To note at section 2.1 the proposed amendments to the to ensure compliance with the Government’s requirements and most recent issued guidance. To agree the draft in Appendix A for onward publication and submission to the relevant government departments.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
The existing assurance process has been described as bureaucratic, unresponsive and opaque. Changes are being proposed to improve the process in line with the following principles:
• The process needs to be simple, transparent and streamlined
• The process should support pragmatic decision making that acknowledges approvals already in place with government departments
• The process will add value and minimise duplication
• The process is compliant with government requirements
• Decisions will be taken by one Board only (Thematic Board for projects less than £2m and MCA Board for projects more than £2m) South Yorkshire Mayoral Combined Authority
Proposed�process�for�project�and�programme�approvals Reduced touch-points and streamlined approval process:
Step 1 : Programme Step 2: Assessment of Step 3: Business Case Entry Business Case Approval • Assess for • Recommendation strategic fit to relevant Board against agreed for approval or Thematic or MCA criteria for otherwise, using Board decide to reject Initial • Co-development of funding pot as at business case evidence based or approve funding Proceed to proposal contract if broadly present • Due diligence analytical with broadly specified • Agree release of specified undertaken assessment thresholds conditions set by funding required • Any issues including of BCR, MCA are met. If for further communicated to LA risk and legal not resubmit to proposal colleagues in a timely issues MCA development manner South Yorkshire Mayoral Combined Authority
Step�1:�Programme�Entry� Identifying the right projects early in the process:
Relevant Grant Letter Mandate Form Thematic issued for Assessment Pipeline entry Board and (MF) development MCA Board funding kept informed
• Scheme promoter submits a Mandate Form including Statement of Strategic Fit to MCA. Project details will then be captured on Verto – the shared project management system. • Mandate Form and Statement of Strategic Fit is assessed for: o Fit with agreed MCA strategic objectives (economic growth; social inclusion & inequalities; environmental sustainability) o Contribution to agreed outcomes as per the co-developed Outcomes Framework (see slides 6 and 7) o Compliance with Government requirements for the relevant funding pot (where applicable) • Following approval, Grant Letter sent to scheme promoter confirming any early release of development funding to develop the project to Business Case stage. South Yorkshire Mayoral Combined Authority
Step�2:�Project�Development�&�Business�Case�Completion� One business case and one decision point:
Funding Decision by agreement relevant Board Conditions of Business Case Technical signed and (Thematic/MCA) funding approval Submission Assessment exchanged once to reject, defer or communicated conditions are approve met
• Scheme promoter and MCA co-design and co-develop the project and prepare the Business Case • Scheme promoter submits the Business Case to MCA technical assessment including o Confirmation of Value for Money o Suitability of preferred option o Financial and commercial due diligence o Confirmation of statutory processes (if any) o Risk and deliverability • Business Case and other documentation submitted to relevant Board (Thematic Board for projects up to £2m or directly to MCA Board for projects over £2m) for consideration & approval • Funding agreements are prepared in parallel • Conditions of approval, including any tolerances and thresholds are communicated to scheme promoter • Funding agreements are signed once conditions have been met and revised business case is submit for audit purposes. South Yorkshire Mayoral Combined Authority
Preparation�for�Contract Preparing contracts as early as possible to support quick procurement:
Programme Revised business Board confirm Funding case submission Final checks that Funding Agreement (FBC) Agreement can signed be issued
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.