Resolved
RESOLVED, that the Board: Approve the removal of four schemes from the pipeline thus reducing the over-programming position. Approve the return of one scheme with funding approval to the pipeline to increase the available headroom.
Local Enterprise Partnership approved this item on Thursday 16 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED, that the Board: Approve the removal of four schemes from the pipeline thus reducing the over-programming position. Approve the return of one scheme with funding approval to the pipeline to increase the available headroom.
This report updates the LEP Board of the current LGF programme position, the available headroom and the current level of over programming. The report makes recommendations to reduce the number of schemes in the pipeline thus reducing the over programming and also recommends actions are endorsed to be progressed with schemes in contract or with funding approval that are not progressing in accordance with the milestones agreed and are deemed to have a high risk of slipping beyond the life of the LGF programme.
Thematic Priority
Cross cutting - financial
Freedom of Information and Schedule 12A of the Local Government Act 1972
The paper will be available under the SCR Publication Scheme
LEP Board are asked to consider the review of the LGF programme, including the available headroom and over programming position and agree the steps to be undertaken:
1. Removal of four schemes from the pipeline thus reducing the over-programming position; 2. Return of one scheme with funding approval to the pipeline to increase the available headroom;
1. Introduction
1.1LGF is a 6 year, £360m funding programme secured through three rounds of Local Growth Fund bids. 2019/20 is the fifth and penultimate year of funding. Some investment made in the early years of the programme have now repaid loan funding back to the programme which has increased the total value of available programme funding to £377.6m. 1.2 The programme position at the November 2019 board was headroom of £32m, however 3 projects with a value of £22.5m were subsequently approved at the MCA Board in November leaving available headroom of £9.5m. The LEP Board made the decision to retain this level of funding for inward investment activity, whilst requesting that each scheme in the programme continued to be reviewed to identify opportunities to reduce the pipeline of schemes and / or increase available headroom. 1.3 A line by line review of all schemes has been undertaken and all schemes with approval but not yet in contract have been assessed against their readiness to meet the conditions associated with their approval, this exercise has resulted in a reduction in the pipeline and the approvals as some schemes have voluntarily withdrawn their scheme. 1.4 The programme position is: • £123.1m of projects have now completed • £159.2m of projects are currently in delivery • £26.3m has been approved for projects which are in the process of satisfying conditions prior to contract. Cumulatively this gives a total commitment of £308.6m There are, in addition, two ringfenced schemes within the programme pipeline totalling a further £45.1m. Collectively the total commitment is £353.7m When set against the total programme value of £377.6, the available programme headroom is £23.9m. 1.5 The pipeline of schemes is currently £58,457,116 leading to an over programming position of £34.6m. 2. Proposal and justification
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Full programme listAppendix A | 179 KB | Download |
PDF |
Local Growth Fund and Programme DemandReport | 161 KB | DownloadRead as text |
Follow Local Enterprise Partnership at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Notes and Action Log of Last MeetingThat the notes of the meeting held on 18 th May be agreed as a true record. to note updates to the action log. | Agreed | Open |
| 13 Jul 2023 | South Yorkshire's Investment ZoneThat the Board note the update. | Noted | Open |
| 13 Jul 2023 | The South Yorkshire EconomyTo note the update. | Noted | Open |
| 13 Jul 2023 | LEP Annual Report and Governance ChangesRESOLVED : That the Board: 1. Approve the Annual Report as attached at Appendix A. 2. Note the new business engagemen... | Approved | Open |
| 13 Jul 2023 | Development of a Northern Pan Regional PartnershipThat the Board: 1. Note the Government’s intention to establish a formal Northern Pan Regional Partnership (PRP) and ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.