RESOLVED, that the Board: Approves acceptance of the £33.6m Getting Building Fund and grant allocation to deliver the proposed programme (outlined in Annex 1 to this report). Approves acceptance of the £40m Brownfield Fund grant allocation to deliver a programme of housing schemes on brownfield land for 2020-25, subject to agreement on the terms and conditions set out in section 2.6. Approves a new approach to enable earlier release of scheme development costs (as set out in section 2.8) to accelerate the development and delivery of the infrastructure schemes over the next 18 months. Delegates authority to the S73 Officer in conjunction with the Head of Paid Service and Monitoring Officer to accept the grants of £73.6m subject to their acceptance of the terms of the agreements when these are received.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
This report provides an update on the recent announcements for devolved funding to support major employment and housing development in the SCR, and requests that the MCA agrees to accept the funding and supports the proposals for accelerating delivery of the infrastructure and housing schemes.
Thematic Priority This report relates to the following Strategic Economic Plan priorities:
• Secure investment in infrastructure where it will do most to support growth. • Facilitate and proactively support growth amongst existing firms.
Freedom of Information
The paper will be available under the Combined Authority Publication Scheme.
Recommendations
The Board is asked to: • Approve acceptance of the £33.6m Getting Building Fund and grant allocation to deliver the proposed programme outlined in Annex 1 to this report.
• Approve acceptance of the £40m Brownfield Fund grant allocation to deliver a programme of housing schemes on brownfield land for 2020-25, subject to agreement on the terms and conditions set out in section 2.6.
• Approve a new approach to enable earlier release of scheme development costs (as set out in section 2.8) to accelerate the development and delivery of the infrastructure schemes over the next 18 months.
• Delegate authority to the S73 Officer in conjunction with the Head of Paid Service and Monitoring Officer to accept the grants of £73.6m subject to their acceptance of the terms of the agreements when these are received. 1. Introduction
1.1On the 30th June 2020, the Government launched ‘A New Deal for Britain’ which is set as the first steps in the strategy to rebuild Britain following Covid 19 and fuel economic recovery across the UK
1.2As part of this strategy, £73.6m of funding has been allocated to the MCA for supporting immediately deliverable infrastructure schemes and to support the development of housing schemes on brownfield land. This report sets out the actions being taken to meet this challenge and accelerate delivery of these schemes across the SCR.
2 Proposal and Justification
2.1Sheffield City Region Mayoral Combined Authority (MCA) has been awarded £33.6m for a prioritised programme of Major Capital Infrastructure Schemes from the Government’s ‘Getting Building Fund’ that are ‘shovel ready,’ along with a further £40m from the Government’s Brownfield Fund for a programme of housing schemes on brownfield sites over the next 5 years.
Major Capital Schemes
2.2Prior to the Government’s announcement, the MCA and the LEP oversaw the collation and prioritisation of major infrastructure schemes that were ‘shovel ready’ and could be delivered within 18 months. This was undertaken in a very short timescale to meet Government deadlines and involved the prioritisation of a long list of over 80 schemes.
2.3A prioritised list of schemes, as seen in Annex 1, with a funding ask of £31m was submitted to Government. The schemes are a range of employment, skills, digital, public realm, regeneration, and active travel infrastructure schemes, and all but one is located with the Infrastructure Place Package Growth Areas which are aligned in the draft (new) Strategic Economic Plan.
2.4Whilst the total funding ask was £31m, the MCA will receive £33.6m in total. Following consultation with the Mayor, it is proposed that this additional £2.6m is prioritised for a pan- South Yorkshire project which would both benefit all authorities and contribute towards wider SCR priorities such as environmental sustainability. For example, this could include a South Yorkshire wide electric vehicle (EV) charging infrastructure project being prioritised for this additional funding following the work undertaken by Arup for the MCA earlier this year. This would aim to install up to 230 Fast Chargers and Rapid Chargers in urban centres and other key strategic locations across the SCR. Further discussions would need to take place with MHCLG to confirm the final agreed list of projects.
Brownfield Housing Programme
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.