RESOLVED, that the MCA: Approves a project change request from the DN7 Unity project to re-profile £751,800 of expenditure from 2019/20 into 2020/21, to agree an extension to works completion from August 2020 to December 2020 and re-profile of outputs and outcomes in accordance with the revised timescales. Approves a project change request from the Digital Media Centre 2 to re-profile £106,596 of expenditure from 2019/20 into 2020/21, to agree an extension to works completion from March 2020 to June 2020 and a re-profile of outputs and outcomes in accordance with the revised timescales. Approves a project change request from the Strategic Testing Tools project to re-profile £190,196 of expenditure from 2019/20 into 2020/21. Approves a project change request from M1 J36 Phase 1 Hoyland to re-profile £2,621,858 of expenditure from 2019/20 into 2020/21, agree a reduction in the total grant value of £610,009 and a revision of outputs and outcomes in accordance with the revised reprofile. Approves a project change request from M1 J37 Phase 2 - Claycliffe to re-profile £1,376,858 of expenditure from 2019/20 into 2020/21 and the revision of conditions to enable entry into contract. Approves a project change request for the Doncaster Sheffield Airport Car Park Extension Loan to extend the works completion date from April 2020 to January 2021. Gives delegated authority to the Head of Paid of Service, in consultation with the Section 73 Officer and Monitoring Officer, to enter into legal arrangements for the schemes covered in the above recommendations.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
In line with the agreed Assurance Framework this paper seeks approval of change requests for six projects and seeks delegated authority to the Head of Paid Service in consultation with the S73 and Monitoring Officer to enter into legal agreements for the schemes.
Thematic Priority
Secure investment in infrastructure where it will do most to support growth.
Freedom of Information and Schedule 12A of the Local Government Act 1972
This paper will be available under the Combined Authority Publication Scheme
Recommendations
Members are asked to consider the change requests outlined below and if agreed, delegate approval to the Head of Paid Service in consultation with the Monitoring Officer to enter into contract variations, in accordance with the agreement reached.
Members are asked to approve:
1. Project change request from “DN7 Unity project” to reprofile £751,800 expenditure from 19/20 into 20/21, to agree an extension to works completion from August 2020 to December 2020 and reprofile of outputs and outcomes in accordance with the revised timescales. 2. Project change request from “Digital Media Centre 2” to reprofile £106,596 expenditure from 19/20 into 20/21, to agree an extension to works completion from March 2020 to June 2020 and a reprofile of outputs and outcomes in accordance with the revised timescales. 3. Project change request from “Strategic Testing Tools” to reprofile £190,196 expenditure from 19/20 into 20/21 4. Project change request from “M1 J36 Phase 1 Hoyland”- to reprofile £2,621,858 expenditure from 19/20 into 20/21, agree a reduction in the total grant value of £610,009 and a revision of outputs and outcomes in accordance with the revised reprofile. 5. Project change request from “M1 J37 Phase 2 - Claycliffe” to reprofile £1,376,858 expenditure from 19/20 into 20/21 and revision of conditions to enable entry into contract. 6. Project change request from “Doncaster Sheffield Airport Car Park Extension Loan” to extend the works completion date from April 2020 to January 2021. 7. Delegated authority be given to the Head of Paid Service in consultation with the s73 and Monitoring Officer to enter into legal agreements for the schemes covered in 1-6 above. 1. Introduction 1.1 In recognition of unforeseen circumstances that can arise during the project delivery phase the approved Assurance Framework establishes a formal process for the acceptance of change requests. These change requests could be financial requiring reprofiling of funds or could be to amend deliverables or timescales. The Assurance Framework established that some change requests will be presented for approval to the relevant Executive Board, in line with their agreed delegation levels whilst others will require the approval of the MCA Board. 1.2 There are six change requests for LGF which require MCA approval. These are detailed in sections 2.1 to 2.6 below.
2. Proposal and justification 2.1 Scheme 19/20 Allocation 19/20 Final Allocation to be moved Expenditure into 20/21 DN7 Unity Project £8,170,320 £7,418,520 £751,800
The project is building a 2.9km road to unlock housing, retail, commercial and education facilities. The total project cost is £18.17m of which £11.15m is the LGF contribution.
Detail of request – The project was impacted due to the sustained rainfall in October and November. The impact was highlighted as a concern at the time but considered manageable as the site itself didn’t suffer from direct flooding. It was subsequently confirmed that the land had been saturated and was not drying out as quickly as anticipated which highlighted the following issues – inadequate drainage capacity on the site; until the land dries, earthworks could not continue; and the fill material sourced for the site was also saturated and unsuitable for use at this time.
The project is requesting:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies