Resolved
RESOLVED – That the Committee agree that the amended approach gives the required assurance of active risk management and endorse the approach to the MCA Board.
Audit, Standards and Risk Committee agreed this item on Thursday 29 October 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Committee agree that the amended approach gives the required assurance of active risk management and endorse the approach to the MCA Board.
Following a full internal Management Board review and an Internal Audit Report, the risk management framework of the MCA has been revised and refreshed. This report presents a new risk management policy and process and seeks to provide the assurance that risk is being actively managed by the MCA Executive Management Board.
Thematic Priority
Cross cutting.
Freedom of Information
Under the Freedom of Information Act this paper and any appendices will be made available under the Mayoral Combined Authority Publication Scheme. This scheme commits the Authority to make information about how decisions are made available to the public as part of its normal business activities.
Audit and Standards Committee Members are asked to:
• consider and discuss the revised and refreshed MCA Risk Policy and Process documentation, • consider whether the amended approach gives the required assurance of active risk management, and subsequently endorse the approach to the MCA Board.
1. Introduction
1.1A recent Internal Audit Report on risk management concluded that the processes of the MCA Executive in monitoring and managing risk on behalf of the MCA provides ‘significant assurance with some improvements required’.
The recommendations of the audit include refreshing authority’s Risk Management Policy and Process to ensure they; accurately reflect the structure of the organisation, set out reporting requirements, clarify escalation and de-escalation procedures and outlines how the MCA oversees the risk management arrangements of the PTE. The audit report also recommends that a consistent approach to scoring and moderating risks should be developed as well as ensuring adequate training and development for roles with specific risk management responsibilities.
This paper presents a revised Risk Management Policy and Process, strengthened to address the recommendations of the internal audit report.
2. Proposal and justification
2.1Risk Management Policy and Process
The existing Risk Management Policy and Process have been reviewed and strengthened, and now follow the ‘Management of Risk’ (MoR®) principles of risk management which are aligned to the international standard for risk management ISO31000:2009 (There are currently 9 MoR® formally trained risk champions in the MCA Executive Team).
The refreshed Risk Management Policy and Process describes why risk management is important to the organisation and the objectives served by implementing a formal risk management approach. It sets out the approach to risk appetite and risk tolerance thresholds, the procedure for escalation/de-escalation, risk management duties of roles within the organisation and reporting requirements. It also sets out how the organisation plans to carry out risk management and the approach to identifying, assessing and evaluating risk, and planning and implementing mitigations.
The content of the documentation now addresses a number of recommendations made by the audit on risk management including:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Policy and ProcessAppendix A | 1.1 MB | Download |
PDF |
Risk Policy and ProcessReport | 173 KB | DownloadRead as text |
Follow Audit, Standards and Risk Committee at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jul 2026 | Appointment of Chair and Vice-Chair, appointments to Transport Risk Working GroupThat Councillor Mike Levery be appointed Chair and David Phillips be appointed Vice-Chair of the Audit, Standards and... | Decided | Open |
| 9 Jul 2026 | Questions from Members of the PublicThat the questions and responses be noted. | Noted | Open |
| 9 Jul 2026 | Terms of ReferenceThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Health and Safety UpdateThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Bus Franchising UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.