Resolved
RESOLVED – That the Audit and Standards Committee noted the contents of the report.
Audit, Standards and Risk Committee noted this item on Thursday 13 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Audit and Standards Committee noted the contents of the report.
This report sets out the process leading up to the award of contract for the provision of Internal Audit services to the Mayoral Combined Authority group.
Freedom of Information and Schedule 12A of the Local Government Act 1972
Under the Freedom of Information Act this paper and any appendices will be made available under the Combined Authority Publication Scheme. This scheme commits the Authority to make information about how decisions are made available to the public as part of its normal business activities.
The Audit and Standards Committee is asked to note the contents of this report.
1. Introduction
1.1At its previous meeting on 18 April 2019, the Committee requested that a report be presented at the June Audit and Standards Committee detailing the appointment process undertaken for the provision of Internal Audit Services for the SCR Combined Authority and South Yorkshire PTE.
This contract was jointly procured with the Mayoral Combined Authority, but SYPTE entered into the actual contract.
On 31 January 2019, the SYPTE Executive Board approved the award of the contract for the provision of Internal Audit services to Grant Thornton UK LLPE.
The contract value is up to £93,750 per annum across the MCA Group, and officially commenced on 1 April 2019 for an initial 3-year period, with the possibility of an extension for up to 2 further years.
It should be noted that the contract provides sufficient flexibility to reduce and/or increase the number of days by 62.5 (i.e. 25%) in year 1 and in subsequent years. 2. Proposal and justification
2.1The contract with BMBC was awarded following an EU tender process in 2015. SYPTE are subject to both the EU procurement rules and the requirements of their Contract Standing Orders. The contract was awarded in 2015 for a period of 2 years and was subsequently extended by 1 year to allow time for the MCA Group to determine whether a joint audit approach was desirable.
2.2SYPTE and MCA are legally required to follow the procurement rules when awarding service contracts to third party entities. The Principal Solicitor confirmed this position and consulted with the Chair of SYPTE’s Audit & Risk Committee in August 2018.
2.3In Q3 2018/19, SCR Statutory Officers agreed that there was a need to ensure that the MCA group renewed the contract for Internal Audit in 2019/20, given that the existing contract was due to expire in March 2019.
2.4Statutory Officers also agreed that it was important to ensure that the Internal Audit service looked across both organisations to realise efficiencies, developing a joint Audit Plan and reporting to both Audit Committees.
2.5Having run the procurement process for the existing contract, it was further agreed that the SYPTE procurement team would lead on the procurement process for the contract.
2.6Consultation on the specification for the new contract took place between SYPTE and the Chair of SYPTE’s Audit & Risk Committee in November 2018. The specification was then included in the Invitation to Tender (ITT) document which was openly advertised on SYPTE’s website.
2.7The ITT sought a Daily Commercial Rate for the delivery of a joint Audit Plan for the MCA and PTE utilising the days available/contracted for in the most efficient manner and concentrating on the required main controls and the highest risk areas, subject to a maximum of 250 days activity per annum.
2.8The award criteria for this contract was the most economically advantageous tender as set out in the tender documentation. The weighting to be applied for tender evaluation was pre- determined at 50% quality and 50% price.
2.9Five tender submissions were received from the organisations listed below, and were evaluated by the Interim Head of Financial Services of the PTE and the SCR Senior Finance Manager: • West Yorkshire Combined Authority (WYCA) • Mazars LLP • Barnsley MBC • Grant Thornton UK LLP • TIAA Ltd
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Procurement of Internal Audit ProviderReport | 162 KB | DownloadRead as text |
Follow Audit, Standards and Risk Committee at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jul 2026 | Appointment of Chair and Vice-Chair, appointments to Transport Risk Working GroupThat Councillor Mike Levery be appointed Chair and David Phillips be appointed Vice-Chair of the Audit, Standards and... | Decided | Open |
| 9 Jul 2026 | Questions from Members of the PublicThat the questions and responses be noted. | Noted | Open |
| 9 Jul 2026 | Terms of ReferenceThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Health and Safety UpdateThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Bus Franchising UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.