CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
South Oxfordshire District Council
Planning Committee, Wednesday 12 August 2026 at 6.00pm

P25/S3304/FUL - Land to the rear of 87-89 Lower Icknield Way, Chinnor, OX39 4EA

Approved Planning 4 papers

AI summarySouth Oxfordshire District Council Planning Committee approved plans for 9 detached dwellings on land behind 87-89 Lower Icknield Way, Chinnor, subject to 35 planning conditions. Community Infrastructure Levy applies.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedErection of 9 detached dwellings permitted
MoneyCIL applies, no sum givenCommunity Infrastructure Levy payable, amount not specified
What happens nextBegin within 3 yearsPre-commencement conditions must be discharged first
Who it affectsChinnor residents and applicantsBackland site within Chinnor Development Boundary

What was decided

Planning permission granted for 9 detached dwellings on a 0.42ha backland site, subject to 35 conditions covering drainage, ecology, highways, design and construction. Report P86

No affordable housing or retirement housing required, as the development is below the policy thresholds and Policy H9 does not apply to two separate developers and landowners. Report 7.28, 7.30

Community Infrastructure Levy applies to the development. Report 7.34, P86

Why

The principle of residential development was already established by the 13/06/2025 permission in principle for 8-9 dwellings, and the site lies within the Chinnor Development Boundary. Report 7.4, 7.5, 4.0

The density of about 21 dwellings per hectare, the two-storey scale, and the layout are in keeping with recent nearby developments at Walnut Tree Close, Braken Way/Rumpenny and the approved scheme at No.81. Report 7.8, 7.9, 7.11

Technical matters on drainage, trees, ecology, landscaping, access and parking were satisfactorily addressed, with conditions to secure remaining details. Report 8.0, 7.24, 7.25, 7.27

What happens next

The development must begin not later than three years after the date of permission. Report P90, P91

Pre-commencement conditions (drainage, habitat management, CEMP, tree protection, construction traffic management) must be submitted and approved before any work starts on site. Report P86, 7.35

Dwellings cannot be occupied until the access road connecting the site to Lower Icknield Way and the approved surface water drainage works are completed, and the foul and surface water compliance reports are submitted. Report P139, P133, P136

Options considered

  • Chosen: Approve planning permission with 35 conditions (officer recommendation). Site within development boundary, principle of residential development already established, technical matters satisfactorily addressed. Report P86, 8.0, 7.5
  • Rejected: Refuse planning permission (Chinnor Parish Council position). Parish Council objected on grounds of overdevelopment, lack of affordable housing, traffic impact and drainage concerns, but officers found no conflict with the development plan that could be defended at appeal. Report P13, 7.30, 7.24, 7.19

Implications

  • Financial: Community Infrastructure Levy will be payable; no affordable housing contribution is required as the scheme is below the policy threshold. Report 7.34, 7.28
  • Environment and climate: Statutory 10% Biodiversity Net Gain is required, with a Habitat Management and Monitoring Plan covering 30 years and integrated biodiversity enhancements secured by condition. Report 7.27, P102, P118
  • Environment and climate: Drainage strategy must meet National Standards for SuDS, with pre-commencement and pre-occupation drainage conditions to protect surrounding properties from surface water run-off. Report P94, P95, 7.24
  • Environment and climate: Air source heat pumps must meet MCS 020 certification or meet strict noise limits, and an EV charging point is required for each dwelling. Report P154, P160
  • Legal: Permitted development rights for extensions, roof extensions and outbuildings are withdrawn across all 9 plots to protect neighbouring amenity. Report P158, 7.17
  • Other: Construction hours restricted to 08:00-18:00 Monday to Friday and 08:00-13:00 on Saturdays, with no work on Sundays or public holidays. Report P164

Who and where

  • The applicant (Dacastello Limited) Report P2
  • Neighbouring residents of 85, 87, 89, 99, 101 and 103 Lower Icknield Way, 33 and 43 Braken Road, and 3, 5, 7 and 9 Rumpenny Report 1.3
  • Future occupiers of the 9 dwellings Report 7.18, 7.14
  • Chinnor Parish Council, which objected to the scheme Report P13

Timeline

  • 13/06/2025: Permission in principle granted for 8-9 dwellings under P25/S1113/PIP. Report 4.0
  • 23/04/2026: Planning appeal allowed for demolition of No.81 Lower Icknield Way and erection of 10 dwellings under P25/S1091/FUL. Report 4.0, P22
  • 12 August 2026: Planning Committee resolved to approve application P25/S3304/FUL subject to 35 conditions. Report P1, P86
  • Within 3 years of permission: Development must begin, otherwise the permission expires. Report P90

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure.
  • BNG: Biodiversity Net Gain, a measurable improvement in biodiversity resulting from development.
  • SuDS: Sustainable Drainage System, a way of managing surface water run-off close to source.
  • CEMP: Construction Environmental Management Plan, setting out how construction impacts on the environment are controlled.
  • HMMP: Habitat Management and Monitoring Plan, required to secure biodiversity net gain for 30 years.
  • LHA: Local Highway Authority, in this case Oxfordshire County Council.
  • MCS: Microgeneration Certification Scheme, the standard for low-carbon technology such as air source heat pumps.
  • PIP: Permission in Principle, a streamlined planning consent that establishes the principle of development.
  • CRNP: Chinnor Neighbourhood Plan Review 2023, which forms part of the development plan.
  • SOLP 2035: South Oxfordshire Local Plan 2035, the adopted local plan for the district.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item308

Resolved

to approve planning application P25/S3304/FUL subject to the following conditions: Commencement 3 years – Full Planning Permission Approved plans Surface water drainage works (pre-commencement) Foul drainage works (pre-commencement) Construction phase surface water management (pre-commencement) Habitat Management and Monitoring Plan (pre-commencement) Construction method statement (CEMP) (pre-commencement) Construction Traffic Management (pre-commencement) No change in levels (pre-commencement) Tree Protection (Detailed) (pre-commencement) Integrated Biodiversity Enhancements (prior to slab level) Cycle Parking Facilities (pre-slab level) Details of replacement Priority Habitat hedgerow (prior to slab) Hardsurfacing (pre-slab level) Boundary walls & fences (pre-slab level) Schedule of Materials (pre-slab level) Construction phase surface water drainage (pre-occupation) Construction phase foul water drainage (pre-occupation) Roads and footpaths (prior to occupation) Energy Statement Verification (prior to occupation) Lighting for bats (prior to installation) Obscure glazing (implementation) Rooflights (specified cill level) (implementation) Parking & Manoeuvring Areas Retained (implementation) Electric Vehicles Charging Point (implementation) Soft landscaping (implementation) Withdrawal of P.D. (extensions, roof extensions and outbuildings) (implementation) Air Source Heat Pump(s) ... view the full minutes text for item 308.
Word for word from the decision South Oxfordshire published for this meeting. Source: democratic.southoxon.gov.uk

Follow this further

Built from South Oxfordshire's papers

What the report saysPro

Report to Planning Committee

Agenda Item 8 South Oxfordshire District Council – Committee Report – 12 August 2026

APPLICATION NO. P25/S3304/FUL SITE Land to the rear of 87-89 Lower Icknield Way, Chinnor, OX39 4EA PROPOSAL Erection of 9 detached dwellings. APPLICANT Dacastello Limited APPLICATION TYPE Full Application PARISH Chinnor WARD MEMBERS Ed Sadler & Ali Gordon-Creed OFFICER Paul Lucas

1.0INTRODUCTION 1.1 This report sets out the justification for officers’ recommendation to grant planning permission having regard to the development plan and any other material planning considerations. The application is referred to planning committee due to the objection from Chinnor Parish Council.

1.2The application site comprises a 0.42ha parcel of undeveloped grassland subdivided into two parts by a post and rail fence with the two halves connected to the rear gardens of 87 and 89 Lower Icknield Way.

1.3The site is connected to the highway by taking access through No.81 Lower Icknield Way, which is an approved access under planning permission P25/S1091/FUL for the demolition of No.81 and erection of ten dwellings. The site also borders the residential plots of 85, 87, 89, 99, 101 and 103 Lower Icknield Way to the south-east, 33 and 43 Braken Road to the north-east and 3, 5, 7 and 9 Rumpenny to the north-west. The site contains several mature trees and hedgerows close to the site boundaries. The site does not contain any special designations. The application site is shown on the location plan

below:

2.0Proposal

Page 59 South Oxfordshire District Council – Committee Report – 12 August 2026

2.1The application seeks planning permission for the erection of nine dwellings, as shown on the current plans and as described on the supporting documents. The application was amended to change Plot 4 from a house to a bungalow, to provide additional soft landscaping and to make alterations to the proposed drainage strategy and layout.

2.2Extracts of plans accompanying the application are attached at Appendix B. All plans and supporting technical documents accompanying the application are available to view online on the Council’s website, www.southoxon.gov.uk.

3.0SUMMARY OF CONSULTATIONS & REPRESENTATIONS 3.1 The application was publicised in accordance with the relevant procedures for the type of application.

3.2A summary is provided of the key comments made by consultees and these are expanded on within the main body of the report where necessary. Full responses can be viewed online on the Council’s website.

Consultees Chinnor Parish Council - Objection This scheme creates an overly dense cluster of market-priced homes and fails to address Chinnor’s housing needs or comply with its Neighbourhood Plan. This site is not included in the Chinnor Neighbourhood Plan for development. In addition, it creates further issues with more traffic entering and exiting the B4009 with no continuous pavements for pedestrians or safe facilities for cyclists. The stated link with the Drovers Way development creates a development of some 18/19 dwellings which has been separated out to avoid the requirement for affordable housing. This is unacceptable. The latest amendments to the original application is following the trend of those proposed on Drovers Way by reducing the height of a single property and will do little to repel the visual intrusion of this development on adjacent properties. There are no proposals to meet the requirements within the CNP for 10% biodiversity gain on site. There is much concern that run-off water from this site will impact on properties which surround this site particularly in the north-eastern corner which is where the proposed bungalow on plot 4 will be situated. Any drainage works are likely to direct excess water onto the Chiltern View development. The Parish Council objects to the proposed amendments and upholds its original decision to object to this application.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix BAppendix B 4.8 MB Download
PDF
Appendix BAppendix B 4.8 MB Download
PDF
P25/S3304/FUL: Land to the rear of 87-89 Lower Icknield Way, Chinnor, OX39 4EAReport 317 KB DownloadRead as text
PDF
P25/S3304/FUL: Land to the rear of 87-89 Lower Icknield Way, Chinnor, OX39 4EAReport 317 KB Download

At this meeting

Whole meeting

Who was there

16 of 46 attended
DB
David BrethertonChair, present
JN
James NormanVice-Chair, present
KA
Ken ArlettCommittee Member, present
TB
Tim BearderCommittee Member, expected
PD
Peter DragonettiCommittee Member, present
KK
Katharine Keats-RohanCommittee Member, present
AM
Axel MacdonaldCommittee Member, present
PR
Peter RamsdaleCommittee Member, apologies
JR
Jo RobbCommittee Member, apologies
ES
Ed SadlerCommittee Member, present
CT
Crispin ToppingCommittee Member, present
NB
Nick BennettCouncil Staff, expected

All 46 on the meeting page

On this subject at South Oxfordshire

Search all
  1. P25/S3304/FUL - Land to the rear of 87-89 Lower Icknield Way, Chinnor, OX39 4EAThis decision
  2. P25/S0350/FUL - Land to the rear of Pennyhill Woodlands Road Harpsden, RG9 4AADecided
  3. P24/S1336/FUL - Land north-west of Nuneham Courteney situated to the west of the A4074 north of Upper Farm and south of Lower FarmDeferred
  4. P25/S0329/FUL - Pennyhill, Woodlands Road, Harpsden, RG9 4AAApproved
  5. P25/S1415/FUL and P25/S1416/LB - Morland House, Station Road, Chinnor, OX39 4QAApproved
  6. P24/S1287/FUL - Land to the rear of The Paddocks, Lower Icknield Way, Chinnor, OX39 4GRAgreed

More from South Oxfordshire Planning Committee

All decisions
MeetingDecisionOutcome
12 Aug 2026 Minutes of the previous meetingRESOLVED : to approve the minutes of the meeting held on 30 August 2026 as a correct record and agree that the Chair ... Approved Open
12 Aug 2026 P25/S0350/FUL - Land to the rear of Pennyhill Woodlands Road Harpsden, RG9 4AAto delegate to the Director of Planning, in consultation with the Chair of Planning Committee, to grant planning perm... Decided Open
30 Jul 2026 Minutes of the previous meetingRESOLVED : to approve the minutes of the meeting held on 15 July 2026 as a correct record and agree that the Chair si... Approved Open
30 Jul 2026 P25/S3380/FUL - Breach Farm, Wheatley Road, Stanton St John, OX33 1FGto approve planning application P25/S3380/FUL subject to the following conditions: Commencement 3 years – Full Planni... Approved Open
30 Jul 2026 P25/S0273/HH - Yew Tree Cottage, The Street, Ewelme, OX10 6HQto approve planning application P25/S0273/HH subject to the following conditions: Commencement 3 years – Full Plannin... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies