Resolved
to note the update and to continue to support the Bid.
Local Enterprise Partnership noted this item on Thursday 8 September 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
to note the update and to continue to support the Bid.
1.1The Levelling Up Fund (LUF) is led by the Department for Levelling Up Housing and Communities (DLUHC) and is designed to invest in infrastructure that improves everyday life across the UK, supporting town centre and high street regeneration, local transport projects, and cultural and heritage assets.
1.2MCAs are eligible to receive funding for one transport submission, SYMCA were not successful in round one during 2021 and so have produced a submission for round two of the programme. This is expected to be the final round of LUF offered by DLUHC.
1.3Following a review of the feedback from our original LUF submission and successes from other regions, it was determined that revision of the round one proposal was not suitable and a more innovative approach has been developed. The round two submission is centred on the modernisation of the passenger transport network and establishment of a SMART transport system to provide a greater customer offering and experience.
1.4The proposal has three main pillars; the ability to plan better journeys through the provision of technology and customer information improvements at stops and interchanges, the ability to ‘buy better’ through an integrated and simple ticket purchasing process and better travel opportunity through improvements to the reliability of scheduled services and the creation of a new Demand Responsive Transport (DRT) service capability.
2. Key Issues
2.1At a national level the LUF round one programme was heavily over-subscribed and it is realistic to expect that this will happen again with round two, this increases the risk of proposals not being funded.
2.2The activities within the LUF submission, in particular the development of DRT capability, is innovative and a new area of work for SYMCA. This has required the proposals to be developed from a zero base as there wasn’t existing delivery experience to build from, and this work has had to be undertaken at pace to meet the DLUHC submission schedule. Considerable progress has been made to get the submission developed as far as possible however further definition is required. The commitment to delivering this definition has been clearly stated in the submission made on 2nd August. 2.3 The DLUHC process now requires an Outline Business Case to be submitted before any funding will be committed, the work to progress the proposals to this OBC level has commenced.
3. Options Considered and Recommended Proposal
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Levelling Up Fund Bid UpdateReport | 275 KB | DownloadRead as text |
Follow Local Enterprise Partnership at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Notes and Action Log of Last MeetingThat the notes of the meeting held on 18 th May be agreed as a true record. to note updates to the action log. | Agreed | Open |
| 13 Jul 2023 | South Yorkshire's Investment ZoneThat the Board note the update. | Noted | Open |
| 13 Jul 2023 | The South Yorkshire EconomyTo note the update. | Noted | Open |
| 13 Jul 2023 | LEP Annual Report and Governance ChangesRESOLVED : That the Board: 1. Approve the Annual Report as attached at Appendix A. 2. Note the new business engagemen... | Approved | Open |
| 13 Jul 2023 | Development of a Northern Pan Regional PartnershipThat the Board: 1. Note the Government’s intention to establish a formal Northern Pan Regional Partnership (PRP) and ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.