Delivering The Transforming Cities Fund Programme - Update

Noted Committee 1 paper

SCR - Transport Board noted this item on Friday 4 September 2020. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

RESOLVED – That the Board: a) Note the current programme delivery issues and approaches being made to mitigate them. b) Agree to undertake a review of the current programme with a view to receiving a revised programme at the October Transport Board meeting.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to SCR - Transport Board

TRANSPORT BOARD

4TH September 2020

DELIVERING THE TRANSFORMING CITIES FUND PROGRAMME - UPDATE

Purpose of Report This report provides an update on how the MCA Executive intends to continue to work with scheme sponsors to deliver the Transforming Cities Fund programme by March 2023.

Thematic Priority Secure investment in infrastructure where it will do most to support growth.

Recommendations That members of the Transport Board:

• Note the current programme delivery issues, and approaches being used to mitigate them. • Agree to undertake a review of the current programme with a view to receiving a revised programme at the October Transport Board meeting.

1. Introduction

1.1The Strategic Outline Business Case (SOBC) for the Transforming Cities Fund (TCF) programme was submitted to the Department for Transport (DfT) on 27th November 2019. The subsequent acceptance of the £166m grant from DfT was reported at the MCA meeting on 1st June 2020.

1.2The development and delivery of a large capital programme requires significant early investment and resources. This is especially important with the TCF programme given the 3-year delivery timeframe. This paper provides an update on the current position with the programme, issues which could impact on the current profile and approaches being used to mitigate them.

2. Proposal and justification

2.1The original TCF bid submitted in November 2019 set out the overall programme spend each year between 2020/21 and 2022/23. The profile on the grant letter from DfT started from 2019/20 (a year earlier than requested).

2.2In order to update the overall programme and likely spend profile, scheme promoters were asked to provide updated information in June 2020 with a deadline of August 2020. The information predominantly remains outstanding.

2.3However, there are already concerns that scheme promoters are increasingly seeking to move project spend towards the end of the programme. The latest profile is shown below but this is expected to change further as additional information becomes available from partners.

SCR TCF Programme 19/20 2020/21 2021/22 2022/23 Spend Profile in the bid - £20m £81m £65m

DfT Grant letter £8m £21m £65m £72m

Latest Profile - £16m £72m £78m

2.4There are a number of reasons for the request of scheme promoters to move project spend into later years, not least the impact of Covid-19 along with new pressures related to additional funding being secured by the MCA as a result of recent Government announcements.

2.5Covid-19 has had a significant impact on TCF programme delivery and planning. Issues include delays to data collection and the need to re-consider how consultation is undertaken, both of which could affect delivery of the overall programme by six to nine months. The MCA Executive is reducing the effect of data collection delays by being pragmatic about what can be used as an appropriate data source for a scheme appraisal while partners are adjusting their consultation processes on projects as it is not expected that we will be back to ‘normal’ in the next few months.

2.6Projects in the early delivery phase of TCF have seen delays in more specialist construction materials, as well as inflated cost estimates linked to supply and demand within the supply chain. This issue is expected to be seen throughout the programme life, and although there is a £16m programme level risk allowance to help mitigate this situation in Tranche Two, this value will need to be regularly reviewed in light of ‘actual’ costs within the programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Delivering The Transforming Cities Fund Programme: UpdateReport 132 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
MD
Mayor Dan Jarvis MBEChair, present
CR
Councillor Chris ReadVice-Chair, apologies
PK
Peter KennanCommittee Member, present
DL
Councillor Dave LeechCommittee Member, present
CF
Councillor Chris Furness (Non-constituent representative)Committee Member, present
AK
Councillor Abdul KhayumCommittee Member, present
JB
Councillor Joe BlackhamCommittee Member, apologies
AK
Alison KinnaCommittee Member, apologies
ML
Mark LynamCommittee Member, apologies
SN
Sarah NormanCommittee Member, apologies, sent representative
EH
Emily HickeyOfficer, in attendance
FK
Felix Kumi-AmpofoOfficer, in attendance

All 16 on the meeting page

More from South Yorkshire Mayoral Combined Authority SCR - Transport Board

All decisions
MeetingDecisionOutcome
4 Sep 2020 Minutes of the Previous MeetingRESOLVED – That the minutes of the meeting of the Board held on 3 rd July 2020 be agreed as a true record. Agreed Open
4 Sep 2020 Bus Review Response WorkRESOLVED – That the Board approve the approach to delivering the Bus Review Response work programme through the work ... Approved Open
4 Sep 2020 Integrated Rail Plan For The Midlands And The NorthRESOLVED – That the Board approve the Rail Needs Prospectus, attached to the report, for submission to the Department... Approved Open
4 Sep 2020 Roads Implementation Plan And Approach To The Key Route NetworkRESOLVED – That the Board: a) Note the work undertaken to date with the Local Authorities to develop the SCR Roads Im... Noted Open
4 Sep 2020 Dearne Valley Regeneration RouteRESOLVED – That the Board: a) Note the progress made to date in developing the Strategic Outline Business Case. b) Su... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies