Resolved
RESOLVED, that the Committee notes the progress of 2019/20 audit activity undertaken by Grant Thornton for: Joint SCR & SYPTE audits, SCR MCA audits and SYPTE audits.
Audit, Standards and Risk Committee decided this item on Thursday 23 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED, that the Committee notes the progress of 2019/20 audit activity undertaken by Grant Thornton for: Joint SCR & SYPTE audits, SCR MCA audits and SYPTE audits.
Audit & Standards Committee
23rd January 2020
Group Internal Audit Plan Progress Report
Purpose
This report provides an update on the progress of the 2019/20 Group Internal Audit Plan.
Freedom of Information & Section 12A of the Local Government Act 1972
Under the Freedom of Information Act this paper and any appendices will be made available under the Mayoral Combined Authority Publication Scheme. This scheme commits the Authority to make information about how decisions are made available to the public as part of its normal business activities. Recommendations
The Audit and Standards Committee are asked to note the progress of 2019/20 audit activity undertaken by Grant Thornton for:
• Joint SCR & SYPTE audits • SCR MCA audits • SYPTE audits Commercial in confidence
Internal Audit Progress Report Sheffield City Region Mayoral Combined Authority and South Yorkshire Passenger Transport Executive
January 2020
© 2020 Grant Thornton UK LLP | Progress Report | January 2020 Commercial in confidence
Introduction & headlines Purpose Resourcing This report provides an update on progress against the 2019/20 internal audit plan. We We confirm that we have sufficient internal audit team members available to deliver the have delivered 38 of the 69 days in respect of SCRMCA reviews and a total of 127 of the internal audit plan on time. We will flex the plan where needed for emerging priorities and 250 days in the joint audit plan, a full detailed breakdown can be found at pages 3 and 4. to accommodate timescales requested by management.
Work in progress Changes to the audit plan since the last meeting subject to approval As at the date of preparing this report we are currently working on the following reviews: There has been no further changes to the Audit Plan since the last Audit Committee. ▪ Core Financial Controls ▪ Risk Management Additional work undertaken outside of the audit plan ▪ Information Governance / GDPR There has been no work undertaken outside of the Audit Plan. ▪ Resource Management / HR systems review ▪ Programme Management
Scoping and planning has also commenced in respect of the following reviews:
▪ Governance ▪ Back Office Transformation
© 2020 Grant Thornton UK LLP | Progress Report | January 2020 Commercial in confidence
Progress against 2019/20 Internal Audit Plan Mgt Scope Fieldw Draft Final Planne APB Fieldwork Debrief respons Days Audit Start date Meeting ork report report d days agreed completed held e used held started sent sent received Annual Reviews for HOIA opinion and Joint Authority Audits Core financial controls 30 Quarter 3 6 Risk Management 14 Quarter 4 11 Governance 14 Quarter 4 1 Information Governance / GDPR 15 Quarter 4 10 Capital Programme 12 Quarter 4 1 Sub-total 85 29 Sheffield City Region Mayoral Combined Authority Resource Management / HR Systems 12 Quarter 2 10
Back Office Transformation 12 Quarter 3 1
Grant Claims 6 Quarter 2 6 Programme Management 12 Quarter 3 8 Adult Education Budget 4 Quarter 3 0 Follow up of recommendations 5 Ongoing 1 Attendance at Audit Committee & other 18 12 client meetings Sub-total 69 38
© 2020 Grant Thornton UK LLP | Progress Report | January 2020 Commercial in confidence
Progress against 2019/20 Internal Audit Plan Scope Draft Mgt Final Planned APB Fieldwork Fieldwork Debrief Days Audit Start date meeting report response report days agreed started completed held used held sent received sent South Yorkshire Passenger Transport Executive Ticketing and Concessions 16 Quarter 3 4 Grant Claims 3 Quarter 3 3 Project Management 12 Quarter 2 12 Asset Management 15 Quarter 2 15 Assurance Mapping 8 Quarter 1 4 Air Quality and Environment 8 Quarter 2 6 Follow up of recommendations 5 Ongoing 2
Attendance at Audit Committee & 20 Ongoing 14 other client meetings
Sub-total 87 60
Contingency 9 0
Total 250 127
© 2020 Grant Thornton UK LLP | Progress Report | January 2020 © 2020 Grant Thornton UK LLP. Confidential and information only.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress ReportReport | 263 KB | DownloadRead as text |
Follow Audit, Standards and Risk Committee at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jul 2026 | Appointment of Chair and Vice-Chair, appointments to Transport Risk Working GroupThat Councillor Mike Levery be appointed Chair and David Phillips be appointed Vice-Chair of the Audit, Standards and... | Decided | Open |
| 9 Jul 2026 | Questions from Members of the PublicThat the questions and responses be noted. | Noted | Open |
| 9 Jul 2026 | Terms of ReferenceThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Health and Safety UpdateThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Bus Franchising UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.