Resolved
RESOLVED – That the Board notes the current position of the project and supports the project as set out and as per how it is progressing.
SCR - Transport Board decided this item on Friday 3 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Board notes the current position of the project and supports the project as set out and as per how it is progressing.
To provide the Transport Board with an update on the Trans-Pennine Tunnel (TPT) project, which Highways England have been commissioned by the Department for Transport (DfT) and Transport for the North (TfN) to develop options for.
Thematic Priority
Secure investment in infrastructure where it will do most to support growth.
That members of the Transport Board:
• Note the current position of the work and comment on whether Board are supportive of the project as set out and as per how it is progressing. • Provides feedback on the comments on the ‘key issues’ section (2.10) to enable SCR to ensure the Boards views are represented during the on-going development of the scheme.
1. Introduction
1.1In July 2015, the Department for Transport (DfT) and Transport for the North (TfN) jointly commissioned Highways England (HE) to produce a strategic study assessing the feasibility of a new strategic highway route (including a tunnel under the Pennines) connecting the M1 at Sheffield and M60 at Manchester.
1.2Previous studies have shown that journeys between Sheffield and Manchester to be amongst the lowest between two core cities due to the poor road (and rail) connectivity across the Pennines. A new strategic route also has the potential to promote growth in the City Region, improve capacity and resilience of the highway network as well as reduce the impact of traffic in the Peak District National Park (PDNP)
The length of the strategic link was expected to be around 25 miles, designed to dual, 1.3 two-lane all-purpose standards and have an operating speed of at least 60 mph.
This project is still in the very early stages - DfT have only committed funding for its early 1.4 development, not its delivery.
2. Proposal and justification
2.1Work has concentrated on: • A strategic route option assessment – leading to a sifting exercise to identify which corridors across the Pennines (and routes within corridors) were more suitable to progress than others. • Establishing the economic benefits of the scheme – using a spreadsheet-based assessment in advance of the Regional Transport Model being available. • Environmental Impacts and • Indicative scheme Costs
Strategic Route Option Assessment
2.2An initial sifting exercise was undertaken to identify which corridors across the Pennines (and routes within corridors) were more suitable to progress than others. More detail is included in Appendix One1
The Government subsequently announced that more work would be carried out to 2.3 understand the full costs and benefits of a tunnel, including the impact on the wider transport infrastructure across the southern Pennines. This ‘wider connectivity’ study area included the A1 and M18 in the City Region.
The findings of this work concluded that a shorter tunnel through the highest and most 2.4 difficult terrain, coupled with a wider connectivity package:
• Provides better value for money. • Provides the same strategic benefits to the full-length tunnel. • Improves access to the Peak District National Park’ • Allows a phased approach to delivery – which provides an earlier realisation of benefits for local and wider communities’
Establishing economic benefits The initial analysis used a spreadsheet-based model to forecast traffic levels, not a full 2.5 transport model. The nature of the spreadsheet-based approach means that the likely increase in the proportion of commuter trips and the impact on employment and housing land cannot be captured. Furthermore, the appraisal considers the impact of the TPT in isolation from the other schemes.
It is anticipated that an improved Trans-Pennine route could roughly double the existing 2.6 usage on the A628, initially attracting around 35,000 vehicles a day. Anticipated journey time reductions from the M1-M60 could be around 30 minutes.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Initial strategic route option assessmentAppendix 1 | 320 KB | Download |
PDF |
Proposed scheme alignmentAppendix 2 | 169 KB | Download |
PDF |
Trans-Pennine Tunnel Project UpdateReport | 133 KB | DownloadRead as text |
Follow SCR - Transport Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Sep 2020 | Minutes of the Previous MeetingRESOLVED – That the minutes of the meeting of the Board held on 3 rd July 2020 be agreed as a true record. | Agreed | Open |
| 4 Sep 2020 | Bus Review Response WorkRESOLVED – That the Board approve the approach to delivering the Bus Review Response work programme through the work ... | Approved | Open |
| 4 Sep 2020 | Integrated Rail Plan For The Midlands And The NorthRESOLVED – That the Board approve the Rail Needs Prospectus, attached to the report, for submission to the Department... | Approved | Open |
| 4 Sep 2020 | Roads Implementation Plan And Approach To The Key Route NetworkRESOLVED – That the Board: a) Note the work undertaken to date with the Local Authorities to develop the SCR Roads Im... | Noted | Open |
| 4 Sep 2020 | Dearne Valley Regeneration RouteRESOLVED – That the Board: a) Note the progress made to date in developing the Strategic Outline Business Case. b) Su... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.