RESOLVED, that the Board: 1. Notes the background information on the development of the Supertram network and its current performance 2. Notes the progress made to date on the development of the Outline Business Case (OBC) seeking funding from government for the renewal of the asset. 3. Notes the options being considered, the financial aspects of the options described and the approach to identifying and securing a local contribution to the capital costs.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
To advise Board members of progress to date on the operation and long-term renewal of the Supertram asset in South Yorkshire.
Freedom of Information
A – the paper will be available under the Combined Authority Publication Scheme
This paper may be released under a Freedom of Information request. In this section, it must be clear if the paper has any exemption under Part II of the Freedom of Information Act 2000 (the report author must specify which exemption applies and why).
Recommendations
Board members are asked to:
1. Note the background information on the development of the Supertram network and its current performance. 2. Note the progress made to date on the development of the Outline Business Case (OBC) seeking funding from government for the renewal of the asset. 3. Give their views as to the options being considered, the financial aspects of the options described and the approach to identifying and securing a local contribution to the capital costs.
1. Introduction
1.1For over 20 years, Supertram has been connecting high numbers of people to jobs, education, shopping and leisure in Sheffield and beyond. Making over 12 million passenger journeys a year, it plays an important role in the wider public transport network within the Region and is recognised as an attractive, reliable and efficient mode of travel. The tram system reduces congestion, helps improve air quality, and potentially could play an important part in future plans to better connect residents and businesses to our urban centres and major housing, retail, leisure and employment sites within the Sheffield City Region.
1.2A 2014 study found that after more than 20 years of continuous operation, parts of the existing tram network and vehicles are approaching the end of their working life. Whilst ongoing general maintenance costs are paid for by the current tram operator (Stagecoach), there is no funding currently in place for the long-term renewal of the system. Investment is therefore needed to allow the Supertram network to operate for at least another 30 years, and central government funding will be required to support this.
1.3In October 2018, a tram-train pilot service commenced operation between Sheffield Cathedral and Rotherham Parkgate. This pilot (the first of its kind in the UK), funded by DfT, is testing the use of tram-train technology on a light rail system to evaluate its potential use elsewhere. It makes use of a shared section of network rail track between Tinsley and Rotherham Parkgate, running on the same tracks as heavy rail services. Three services per hour operate between Sheffield and Rotherham, with stops at Rotherham Central and Parkgate.
2. Proposal and justification
2.1The Supertram network plays a fundamental role in supporting the economy and residents of South Yorkshire. It provides a key means of connectivity to allow people to travel to work, education and for leisure purposes. In doing so, it contributes to reducing traffic congestion and improving air quality, providing a zero-emissions transport network capable of moving customers within the region.
2.2The current network commenced construction in 1991 and opened for use in 1994. The asset has subsequently worn over time and as it now approaches the end of its economic life it is in need of investment to allow the network to continue beyond March 2024, the date at which the current concession operation ends with Stagecoach.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow SCR - Transport Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Dearne Valley Regeneration RouteRESOLVED – That the Board: a) Note the progress made to date in developing the Strategic Outline Business Case. b) Su...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.