AI summarySouth Yorkshire MCA board notes bus franchising progress, endorses Tranche 1 plans and delegates grant and network decisions to officers, keeping award of anchor contracts for the board.
Written from the decision and the officer reportPDF Pro
OutcomeNoted
MoneyUp to £355m capital, £20m revenue
What happens nextAward anchor franchise contractsTranche 1 services due to start 5 September 2027
Who it affectsSouth Yorkshire bus passengers and operatorsBeginning in Doncaster and parts of Sheffield
What was decided
The board noted progress since the March 2025 franchising decision and endorsed the high level programme, milestones and Tranche 1 features set out in the exempt appendices. Report 1.1, 1.3, 1.4, 1.6
Decisions to keep the current bus network stable during transition, and to accept future grants for franchising and zero emission buses, are delegated to the Executive Director of Transport and Executive Director of Resources and Investment, within approved budget. Report 2.3, P50
Awarding anchor franchise contracts is reserved as a future decision of the MCA board, with capital funding and progress assured through the Investment Board and Performance Board. Report 1.5, P10, 2.4, P52
Why
Bus franchising is a critical part of delivering an integrated public transport system to support growth and inclusion in South Yorkshire. Report P2
Franchising will return the bus system to public control, beginning in Doncaster and parts of Sheffield from September 2027, with a network broadly consistent with June 2025 plus strategic enhancements. Report 1.1, P21
Further delegation is needed so programme decisions can be taken quickly and regularly without waiting for additional board meetings, while the award of key operating contracts stays with the board as a safeguard. Report 2.1, P46, 2.2, P48, 2.4, P52
What happens next
Tranche 1 anchor franchise contracts are to be awarded in January 2027, with services starting on 5 September 2027, drawing on the Leger Way and Olive Grove depots. Report 1.4, 1.8, P31, 4.1
Key near-term decisions include the bus fleet strategy, depot strategy and citizen experience strategy in Q4 2025, then vehicle specification, network scope, fares strategy and control room approach in Q1 2026. Report 1.7, P28, 1.8, P36
Compulsory Purchase Order process for Olive Grove depot is already underway alongside negotiations, and discussions continue with the Department for Transport about bringing forward CRSTS2 funding. Report 1.7, P24, 1.10, P42
The money
£20m Revenue budget for the franchising transition period Report 1.10, P41
£355m Total capital budget for franchising delivery Report 1.10, P41
£5m Capital already assigned from CRSTS1 Report 1.10, P41
£350m Capital agreed as part of CRSTS2 / TCR Report 1.10, P41
£20m Grant in discussion from DEFRA and DfT for Sheffield bus fleet electrification Report 1.10, P43
£11m Fund held by Sheffield City Council for electrifying Sheffield's bus fleet Report 1.10, P43
Options considered
Rejected: Option 1: Operate within existing delegated authority levels. Risk of unplanned delays because decisions not delegated could not be made quickly enough, putting the September 2027 milestone at risk Report 2.1, P46, 2.2, P48
Chosen: Option 2: Delegate further elements of programme delivery and grant acceptance to the Executive Directors. Allows quicker, more regular decisions within budget and policy, while reserving award of anchor franchise contracts to the MCA board as a safeguard Report 2.3, P50, 2.4, P52, 2.5, P54
Implications
Financial: Programme expected to stay within £355m capital and £20m revenue envelope, but CRSTS2 funds may need to be spent ahead of the 2027-32 window to deliver on time. Report 1.10, P41, P42
Legal: MCA has powers to implement a Bus Franchising Scheme under the Transport Act 2000; the Officer Scheme of Delegation governs how decisions are taken, with promotion of a Compulsory Purchase Order reserved to the board. Report 6.1, 6.2, P63
Equalities: Equality and Diversity Impact Assessment from March 2025 will be updated as franchising progresses, with workstreams required to consider impacts on protected groups and user groups. Report 8.1, 8.2, 8.3
Climate: At least 30% of new buses in Tranche 1 will be zero-emission and all other new buses low-emission, supporting decarbonisation and Clean Air Zone compliance. Report 1.6, P19, 1.7, P25, 9.3
Risk: Limited capacity within the digital and technology team and competing demand from other city regions for specialist franchising suppliers could affect delivery timescales and costs. Report 10.3
Staffing: Additional staff are being recruited to deliver the programme within the agreed budget, with early engagement with trade unions and operators on TUPE. Report 7.1, 7.2, 7.3, 7.4
Other: A new transport brand, simplified ticketing and tap-on fare capping will be introduced, with cash, card and app purchase options retained. Report 1.6, P18, P22, 1.8, P32
Who and where
Bus passengers across South Yorkshire, starting in Doncaster and parts of Sheffield Report 1.1, 1.6, P21
Current bus operators, including those running services from Leger Way and Olive Grove depots Report 1.4
Small and medium-sized bus operators, who will retain facilities for smaller franchise contracts Report 1.7, P24
South Yorkshire MCA Investment Board, Performance Board and Overview and Scrutiny Committee, which will oversee funding, progress and scrutiny of the programme Report 1.5, P10, P15
Staff being recruited into the MCA delivery team, with TUPE implications for staff transferring from existing operators Report 7.1, 7.4
Timeline
March 2025: MCA board agreed to make a bus franchising scheme for South Yorkshire Report 1.1
2 September 2025: Report considered by the Overview and Scrutiny Committee Report P4
Q4 2025: Decisions expected on bus fleet strategy, depot strategy and citizen experience strategy; procurement of non-anchor franchise contracts starts Report 1.7, P28, 1.8, P36
Q1 2026: Decisions expected on vehicle specification, Tranche 1 network scope, fares and ticketing strategy and control room operations Report 1.7, P28, 1.8, P36
Q2 2026: Decisions expected on placing orders for new vehicles, cross boundary bus services and the franchise performance management regime Report 1.7, P28, 1.8, P36
Q3 2026: Decisions expected on mobilisation and demobilisation planning and the data and insight approach to service planning and delivery Report 1.7, P28, 1.8, P36
From 2026: Delivery of electrification infrastructure projects at strategic depot locations Report 1.7, P28
Q1 2027: Decisions expected on revenue protection strategy and incident and crisis response management plan Report 1.7, P28
January 2027: Award of Tranche 1 local service contracts targeted Report 1.8, P31
5 September 2027: Tranche 1 franchised bus services due to commence in Doncaster and parts of Sheffield Report 1.1, 1.8, P31, 4.1
Plain English for the jargon
Bus franchising: A model where the local authority decides routes, fares, timetables and service standards and contracts bus operators to run services, rather than operators running commercially chosen services.
Tranche 1: The first phase of franchised bus services in South Yorkshire, covering Doncaster and parts of Sheffield, due to start on 5 September 2027.
Anchor franchise contracts: The main Tranche 1 bus service contracts, drawn from services currently run from Leger Way depot in Doncaster and Olive Grove depot in Sheffield, with the award decision reserved to the MCA board.
CRSTS1 and CRSTS2: City Region Sustainable Transport Settlement funding rounds from the Department for Transport, providing the agreed capital budgets for franchising.
TCR: Transforming Cities Fund related funding that forms part of the agreed capital budget alongside CRSTS2.
BSR: Business Services Review, a workstream reviewing SYMCA's existing business services and supporting technology to design the operating model for franchising.
CPO: Compulsory Purchase Order, a legal process the MCA has authorised to acquire Olive Grove depot in Sheffield.
ZEB: Zero emission bus funding, the source of additional grants SYMCA may use to support electric bus deployment.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item418
Resolved
RESOLVED that the Board: 1. Note the progress made towards the delivery of bus franchising in South Yorkshire, since March 2025; 2. Note and endorse the bus franchising high level programme and milestones set out in exempt Appendices A and B; 3. Endorse the features of Tranche 1 bus service delivery set out in paragraph 1.6; 4. Delegate decision making which supports maintaining the stability of the current bus network during the transition to bus franchising to the Executive Director of Transport in conjunction with the Executive Director of Resources and Investment subject to such decisions being within the MCA’s approved budget; 5. Delegate the acceptance of future grant funding from external sources which supports the delivery of bus franchising and zero emission bus deployment to the Executive Director of Resources and Investment; 6. Note the Officer Scheme of Delegation will facilitate the required decision making to deliver this programme provided such decisions are within budget and policy, with key decisions being taken in consultation with the Portfolio Lead (Mayor), and where appropriate the MCA Member for the area subject to the decision; 7. Note that bus franchising capital funding and progress against programme will be assured through the MCA’s Investment Board and Performance Board; 8. Note that the decision to award anchor franchise contracts will remain a future decision of the MCA board.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
This report provides an update on progress towards the delivery of bus franchising in South Yorkshire. It sets out the programme and expectations for delivery, in line with the March 2025 franchising decision. It seeks authority to delegate the decision-making in relation to the delivery of the programme to South Yorkshire MCA officers in conjunction with the Mayor of South Yorkshire, within agreed financial parameters. What does this mean for businesses, people and places in South Yorkshire?
The transition to bus franchising is a critical part of the objective to significantly improve public transport services and deliver an integrated public transport system for South Yorkshire. Doing so will support the region’s growth and inclusion strategies.
Recommendations
It is recommended that the Board: 1. Note the progress made towards the delivery of bus franchising in South Yorkshire, since March 2025; 2. Note and endorse the bus franchising high level programme and milestones set out in exempt Appendices A and B; 3. Endorse the features of Tranche 1 bus service delivery set out in paragraph 1.6; 4. Delegate decision making which supports maintaining the stability of the current bus network during the transition to bus franchising to the Executive Director of Transport in conjunction with the Executive Director of Resources and Investment subject to such decisions being within the MCA’s approved budget; 5. Delegate the acceptance of future grant funding from external sources which supports the delivery of bus franchising and zero emission bus deployment to the Executive Director of Resources and Investment; 6. Note the Officer Scheme of Delegation will facilitate the required decision making to deliver this programme provided such decisions are within budget and policy, with key decisions being taken in consultation with the Portfolio Lead (Mayor), and where appropriate the MCA Member for the area subject to the decision; 7. Note that bus franchising capital funding and progress against programme will be assured through the MCA’s Investment Board and Performance Board; 8. Note that the decision to award anchor franchise contracts will remain a future decision of the MCA board. ________________________________________________________________________
Consideration by any other Board, Committee, Assurance or Advisory Panel Overview and Scrutiny Committee 2 September 2025
Background
1.1The Mayor of South Yorkshire, at the MCA board meeting on 18th March 2025, supported recommendations by South Yorkshire leaders to proceed to make a bus franchising scheme for South Yorkshire. This means that the bus system in South Yorkshire will return to public control, beginning in Doncaster and parts of Sheffield from September 2027.
1.2Following the decision, SYMCA commenced work to develop a delivery programme for bus franchising and has started the process of building the delivery team.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.