Local Growth Funding (LGF) and Programme Demand

Decided Committee 3 papers

Local Enterprise Partnership decided this item on Monday 9 September 2019. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED, that the Board: Notes the scale of the pipeline and options available to address the potential overprogramming position. Notes the contents of the Q1 2019/20 DELTA submission.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to Local Enterprise Partnership

Purpose of report

This paper provides LEP Board with an overview of the current LFG programme commitments and the scale of projects in the over-programmed pipeline.

Thematic Priority

Cross cutting theme.

Freedom of Information and Schedule 12A of the Local Government Act 1972

The paper will be available under the SCR Publication Scheme

Recommendations

LEP Board are asked to

1. Consider the scale of the pipeline and discuss options to address the potential over- programming position. 2. Note the contents of the Q1 2019/20 DELTA submission.

1. Introduction

1.1LGF is a 6 year, £360m funding programme secured through three rounds of Local Growth Fund bids. 2019/20 is the fifth and penultimate year of funding. Some investment made in the early years of the programme have now repaid loan funding back to the programme which has increased the total value of available programme funding to £378m.

1.2In the first four years of delivery £239m has been spent (defrayed). A further £49m is committed to projects currently in contract and a further £17m has been approved for projects which are in the process of satisfying contract conditions. The total combined value of approved projects and spend to date is therefore £305m.

1.3The LGF grant allocation includes a ringfenced amount of £40.5m for a major transport project which is retained for separate approval by the DfT, this funding cannot be utilised for other projects. 1.4 The level of funding remaining available for LGF projects across all thematic areas (the programme headroom) is now £32.4m. The programme spend and funding profile is set out in Appendix A.

1.5All funding needs to be fully spend (defrayed) by 31st March 2021.

2. Proposal and justification

2.1When the 2019/20 budget was approved by the MCA in March 2019 the pipeline of projects indicated that there was potential over-programming of up to £24.4m.

As projects have developed some cost estimates have increased and a number of new projects have come forward seeking funding. As a result of these changes the current combined value of project in the pipeline (including the retained major) has increase to £111.5m and therefore the potential over-programming has increased to £38.1m.

2.2During the 2017/18 financial year an independent audit was undertaken of all projects seeking an LGF contribution greater than £1m. A series of milestones, as set by the scheme promoters, were agreed by the LEP Board in September 2018. Projects not meeting these milestones would initially have the funding allocations “un-ringfenced”. If a project is no longer able to complete delivery within the LGF funding timescales funding may ultimately be decommitted from this programme.

2.3In the months following the LEP review the scale and pace of project approvals increased significantly and many of the projects have now entered into contract, some projects however remain in the pipeline. All projects in the pipeline have missed some of the agreed milestones and therefore all projects are now in a competitive programme.

2.4The current profile of project approvals and the remaining pipeline is set out below by theme;

Executive Approved Pipeline Total Comments Board Business £46m £21.1m £67.1m This is £15.1m above the Growth notional allocation and it is unlikely that all projects will land in the region or be able to complete works by 31st March 2021. Housing £10.0m £0.21m £10.21m £4.05m of the £10m housing funding is currently committed to schemes, the remaining £6m is held in the housing fund for pipeline schemes. Infrastructure £197.2m £23.1m £220.3m This includes several highways schemes designed to unlock development space for employment and housing Skills and £18.3m £17.5m £35.8m This is £7.8m above the notional Employment allocation and it is unlike that all projects will be able to complete works by 31st March 2021. Transport £28.5m £49m £77.5m This includes the £40.5m retained major transport project. Total £300.0m £110.9m £410.9m

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 274 KB Download
PDF
Appendix BAppendix B 171 KB Download
PDF
Local Growth Funding (LGF) and Programme DemandReport 174 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 33 attended
JM
James MuirChair, present
NB
Nigel BrewsterVice-Chair, apologies
LB
Laura BennettCommittee Member, apologies
AG
Alexa Greaves - Small Business ChampionCommittee Member, present
PC
Professor Chris HusbandsCommittee Member, present
PK
Peter KennanCommittee Member, present
TK
Tanwer KhanCommittee Member, present
NM
Neil MacDonaldCommittee Member, present
OM
Owen MichaelsonCommittee Member, present
JM
Julia Muir - Equality & Diversity ChampionCommittee Member, apologies
LN
Lucy NicksonCommittee Member, present
PS
Philippa SandersonCommittee Member, present

All 33 on the meeting page

On this subject at South Yorkshire Mayoral Combined Authority

Search all
  1. Local Growth Funding (LGF) and Programme DemandThis decision
  2. Local Growth PlanNoted
  3. Local Growth PlanNoted
  4. Local Growth Fund Update (Year end 2020/21 and 2021/22 Programme Activity)Noted
  5. Local Growth Fund (LGF) ProgrammeApproved
  6. Local Growth Fund (LGF) ProgrammeApproved

More from South Yorkshire Mayoral Combined Authority Local Enterprise Partnership

All decisions
MeetingDecisionOutcome
13 Jul 2023 Notes and Action Log of Last MeetingThat the notes of the meeting held on 18 th May be agreed as a true record. to note updates to the action log. Agreed Open
13 Jul 2023 South Yorkshire's Investment ZoneThat the Board note the update. Noted Open
13 Jul 2023 The South Yorkshire EconomyTo note the update. Noted Open
13 Jul 2023 LEP Annual Report and Governance ChangesRESOLVED : That the Board: 1. Approve the Annual Report as attached at Appendix A. 2. Note the new business engagemen... Approved Open
13 Jul 2023 Development of a Northern Pan Regional PartnershipThat the Board: 1. Note the Government’s intention to establish a formal Northern Pan Regional Partnership (PRP) and ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies