MCA - Housing and Infrastructure Board noted this item on Thursday 22 October 2020. Below is the council's own wording, with the papers it was decided on.
RESOLVED – That the Board:- 1. Noted the contents of the report. 2. Agreed in principle to further work being undertaken on the transfer of responsibilities of the One Public Estate Programme in future years. Endorsed the emerging project long list set out in paragraph 2.2 of the report and agreed for the MCA Executive to agree the final proposed bid submission in liaison with the Board Co-Chairs by the 12th November 2020 submission deadline.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
To provide an update on the emerging proposals for One Public Estate (OPE) and Land Release Fund scheme submissions as part of the OPE 8 funding round invitation.
Thematic Priority This report relates to the following Strategic Economic Plan priorities:
Secure investment in infrastructure where it will do most to support growth
Freedom of Information
The paper will be available under the Combined Authority Publication Scheme.
Recommendations
The Board is asked to:
1. note the contents of the report.
2. suggest a way forward on the leadership of the One Public Estate Programme in future years.
3. endorse the emerging project long list set out in Para 2.2 and agree for the MCA Executive to agree the final proposed bid submission in liaison with the Board Co-Chairs by the 12th November 2020 submission deadline.
1. Introduction
1.1The One Public Estate (OPE) programme is a partnership between the Office of Government Property in the Cabinet Office, the Local Government Association (LGA) and the Ministry of Housing, Communities and Local Government (MHCLG). The fund is revenue based and aims to bring public sector bodies together, to create better places by using public assets more efficiently.
1.2The Land Release Fund (LRF) provides capital funding to bring forward surplus Council assets for new housing delivery.
1.3This is the 8th OPE funding round that has been launched, with £10 million revenue funding available. The LRF has £20 million capital funding available to support housing schemes. The Public Assets Development (PAD) Group agreed to develop a potential OPE/LRF programme of schemes to be submitted by the 12th November 2020 submission deadline. An outline of the emerging package of schemes is set out below, which could form an OPE8 & LRF bid submission.
1.4The report also raises the issues related to the continued resourcing of the OPE programme, and which body(s) are best placed to provide leadership for the programme.
2. Proposal and justification
OPE 8 Funding Submission
2.1Through previous funding rounds the SCR OPE Partnership has successfully obtained a total of £902,000 in OPE revenue funding and £450,000 in Land Release Fund capital monies. To date the programme has facilitated the delivery of 71 new homes, £416,500 revenue savings to public bodies and £295,000 capital receipts, with a further £500,000 revenue and £650,000 capital receipts expected before the end of this financial year.
2.2Discussions are ongoing with OPE partners such as Local Authorities, health service partners and the Police and Fire and Rescue Services, to consider appropriate schemes for both OPE8 and LRF funding. An indicative emerging long list of proposed schemes is set out below with a potential total funding request of £936,500; consisting of £645,00 grant and £291,500 sustainable grant. An additional £175,000 is asked of the LRF programme.
The potential emerging projects have been organised into 5 themes as follows:
1. Masterplanning for urban district centres: Wath, Dinnington & Maltby, Rotherham and Thorne, Rossington & Waterfront, Doncaster.
2. Continued support for existing schemes: Support for the completion of the Outline Business Case (OBC) for Midland Road & Ryegate Hospital.
3. Integrated Care System Primary Care Hub Programme: Support for the completion of OBC & Full Business Case for Rossington & Bentley, Doncaster
4. Community Hubs: Initial feasibility into the potential for community hubs at Wickersley & Munsborough, Rotherham
5. Site preparation: Specific sites on land in Kiveton & Herringthorpe, Rotherham
One LRF scheme has been proposed for the demolition of a former day care centre in Wath, Rotherham.
Programme Resources and Leadership
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow MCA - Housing and Infrastructure Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.