CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
South Yorkshire Mayoral Combined Authority
Mayoral Combined Authority Board, Monday 1 June 2020 at 11.00am

LGF Programme Approvals

Approved Committee 1 paper

Mayoral Combined Authority Board approved this item on Monday 1 June 2020. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

RESOLVED, that the MCA: Approves a project change request from the DN7 Unity project to re-profile £751,800 of expenditure from 2019/20 into 2020/21, to agree an extension to works completion from August 2020 to December 2020 and re-profile of outputs and outcomes in accordance with the revised timescales. Approves a project change request from the Digital Media Centre 2 to re-profile £106,596 of expenditure from 2019/20 into 2020/21, to agree an extension to works completion from March 2020 to June 2020 and a re-profile of outputs and outcomes in accordance with the revised timescales. Approves a project change request from the Strategic Testing Tools project to re-profile £190,196 of expenditure from 2019/20 into 2020/21. Approves a project change request from M1 J36 Phase 1 Hoyland to re-profile £2,621,858 of expenditure from 2019/20 into 2020/21, agree a reduction in the total grant value of £610,009 and a revision of outputs and outcomes in accordance with the revised reprofile. Approves a project change request from M1 J37 Phase 2 - Claycliffe to re-profile £1,376,858 of expenditure from 2019/20 into 2020/21 and the revision of conditions to enable entry into contract. Approves a project change request for the Doncaster Sheffield Airport Car Park Extension Loan to extend the works completion date from April 2020 to January 2021. Gives delegated authority to the Head of Paid of Service, in consultation with the Section 73 Officer and Monitoring Officer, to enter into legal arrangements for the schemes covered in the above recommendations.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to Mayoral Combined Authority Board

Purpose of report

In line with the agreed Assurance Framework this paper seeks approval of change requests for six projects and seeks delegated authority to the Head of Paid Service in consultation with the S73 and Monitoring Officer to enter into legal agreements for the schemes.

Thematic Priority

Secure investment in infrastructure where it will do most to support growth.

Freedom of Information and Schedule 12A of the Local Government Act 1972

This paper will be available under the Combined Authority Publication Scheme

Recommendations

Members are asked to consider the change requests outlined below and if agreed, delegate approval to the Head of Paid Service in consultation with the Monitoring Officer to enter into contract variations, in accordance with the agreement reached.

Members are asked to approve:

1. Project change request from “DN7 Unity project” to reprofile £751,800 expenditure from 19/20 into 20/21, to agree an extension to works completion from August 2020 to December 2020 and reprofile of outputs and outcomes in accordance with the revised timescales. 2. Project change request from “Digital Media Centre 2” to reprofile £106,596 expenditure from 19/20 into 20/21, to agree an extension to works completion from March 2020 to June 2020 and a reprofile of outputs and outcomes in accordance with the revised timescales. 3. Project change request from “Strategic Testing Tools” to reprofile £190,196 expenditure from 19/20 into 20/21 4. Project change request from “M1 J36 Phase 1 Hoyland”- to reprofile £2,621,858 expenditure from 19/20 into 20/21, agree a reduction in the total grant value of £610,009 and a revision of outputs and outcomes in accordance with the revised reprofile. 5. Project change request from “M1 J37 Phase 2 - Claycliffe” to reprofile £1,376,858 expenditure from 19/20 into 20/21 and revision of conditions to enable entry into contract. 6. Project change request from “Doncaster Sheffield Airport Car Park Extension Loan” to extend the works completion date from April 2020 to January 2021. 7. Delegated authority be given to the Head of Paid Service in consultation with the s73 and Monitoring Officer to enter into legal agreements for the schemes covered in 1-6 above. 1. Introduction 1.1 In recognition of unforeseen circumstances that can arise during the project delivery phase the approved Assurance Framework establishes a formal process for the acceptance of change requests. These change requests could be financial requiring reprofiling of funds or could be to amend deliverables or timescales. The Assurance Framework established that some change requests will be presented for approval to the relevant Executive Board, in line with their agreed delegation levels whilst others will require the approval of the MCA Board. 1.2 There are six change requests for LGF which require MCA approval. These are detailed in sections 2.1 to 2.6 below.

2. Proposal and justification 2.1 Scheme 19/20 Allocation 19/20 Final Allocation to be moved Expenditure into 20/21 DN7 Unity Project £8,170,320 £7,418,520 £751,800

The project is building a 2.9km road to unlock housing, retail, commercial and education facilities. The total project cost is £18.17m of which £11.15m is the LGF contribution.

Detail of request – The project was impacted due to the sustained rainfall in October and November. The impact was highlighted as a concern at the time but considered manageable as the site itself didn’t suffer from direct flooding. It was subsequently confirmed that the land had been saturated and was not drying out as quickly as anticipated which highlighted the following issues –  inadequate drainage capacity on the site;  until the land dries, earthworks could not continue; and  the fill material sourced for the site was also saturated and unsuitable for use at this time.

The project is requesting:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LGF Programme ApprovalsReport 176 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 13 attended
MD
Mayor Dan Jarvis MBEChair, present
CR
Councillor Chris ReadVice-Chair, present
GP
Councillor Garry PurdyCommittee Member, apologies, sent representative
JD
Councillor Julie DoreCommittee Member, present
MT
Councillor Martin Thacker MBECommittee Member, apologies, sent representative
MR
Mayor Ros Jones CBECommittee Member, present
SG
Councillor Simon GreavesCommittee Member, apologies
SS
Councillor Sir Steve Houghton CBECommittee Member, present
SF
Councillor Steve FritchleyCommittee Member, apologies
TG
Councillor Tricia GilbyCommittee Member, present
JM
James Muir (Non-Voting Member)Committee Member, present
CF
Councillor Chris FurnessReserve, present

All 13 on the meeting page

On this subject at South Yorkshire Mayoral Combined Authority

Search all
  1. LGF Programme ApprovalsThis decision
  2. LGF Capital Programme ApprovalsApproved
  3. Local Growth Fund (LGF) ProgrammeApproved
  4. LGF Capital Programme ApprovalsApproved
  5. Local Growth Fund (LGF) ProgrammeApproved
  6. LGF Update (year end 19/20 & 20/21 Programme)Decided

More from South Yorkshire Mayoral Combined Authority Mayoral Combined Authority Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the meeting held on 14 July 2026RESOLVED that the minutes of the meeting held on 14 th July 2026 be approved. Approved Open
15 Sep 2026 South Yorkshire Strategy and Proposed Implementation ApproachRESOLVED that the Board endorses: 1. The South Yorkshire Strategy as the shared regional framework. 2. The proposed c... Agreed Open
15 Sep 2026 City Densification FundRESOLVED that the Board: 1. Notes the Government’s allocation of £85m of ing to South Yorkshire. 2. Endorses the prog... Agreed Open
15 Sep 2026 National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ... Noted Open
15 Sep 2026 Governance UpdateRESOLVED that the Board: 1. Notes the recommendation of the Overview & Scrutiny Committee at its meeting on 7th July ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies