South Yorkshire Mayoral Combined Authority
Audit, Standards and Risk Committee, Thursday 4 December 2025 at 10.30am

Risk Monitoring Report & Risk Management Framework Refresh

Noted Finance 2 papers

AI summarySouth Yorkshire MCA's Audit, Standards and Risk Committee noted the updated Risk Management Dashboard and a refreshed Risk Management Framework, with further review of level 2 risks due by 11 December.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRisk Management Framework refresh noted
MoneyNo specific financial implications stated
What happens nextLevel 2 risk reviewNext review cycle ends 11 December
Who it affectsMCA risk governanceAll teams across the organisation

What was decided

The committee noted the Risk Management Dashboard and the update on the review of the Risk Management Framework and assurance mapping progress. Report P4

The committee noted a refreshed framework, first introduced in 2022, that renames Level One risks from Corporate to Strategic, splits Level Two risks into four groups, and introduces separate Level Three risk registers. Report 1.2, P12

Why

The organisation has expanded and taken on greater responsibilities, and the existing framework needed to evolve to remain fit for purpose. Report 1.1

The refresh draws on lessons learned since 2022 and aims to better align risk management with strategic objectives and a more dynamic risk landscape. Report 1.2

Technological and Cyber Security and Health, Safety and Wellbeing are now distinct risk categories, reflecting organisational priorities in these areas. Report P12

What happens next

The next risk cycle will review all level 2 risks, create additional level 3 risk register environments, and establish further parent/child risk relationships. Report 2.3

Level 2 risks with medium/high or high residual scores will be included in the January dashboard, once the current review cycle ends on 11 December. Report P16

The newly established Director's Operational Group will oversee assurance mapping and improvement actions, with results feeding into the Annual Governance Review in quarter 4. Report P21, P22

Implications

  • Risk: Failure to effectively manage risk could have significant financial and reputational impact for the MCA, although no specific financial risk implications are identified. Report 5.1
  • Legal: There are no legal implications arising from the report. Report 6.1
  • Equalities: There are no equality and diversity implications arising from the report. Report 8.1
  • Climate: There are no climate change implications arising from the report. Report 9.1
  • Staffing: There are no human resources implications arising from the report. Report 7.1

Who and where

  • Teams across the South Yorkshire Mayoral Combined Authority involved in risk management Report 1.1
  • Director's Operational Group, with new oversight of assurance mapping Report P21
  • Residents and businesses in South Yorkshire, through better governance and decision making Report P3

Timeline

  • 2022: Original Risk Management Framework implemented Report 1.2
  • 11th December: Current level 2 risk review cycle ends Report P16
  • January: Level 2 risks with medium/high or high residual scores to appear in the dashboard Report P16
  • Quarter 4: Assurance mapping results feed into the Annual Governance Review Report P22

Plain English for the jargon

  • Level One Risk: Strategic risks, renamed from Corporate risks under the refreshed framework.
  • Level Two Risk: Operational risks, now split into four groups: Public Service Delivery, External Change Programmes, Internal Change Programmes, and Compliance and Corporate Performance.
  • Level Three Risk Register: New, separate registers allowing functional areas to manage risk at a more granular level.
  • Assurance Mapping: A process identifying assurance sources across three lines of defence, recorded in the 4Risk system.
  • 4Risk: The system used by the MCA to record risk and assurance data.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item470

Resolved

RESOLVED : That the report be noted.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to Audit, Standards and Risk Committee

Executive summary

This report provides the Risk Management Dashboard and an update on the review of the Risk Management Framework.

What does this mean for businesses, people and places in South Yorkshire?

Effective risk management is a key principle of good governance and decision making, which enables the MCA to pursue its ambitions and objectives in the most effective and efficient way, bringing about better outcomes for residents and businesses in South Yorkshire.

Recommendations

Members are asked to consider the Risk Management Dashboard, note the update on the review of the Risk Management Framework and the progress on assurance mapping. ________________________________________________________________________

Consideration by any other Board, Committee, Assurance or Advisory Panel None

Background

1.1As the organisation has expanded, matured, and assumed greater responsibilities, it became clear that the existing risk management framework needed to evolve to remain fit for purpose. Recognising this, a comprehensive review of the framework has been undertaken, engaging teams across the organisation to ensure a holistic understanding of current and emerging risks, as well as the practical realities faced by different functions.

1.2The review has resulted in reconfigured framework that is suitable for present needs and is also future proofed against anticipated challenges. These enhancements draw on lessons learned since the Framework was originally implemented in 2022, during which the organisation has worked diligently to strengthen its risk culture. By leveraging these experiences, the revised framework is now better aligned with strategic objectives, more responsive to a dynamic risk landscape, and positioned to support continued growth and success.

2. Key Issues

Evolution of the Risk Management Framework

2.1What has changed and why?

2.2The table below outlines the key changes to the Risk Management Framework:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ASRC Dashboard December v5Appendix A 549 KB Download
PDF
Risk Monitoring Report & Risk Management Framework RefreshReport 187 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
PL
Councillor Phillip Lofts LAB Barnsley MBCChair, present
DP
David Phillips Independent MemberVice-Chair, present
JB
Councillor Jamie Baggaley LAB Rotherham MBCCommittee Member, present
JC
Councillor Jason Charity REF City of Doncaster CouncilCommittee Member, absent
ML
Councillor Mike Levery LIBDEM Sheffield City CouncilCommittee Member, present
SW
Steve Wragg Chair of Joint Independent Audit CommitteeCommittee Member, present
PS
Paul Schofield Independent MemberCommittee Member, present
SA
Councillor Sarah Allen LAB Rotherham MBCReserve
SC
Councillor Simon Clement-Jones LIBDEM Sheffield City CouncilReserve
FJ
Councillor Frank Jackson REF City of Doncaster CouncilReserve
MO
Councillor Martin O’Donoghue LAB Barnsley MBCReserve
HL
Henry LauPublic, present

All 13 on the meeting page

On this subject at South Yorkshire Mayoral Combined Authority

Search all
  1. Risk Monitoring Report & Risk Management Framework RefreshThis decision
  2. Risk Monitoring ReportNoted
  3. Risk Monitoring ReportNoted
  4. Risk Monitoring ReportNoted
  5. Risk Monitoring ReportNoted
  6. Risk Monitoring Report (Dashboard)Noted

More from South Yorkshire Mayoral Combined Authority Audit, Standards and Risk Committee

All decisions
MeetingDecisionOutcome
9 Jul 2026 Appointment of Chair and Vice-Chair, appointments to Transport Risk Working GroupThat Councillor Mike Levery be appointed Chair and David Phillips be appointed Vice-Chair of the Audit, Standards and... Decided Open
9 Jul 2026 Questions from Members of the PublicThat the questions and responses be noted. Noted Open
9 Jul 2026 Terms of ReferenceThat the report be noted. Noted Open
9 Jul 2026 Health and Safety UpdateThat the report be noted. Noted Open
9 Jul 2026 Bus Franchising UpdateThat the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies