Tram Future Operating Model

Agreed Committee 1 paper

Mayoral Combined Authority Board agreed this item on Tuesday 18 October 2022. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

RESOLVED that Board members: 1. Authorised the MCA to establish an arm’s length wholly owned subsidiary company (NewCo) to operate the Supertram system (with effect from 22nd March 2024). Agreed to receive further reports regarding the financial sustainability as soon as modelling work is concluded.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to Mayoral Combined Authority Board

Background

1.1The light rail network infrastructure in South Yorkshire (“Supertram”) is publicly owned by South Yorkshire Passenger Transport Executive (SYPTE). In 1997 SYPTE awarded a 27-year concession to a wholly owned subsidiary South Yorkshire Supertram Limited (SYSL). As part of restructuring due to borrowing issues, the Government at the time required SYPTE to dispose of the operating element of the system to a private entity. In 2000 it sold the operating company SYSL to Stagecoach Group. In 2018, the system was extended via Tram Train to Rotherham. The concession contract covers responsibility for the operation, day to day maintenance and revenue risk of the full system and expires on 21st March 2024. At expiration of this contract, SYSL no longer have the right to operate Supertram and operational, managerial and financial responsibility for the system reverts to SYPTE/MCA.

1.2A key milestone for the successful and seamless transition to a new operator in March 2024, is a decision on the future Operating Model. The net operating costs (including revenue risk) for running the tram system transfers to the MCA at this point.

2. Current Position

2.1Although the tram had previously generated a profit, in the year prior to Covid-19, the tram system was operating at a loss, which is largely attributed to a mix of long- term patronage decline reinforced by the closure of parts of the system for renewal works.

2.2General suppression in demand for public transport during Covid-19 including changes to travel habits has exacerbated a further decline in passenger numbers, and an increase in operating costs as a result of inflation, is leading to an increase in financial losses.

2.3Passenger demand is showing signs of recovery but remains uncertain as the rate of recovery post-Covid needs to settle and demand may be plateauing.

2.4The tram infrastructure and vehicles are assets that are owned by the MCA but are nearing the end of their economic life and the renewal programme would see disruption to operations. The MCA has secured c. £100m of capital from DfT to commence this programme of works but requires significantly more funding in the medium term to enable the renewal of all life-expired assets. The MCA is in the process of submitting a business case to DfT for further funding.

3. Challenges

3.1A new operator is required to be in place from March 2024 (17 months).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tram Future Operating ModelReport 515 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 13 attended
MO
Mayor Oliver CoppardChair, apologies
TF
Councillor Terry FoxCommittee Member, apologies
SS
Councillor Sir Steve Houghton CBECommittee Member, present
MR
Mayor Ros Jones CBECommittee Member, present
CR
Councillor Chris ReadCommittee Member, present
AD
Councillor Alex DaleCommittee Member, apologies
SF
Councillor Steve FritchleyCommittee Member, apologies
TG
Councillor Tricia GilbyCommittee Member, apologies
SG
Councillor Simon GreavesCommittee Member, apologies
AB
Adam BottomleyOfficer, in attendance
PB
Pat BeijerOfficer, in attendance
AG
Andy GatesOfficer, in attendance

All 13 on the meeting page

On this subject at South Yorkshire Mayoral Combined Authority

Search all
  1. Tram Future Operating ModelThis decision
  2. South Yorkshire Future Tram Limited Governance ReformsDecided
  3. Tram - Future Operating ModelDecided

More from South Yorkshire Mayoral Combined Authority Mayoral Combined Authority Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Minutes of the meeting held on 14 July 2026RESOLVED that the minutes of the meeting held on 14 th July 2026 be approved. Approved Open
15 Sep 2026 South Yorkshire Strategy and Proposed Implementation ApproachRESOLVED that the Board endorses: 1. The South Yorkshire Strategy as the shared regional framework. 2. The proposed c... Agreed Open
15 Sep 2026 City Densification FundRESOLVED that the Board: 1. Notes the Government’s allocation of £85m of ing to South Yorkshire. 2. Endorses the prog... Agreed Open
15 Sep 2026 National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ... Noted Open
15 Sep 2026 Governance UpdateRESOLVED that the Board: 1. Notes the recommendation of the Overview & Scrutiny Committee at its meeting on 7th July ... Decided Open