Resolved
Resolved that the contents of the paper in relation to progress with the Enhanced Partnership Scheme be noted and support be provided where required.
Enhanced Partnership Board noted this item on Tuesday 4 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the contents of the paper in relation to progress with the Enhanced Partnership Scheme be noted and support be provided where required.
The South Yorkshire Enhanced Partnership Plan and Scheme was approved by the Mayoral Combined Authority in March 2022 and commenced on 1 April 2022.
This paper summarises the progress made in delivering the agreed components of the Scheme, upcoming milestones, risks and issues and any actions to be considered by the Board.
What does this mean for businesses, people and places in South Yorkshire?
SYMCA’s Strategic Economic Plan and Transport Strategy both underline the importance of the bus network to businesses, residents and visitors in South Yorkshire, whilst the independent Bus Review indicated a number of issues with the current network. The Service Improvement Plan includes a range of short-, medium- and long-term actions aimed at supporting the recovery from the COVID-19 pandemic and providing the bus network that South Yorkshire needs to achieve its aims for a stronger, fairer and greener region. The Enhanced Partnership Plan and Scheme is a means of delivering the short- term actions within the Bus Service Improvement Plan
It is recommended that the Board notes the contents of this paper in relation to progress with the Enhanced Partnership Scheme and provides support where this is required.
1.1The South Yorkshire Enhanced Partnership Plan (EPP) and Scheme (EPS) was approved by the Mayoral Combined Authority in March 2022 and commenced on 1 April 2022. Effective and timely delivery of the components of the EPS, and any interventions included in other EPSs that may be agreed, is critical to the achievement of the objectives of the EPP.
1.2As part of the regular reporting cycle to the Enhanced Partnership Board, the EP Development Group receives and discusses a regular EPS Programme Monitoring Report. This paper summarises the key issues arising and any actions that to be considered by the Board.
1.3It should be noted that the activity discussed in this paper does not represent the totality of the activity underway across South Yorkshire by all partners to improve bus services. The EP Development Group has started collating information on bus initiatives undertaken by all parties in the Enhanced Partnership to provide a fuller picture to the Board, with a progress monitoring mechanism.
2. Summary of Key Changes in EPS Delivery
2.1Develop new forum for passenger representation, to include bus user groups, representatives of disabled people and local business groups – The Mayor has invited all members of the EP Forum to a first meeting on 28 September 2022, which will revolve around starting the development of a new Customer Charter.
Implementation of a common branding across South Yorkshire transport network – An initial rollout plan was discussed at the EP Development Group on 7 September 2022 and will be progressed to develop a proposal for the EP Board.
Service changes to be limited to twice per year – The August 2022 EP Operating Group meeting agreed to limit service changes to twice a year, with typical dates agreed to be the first Sunday after Easter and the last Sunday before the start of a new school year. (NB: October 2022 changes count as a service change).
Price rises limited to once a year – Operating Group agreed price rises once a year in January, except for 2023 when a price change might be implemented in March to fall in line with the rail industry.
A61 bus priority road widening scheme – The scheme is currently awaiting planning permission, which has been delayed (planning application submitted in December 2021). The granting of this permission will determine the delivery timeline, but preparatory and mobilisation work continues to progress in the meantime, assuming construction work can commence after Christmas holidays in early 2023. There is a funding shortfall to deliver both phases, with the Project Manager exploring alternative options to deliver Phase 2.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EPS1_Progress Monitoring ReportAppendix A | 172 KB | Download |
PDF |
Enhanced Partnership Scheme Progress ReportReport | 702 KB | DownloadRead as text |
Follow Enhanced Partnership Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jun 2026 | Minutes & actions of the previous meetingRESOLVED that the minutes of the meeting held on 4 th March 2026 were agreed as a true and accurate record. The Chair... | Agreed | Open |
| 10 Jun 2026 | DRT UpdateThat the Board noted the update. | Noted | Open |
| 10 Jun 2026 | Vision Strategy UpdateThat the presentation be noted. | Noted | Open |
| 10 Jun 2026 | Fleet Accessibility and Safety EngagementThat the presentation be noted. | Noted | Open |
| 10 Jun 2026 | EP Forum UpdateThat the update be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.