution by September 2026. Report P24

Options considered

  • Rejected: Cabinet approves the End of Year Report 2025-26. Recommendation is for Cabinet, not Scrutiny; Scrutiny only reviewed the emerging version Report P5, P38

Implications

  • Financial: No immediate financial implications; future budget proposals will follow usual processes and sit alongside the Medium Term Financial Plan. Report P25, P27
  • Legal: No anticipated legal implications; any project-level legal issues will be considered case by case. Report P28
  • Equalities: An Equality Impact Assessment for the Council Plan 2025-29 concluded a positive impact on groups with protected characteristics, rural communities and areas of deprivation. Report P31
  • Climate: Individual projects were assessed using the Climate Impact Assessment Tool; the high-level strategy was not assessed with the tool as agreed with the climate team. Report P29, P30
  • Risk: Wider factors such as local government reorganisation and funding reform may affect implementation of the Council Plan 2025-29 and will be addressed in the report narrative. Report P33, P35

Who and where

  • All wards across South Oxfordshire Report P3
  • Residents, councillors and stakeholders monitoring council performance Report P20

Timeline

  • 12 February 2025: Full Council adopted the Council Plan 2025-29 Report P10
  • July 2025: The 2025-26 Annual Delivery Plan was adopted Report P15
  • 1 July 2025 to 31 March 2026: Reporting period covered by the 2025-26 End of Year Report Report P16
  • 15 June 2026: Scrutiny Committee reviewed the emerging end of year report Report P4, P5
  • 2 July 2026: Developed draft report due at South Cabinet for review Report P4, P24
  • By September 2026: Designed public version of the report intended for distribution Report P24

Plain English for the jargon

  • Annual Delivery Plan: Yearly plan setting out key activities and outcomes that deliver the Council Plan's priorities.
  • Council Plan 2025-29: Strategic plan adopted by Full Council on 12 February 2025 setting out vision, priorities and objectives.
  • MTFP: Medium Term Financial Plan, the council's multi-year budgeting framework.
  • RAG ratings: Red, Amber, Green status indicators used on the performance dashboard to show progress against goals.
  • Climate Impact Assessment Tool: Tool used to assess climate and ecological impacts of individual council projects.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item158

Resolved

Committee reviewed the emerging Annual Delivery Plan End of Year Report for 2025-26.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Scrutiny Committee

Agenda Item 9

Scrutiny Report

Report of Director of Policy and Programmes Author: Aisling Passmore E-mail: [email protected] Wards affected: All

South Cabinet member responsible: Cllr Mike Giles E-mail: [email protected] To: SCRUTINY Date: 15 June 2026 To: CABINET Date: 2 July 2026

The Way Ahead: Annual Delivery Plan 2025-26 End of Year Report Recommendation to Scrutiny That committee review the emerging Annual Delivery Plan End of Year Report for 2025- 6 (Appendices 1 and 2).

Implications Financial Legal Climate and Equality and (further detail Ecological diversity within the report) No No No No

Signing off Anna Winship Nick Bennett Dom Lamb Ruth Lewin- officer Leigh

Page 12 Agenda Item 9

Purpose of report 1. To seek Cabinet approval for the proposed Annual Delivery Plan End of Year Report 2025-26, which seeks to review the activities undertaken to progress the priorities and objectives articulated in the Council Plan 2025-29.

Corporate Objectives 2. Following a comprehensive democratic and scrutiny process, the Council Plan 2025-29 was adopted by Full Council on 12 February 2025. The Council Plan 2025-29 sets out a vision, strategic priorities, and objectives for the council and forms part of the council’s policy framework.

3. The Annual Delivery Plan is underpinned by the Council Plan 2025-29 and sets out the key activities and outcomes that will enable the council to make progress towards achieving its ambitions either through direct delivery, in partnership, or exerting its influence as a local government body.

Background 4. The Council Plan 2025-29 sets the strategic context for the delivery and monitoring of council services in accordance with councillor intentions. The Annual Delivery Plan, aligned to the Council Plan, sets out the key activities and outcomes that will enable the council to make progress towards achieving its ambitions. Effectively, the Annual Delivery Plan articulates how the council will implement the strategic priorities and objectives set out in the Council Plan 2025-29 and forms the basis upon which progress will be monitored.

5. The Council Plan and Annual Delivery Plan reflect the financial landscape of the council and sit alongside the Medium Term Financial Plan (MTFP). For the Council Plan to serve as a credible strategic framework, it must balance ambition with financial responsibility, ensuring it is supported by appropriate budgeting.

6. The Annual Delivery Plan acts as a key component of the ‘golden thread’ linking the Council Plan to service delivery, and the End of Year Report is intended to offer an accessible means for members and the public to review progress made against the objectives which underpin the corporate priorities outlined in the Council Plan 2025-29.

Annual Delivery Plan and End of Year Report 7. Following adoption of the Council Plan 2025-29, each year the council will develop an Annual Delivery Plan setting out a range of activity and outcomes to support delivery of the priorities and objectives outlined in the Council Plan. The 2025-26 Annual Delivery Plan was adopted in July 2025 and was intended to cover a reporting period up to June 2026.

8. However, the reporting period of the 2026-27 Annual Delivery Plan was amended to run from 1 April 2026 to 31 March 2027. This change aimed to better align with the annual council budget setting process and therefore reflect any required changes close to the beginning of the financial year. This means the 2025-26 End of Year report covers the period from 1 July 2025 – 31 March 2026.

Page 13 Agenda Item 9

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Delivery Plan Performance Report 2025/2026Report 211 KB DownloadRead as text
PDF
Appendix 2Appendix 2 409 KB Download
PDF
South ADP End of Year Report Updated Copy 01 06Report 1.8 MB Download

At this meeting

Whole meeting

Who was there

7 of 17 attended
JO
Julian OsgathorpeCouncil Staff, expected
SC
Sam Casey-RerhayeChair, present
MK
Mocky KhanVice-Chair, apologies
KA
Ken ArlettCommittee Member, present
KG
Kate GregoryCommittee Member, present
AP
Andrea PowellCommittee Member, present
PR
Peter RamsdaleCommittee Member, present
DR
David RouaneCommittee Member, present
CT
Crispin ToppingCommittee Member, present
DT
David TurnerCommittee Member, expected
PB
Phil BarkerOfficer, expected
CB
Candida BasilioOfficer, expected

All 17 on the meeting page

On this subject at South Oxfordshire

Search all
  1. Annual Delivery Plan Performance Report 2025/2026This decision
  2. Annual Delivery Plan Performance Report 2025/2026Approved
  3. Housing Delivery Strategy Update and Action Plan 2026/27Noted
  4. The Way Ahead: Annual Delivery Plan 2026-27Approved
  5. Housing Delivery Strategy update & action planDecided
  6. Annual Delivery Plan 2026/202Agreed

More from South Oxfordshire Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Sep 2026 Minutes of the last meetingDecision (ICMD) relating to a contract extension, which due to timing meant that calling-in the decision would not be... Agreed Open
21 Sep 2026 Work schedule and dates for all South Scrutiny meetingsCommittee noted the work programme with the additional comments. Noted Open
21 Sep 2026 Financial Outturn 2025/26to note the overall outturn position of the council as well as the outturn of individual service areas. Noted Open
21 Sep 2026 Berinsfield Garden Village - Update and next stepsa) Scrutiny Committee supported the corporate position for Berinsfield Garden Village and the draft Berinsfield Garde... Decided Open
15 Jun 2026 Work schedule and dates for all South scrutiny meetingsCommittee noted the work programme with the additional comments. Noted Open