It was agreed a final decision on advisory attendance should be taken once the Board has become more established. Consideration was given to whether the Board’s sphere of interest should extend beyond the scope of the housing investment programme. It was agreed it should noting the inclusion in the terms of reference ‘to shape future policy development and priorities on issues related to housing’. The paper also proposed the schedule of dates for future meetings. RESOLVED, that the Board: 1. Notes the approved governance arrangements. 2. Notes the proposed future scheduling of Housing Board meetings. 3. Notes the potential to engage a wider membership on an advisory basis
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
This report summarises for Housing Board Members the approved governance arrangements for the Housing Board, approved by the Mayoral Combined Authority and the Local Enterprise Partnership. The paper also proposes dates for future meetings.
Freedom of Information
Thematic Board Papers and any appendices will be made available under the Combined Authority Publication Scheme. This scheme commits the Authority to make information about how decisions are made available to the public as part of its normal business activities.
Recommendations
Board members are asked to:
1. note the approved governance arrangements and clarify any issues, 2. note the proposed future scheduling of Housing Board meetings, 3. note the potential to engage a wider membership on an advisory basis and consider how this may be approached
1. Introduction
1.1Following consultation with partners and a review of the models in other mayoral combined authorities, the MCA and LEP at their meetings 17th December 2018 and 14th January respectively approved strengthen governance arrangements. These arrangements have been designed to create more efficient, effective and transparent decision-making processes. The MCA Constitution has been amended to reflect these new arrangements. From the 1st April 2019 five thematic boards, with appropriate delegations to complement their role in implementing policy and programmes more transparently, came into effect.
2. Proposal and justification
2.1Governance Model Appendix 1 to this report attaches the approved governance paper for Board Members to review and discuss.
2.2Terms of Reference Appendix 2 of this report includes the terms of reference for the Housing Board to review and discuss. 2.3 Meeting Schedule This paper proposes that the Housing Board meets during week 4 of the MCA 8 week cycle. This will allow any decisions requiring escalation to the MCA, due to the value exceeding the delegation, to progress through the decision-making process in a timely manner. The proposed dates are suggested below
Proposed Housing Board dates (week 4 of MCA Date (week 8 of the 8-week cycle) the 8-week cycle) 26/08/19 – 30/08/19 23/09/19 21/10/19 – 25/10/19 18/11/19 *30/12/19 - 03/01/20 27/01/20 24/02/20 – 28/02/20 23/03/20 04/05/20 – 08/05/20 01/06/20 29/06/20 – 03/07/20 27/07/20 24/08/20 – 28/08/20 21/09/20 19/10/20 – 23/10/20 16/11/20
*potentially move to week 2 or to week 5 to avoid the Christmas and new year period.
2.4Advisory Membership The decision-making Board Members are detailed in Appendix 1, section 2.3. The membership of the Board will comprise two leaders, with one from the constituent councils and one from the non-constituent councils, a member of each of the remaining councils (to be nominated by the respective authority) and two private sector LEP Board members, as well as a lead chief executive from a different authority to the leader.
There is the potential for Board Members to develop a broader advisory network through the engagement of appropriate organisations. This advisory network does not necessarily require attendance at the Thematic Board but could be through other mechanisms. Board Members are asked to consider this matter to start to develop their preferred approach.
3. Consideration of alternative approaches
3.1There is no discretion to change governance arrangements, as these have been approved by both the MCA and the LEP but to note it is planned that there will be a review of arrangements after 6 months of meetings.
4. Implications
4.1Financial
Thematic Boards have the authority to approve agreed pipeline projects and schemes with a value of less than £2m. This provides consistency with the limits previously in place for the Housing Investment Board. The Thematic Boards are also able to accept tenders and quotations for the supply of goods, materials and services up to a limit of £200,000.
4.2Legal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow SCR - Housing Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Previous MeetingIt was agreed that the minutes of the previous meeting are an accurate record and may be signed by the representative...
SCR Renewal Action Plan ImplementationRESOLVED – That Board Members considered the SCR Renewal Action Plan, in order to shape and develop the actions being...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.