To provide the Transport Board with an update on progress and issues associated with the SCR Mass Transit (SCR MT) and related projects.
Freedom of Information
This paper will be made available under the Combined Authority Publication Scheme. This scheme commits the Authority to make information about how decisions are made available to the public as part of its normal business activities.
That Transport Board notes the contents of the report and provides any feedback, comments or concerns they have to the Project Team.
1. Introduction
1.1At Transport Board on 19 July, Board members were provided with a summary of the need for renewal works to ensure that the existing Supertram network can continue to be used safely beyond the end of the current concession agreement in 2024.
The paper provided details of the cost implications of renewal, as well as alternatives for phased renewal activity, as well as do nothing and closure options. Details were also provided on the need for the region to secure a local contribution to the capital costs of works to support the application for grant funding from DfT.
1.2This report provides and update on the latest progress made on the production of the Outline Business Case (OBC), submission for funding, local contribution and capital costs.
2. Proposal and justification
2.1Local Contributions and DfT Funding
To date, sources for approximately £14M have been found. This equates to 50% of what is needed if a 7% local contribution is needed (the actual percentage of the local contribution has not been agreed with DfT but current discussions are in the range 7% to 15%). 7% is also the local contribution made by Nexus (North East Combined Authority) to the renewal of their Metro light rail network vehicle fleet.
The latest on potential sources is as follows:
• A further £3.5M has been earmarked from revaluation reserves to add to £11M revenue resources already identified. • Local Growth Fund (LGF) to 2021 is nearly fully committed and therefore almost certainly ruled out. • Following discussions with SCC, they are looking at an additional contribution to the Local Contribution to recognise that they are one of the primary beneficiaries of the network. • The use of other sources of external funding, including a passenger fare supplement, continues to be investigated.
Work on proposing that previous expenditure could be used as match, or as part of a case to reduce the percentage local contribution, continues. This includes the capital costs borne by the region to date to undertake re-railing work between 2013 and 2020. A summary of the funding for the three rail replacement contracts we have awarded to date is given below:
Item Notes EFC of works (3 contracts to date) £42M (1) SYSL Capital Contribution £1M DfT (pinch point and Tram-Train) £12.2M ITB £3M SYPTE/SYSL joint funding (QUEST) £0.28M Borrowing £15.1M (2) SYSL revenue £10.1M (3) TOTAL £42M
(1) Does not include revenue lost during works. Post 2024 this will be our responsibility (captured in Grant Thornton operating cost model for Mass Transit) (2) Amount borrowed, not total cost of borrowing. (3) Revenue support including cost of providing bus replacement services
Not having an agreed position on local contribution means it is no longer possible to seek full approval for submission of the OBC to DfT in October 2019. This is because the submission needs a firm commitment to the Local Contributions which in turn would need to be approved by the MCA at the September 2019 meeting. An update on the position regarding DfT funding and the plan to resolve the local contributions challenge will be given at a future meeting.
2.2Programme to Submission
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SCR Mass Transit Programme Progress UpdateReport | 178 KB | DownloadRead as text |
Follow SCR - Transport Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Sep 2020 | Minutes of the Previous MeetingRESOLVED – That the minutes of the meeting of the Board held on 3 rd July 2020 be agreed as a true record. | Agreed | Open |
| 4 Sep 2020 | Bus Review Response WorkRESOLVED – That the Board approve the approach to delivering the Bus Review Response work programme through the work ... | Approved | Open |
| 4 Sep 2020 | Integrated Rail Plan For The Midlands And The NorthRESOLVED – That the Board approve the Rail Needs Prospectus, attached to the report, for submission to the Department... | Approved | Open |
| 4 Sep 2020 | Roads Implementation Plan And Approach To The Key Route NetworkRESOLVED – That the Board: a) Note the work undertaken to date with the Local Authorities to develop the SCR Roads Im... | Noted | Open |
| 4 Sep 2020 | Dearne Valley Regeneration RouteRESOLVED – That the Board: a) Note the progress made to date in developing the Strategic Outline Business Case. b) Su... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.