RESOLVED – That the Committee considered the report and verbal update provided by the Chair of the Audit, Standards and Risk Advisory Panel in seeking assurance on the progress towards integration.
Audit, Standards and Risk Committee decided this item on Thursday 27 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Committee considered the report and verbal update provided by the Chair of the Audit, Standards and Risk Advisory Panel in seeking assurance on the progress towards integration.
Committee/Board Name and Date of Meeting: Audit, Standards and Risk Committee
Meeting Date: 27 January 2022
Report Title Integration Assurance Update
Is the paper exempt from the press No and public?
Reason why exempt: Not applicable
Purpose of this report: Monitoring/Assurance
Is this a Key Decision? No
Has it been included on the No Forward Plan?
Director Approving Submission of the Report: Ruth Adams, Deputy Chief Executive
Report Author(s): Claire James [email protected]
Executive Summary This paper reports on the assurance activity for the Integration Programme.
What does this mean for businesses, people and places in South Yorkshire? The decision to formally integrate the PTE and MCA was made in order to ensure greater political oversight and decision making of passenger transport services in South Yorkshire.
Recommendations The Committee are asked to consider the report and verbal update provided by the Chair of the Audit, Standards and Risk Advisory Panel in seeking assurance on the progress towards integration.
Consideration by any other Board, Committee, Assurance or Advisory Panel Appendix 1 of this report was considered by the Audit and Risk Advisory Panel 13th January 2022. 1. Background
1.1The Audit, Standards and Risk Advisory Panel terms of reference include undertaking assurance of the Integration Programme. This report updates the Committee on the assurance received by the Panel at its last meeting held on 13 th January. The report also provides an update on the progress of the Integration Programme.
2. Key Issues
2.1Programme Progress
The Programme Plan for Integration set out two key milestones: • Integration of two organisations into a single MCA Executive (operational by 01.04.22) • Legal dissolution of the PTE via a statutory order (by 31.03.22)
The first of these milestones is on track to be achieved within timescales set out. The second will not be achieved as government have confirmed that they are unable to progress the statutory process to dissolve the PTE prior to the May elections.
The implications of this are that the legal identities of the two organisations will continue into the new financial year. Work has been undertaken that sets out the implications of the delay to the statutory order for consideration by the Programme Board and scrutiny by the ASRC Panel. An example of this is that 2 sets of accounts will still be required to be produced in 22/23. The mitigation plan was agreed by the Programme Board on 11th January.
2.2Programme Governance and Assurance Activity
The Advisory Panel on 13th January, considered a summary of the assurance activity undertaken by the Programme Management Office since the Panel last met in October. This included: • An overview of the Programme Governance meetings held and their remit and outputs • The actions taken to strengthen Programme Management (including the introduction of a formal change management process) • The outputs from the Phase One Programme Review activity at the end October/beginning of November which included lessons learned recommendations and change requests • An overview of the business areas requiring workarounds due to the delay of the dissolution Order • The outline timetable for the next phase of the Programme which is focussed on mobilising the new structure and operating model.
2.3The Panel also received a presentation that focussed on the overall condition or health of the Programme by examining key indicators including: • Critical milestones – are these being met? • Change Requests – are we making a significant number of changes to the programme plan and will this impact on achievement of objectives/benefits realisation and timescales? • Slippage – are we managing to stick to our plan and any slippage brought back on line? • Resources – is the Programme resourced appropriately and keeping within budget? • Engagement - how are we making sure our people are on board, do they understand what’s going on and why and what it means for them?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
16i Appendix 1: Advisory Panel Update Jan 22Appendix | 248 KB | Download |
PDF |
Integration UpdateReport | 208 KB | DownloadRead as text |
Follow Audit, Standards and Risk Committee at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jul 2026 | Appointment of Chair and Vice-Chair, appointments to Transport Risk Working GroupThat Councillor Mike Levery be appointed Chair and David Phillips be appointed Vice-Chair of the Audit, Standards and... | Decided | Open |
| 9 Jul 2026 | Questions from Members of the PublicThat the questions and responses be noted. | Noted | Open |
| 9 Jul 2026 | Terms of ReferenceThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Health and Safety UpdateThat the report be noted. | Noted | Open |
| 9 Jul 2026 | Bus Franchising UpdateThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.