Integrated Settlement: Update and Outcomes Framework
ApprovedCommittee2 papers
AI summarySouth Yorkshire MCA Board approves near-final Integrated Settlement Outcomes Framework, unlocking around £1.3 billion over four years from April 2026, and delegates final sign-off to its Chief Executive.
Written from the decision and the officer reportPDF Pro
OutcomeApproved
Moneyc.£1.3 billion over 4 yearsTotal Integrated Settlement funding package over the next four years
What happens nextFunds expected 15 April 2026Government to publish ISOF in late March 2026; funding flexibility paper to follow
Who it affectsSouth Yorkshire businesses, people and placesOutcomes will guide investment and allow public accountability for delivery
What was decided
The Board approved the Integrated Settlement Outcomes Framework in its near-final draft, which runs from April 2026 to March 2029 and covers six thematic policy areas. Report P11, P3, 1.2
The Board delegated authority to the MCA's Chief Executive Officer, in consultation with the Mayor, to finalise the framework and agree outstanding targets with government, and to the S73 Officer to accept the funding. Report P12, 1.9, 1.10
The Board noted the readiness work and the emerging findings of the Government's assessment, which found SYMCA is at a 'building to embedded' system level. Report P13, 1.13
Why
The Integrated Settlement is the most significant change in SYMCA's funding environment since 2014, replacing fragmented streams with a more consolidated and flexible arrangement. Report P1, 1.1
Agreeing an outcomes framework is required in return for the new settlement, so that the MCA can be held to account for delivery of outcomes, indicators and targets. Report P2, P9, 6.1
A small number of targets, including active travel and A, B and C road maintenance, are still being negotiated with government, so finalisation is being delegated. Report 1.5, 1.6, 1.9
What happens next
SYMCA expects to receive Integrated Settlement funds on 15 April 2026, with the S73 Officer delegated to accept the funding. Report 1.10
Officers will bring a proposal on funding flexibilities to a future Board, and a paper on the South Yorkshire Strategy is scheduled for the March 2026 MCA Board. Report P7, 1.15
The 2026/27 Budget report, including updated Integrated Settlement quantums and Improvement Plan resourcing, will be presented to the March 2026 MCA Board for approval. Report 5.3, 5.6
The money
c.£1.3 billion over the next 4 years Total Integrated Settlement funding package, providing medium term financial planning certainty Report 5.1
Options considered
Chosen: Approve the ISOF in its near-final draft and delegate finalisation of outstanding targets. Small number of targets, including active travel and road maintenance, are still under discussion with government and need later agreement Report 1.5, 1.6, 1.9
Chosen: Delegate authority to the S73 Officer to accept the Integrated Settlement funding. Funds are expected on 15 April 2026 and need to be accepted on the MCA's behalf Report 1.10
Chosen: Note the readiness work and emerging findings of the Government assessment. The assessment broadly agreed with SYMCA's self-assessment, with two near-term recommendations to address Report 1.13, 1.15
Implications
Financial: Unlocks around £1.3 billion over four years and gives significant funding flexibility to move money between pillars, with new financial reporting requirements to central government. Report 5.1, 5.5
Legal: An agreed ISOF is integral to the Integrated Settlement process; the readiness work raises no direct legal implications. Report 6.1, 6.2
Staffing: The Integrated Settlement Improvement Plan will require additional MCA capacity and capability in the near term, with resource provided in the accompanying budget report. Report 5.6, 7.1
Equalities: No specific equality and diversity implications identified. Report 8.1
Climate: Environment and climate change is one of six thematic areas, but Integrated Settlement funding for it is minimal and limited to oversight of the Local Nature Recovery Strategy. Report 9.1, 1.2
Risk: Some targets were agreed before delivery plans were finalised, creating a risk of compromising investment flexibility; targets can be renegotiated by exception at six-monthly programme boards. Report 2.4, 2.5
Other: Digital and Technology Services will need to strengthen joined-up information management and reduce manual processes to meet increased reporting expectations. Report 10.2, 10.3
Who and where
Businesses, people and places in South Yorkshire Report P8, P10
The four South Yorkshire local authorities, engaged throughout ISOF development Report P4, 1.3, 3.1
The Overview and Scrutiny Committee and Audit, Standards and Risk Committee Report P14, 3.2
Central government departments, which will receive six-monthly progress reports Report 2.5, 2.6
Timeline
Summer 2025: SYMCA agreed principles with the Mayor, Executive Leadership team and Local Authorities to guide ISOF development Report 1.3
30 September 2025: First draft of the ISOF submitted to Government Report 1.4
14 November 2025: Informal sessions held with Overview and Scrutiny Committee and Audit, Standards and Risk Committee Report P14, 3.2
25 November 2025: Formal update to the Overview and Scrutiny Committee Report P14, 3.2
26 November 2025: Government published scope and quantum of Integrated Settlement funding Report 2.1
28 January 2026: Informal session with the Overview and Scrutiny Committee Report P14
13 February 2026: Final draft of the ISOF submitted to Government Report 1.4
20 February 2026: Small number of further amends submitted to Government Report 1.4
Late March 2026: Government expected to publish the ISOF and Integrated Settlement Outcomes Frameworks for all eligible MCAs, subject to Ministerial approval Report 4.1, 11.1
17 March 2026: Further Overview and Scrutiny Committee meeting Report P14
24 March 2026: MCA Board meeting; verbal update on any further ISOF developments; Budget report and South Yorkshire Strategy paper scheduled Report 1.8, 5.3, 1.15
April 2026 to March 2029: Period covered by the Integrated Settlement Outcomes Framework Report P3
Later in 2026: Active travel targets to be agreed with government once CWIS3 targets are finalised Report 1.6
2027: A, B and C road maintenance targets to be agreed in line with forthcoming monitoring methodology changes Report 1.6
15 April 2026: SYMCA expects to receive Integrated Settlement funds Report 1.10
Plain English for the jargon
Integrated Settlement: A consolidated funding arrangement replacing previously fragmented funding streams, available to established mayoral strategic authorities from April 2026.
Integrated Settlement Outcomes Framework (ISOF): A structured approach to defining, measuring and reporting on the MCA's performance on Integrated Settlement delivery from April 2026 to March 2029.
MSA: Mayoral Strategic Authority.
S73 Officer: The officer designated under Section 73 of the Local Government Act 1985 with responsibility for the proper administration of financial affairs.
CWIS3: Cycling and Walking Investment Strategy 3, the national framework informing active travel targets.
PwC: The Government-appointed independent body that conducted SYMCA's external readiness assessment.
Local Growth Plan: SYMCA's plan for economic growth, developed alongside the South Yorkshire Strategy and the ISOF.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item462
Resolved
RESOLVED that the Board: Approves the contents of the Integrated Settlement Outcomes Framework in its near-final draft, attached. That, given the small number of outstanding targets under discussion with government, that the Board delegates authority to the MCA’s Chief Executive Officer in consultation with the Mayor to finalise the Integrated Settlement Outcomes Framework and agree any outstanding targets with government, and delegates authority to the S73 Officer to accept the funding. That the Board notes the work on readiness and the emerging findings of the Government assessment.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting.Source: governance.southyorkshire-ca.gov.uk
Follow this further
Built from South Yorkshire Mayoral Combined Authority's papers
The Integrated Settlement represents the most significant change in SYMCA’s funding environment since its inception in 2014, moving us away from a fragmented funding structure to a more consolidated and flexible one.
In return for this new settlement and the associated flexibilities, the MCA is required to agree a set of outcomes with Government to be delivered via the resource provided.
The process through which these outcomes are agreed and measured is referred to as the Integrated Settlement Outcomes Framework (ISOF). The ISOF provides a structured approach to defining, measuring and reporting on the MCA’s performance on Integrated Settlement delivery from April 2026 to March 2029.
We developed outcomes, indicators and targets for the ISOF in discussion with the Mayor, Leaders, central government, our four local authorities and internal delivery teams. The ISOF was developed alongside the South Yorkshire Strategy and our Local Growth Plan to ensure that the outcomes we agree in the ISOF align with the wider ambitions set out in the strategy and growth plan. The ISOF is attached for approval by MCA Board.
In preparation for receiving the Integrated Settlement, we have also taken forward programmes of work to ensure we are organisationally and culturally ready. This includes conducting a self-assessment of our readiness for the new flexibilities and associated responsibilities, and the production of an improvement plan to ensure we invest in the required systems, capabilities and capacity required to make best use of them.
Government subsequently assessed our readiness, and while the report is not yet finalised it largely agreed with our self-assessment, identifying areas of leading practice but other areas that require investment.
Government has provided two recommendations to be completed in the near-term, one on agreeing processes to support management of funding flexibilities and one on finalising the South Yorkshire Strategy. We intend to work with local authority officers in the coming weeks to allow a proposal to be brought forward to Board on funding flexibilities. A paper on the South Yorkshire Strategy is scheduled for the March MCA Board.
What does this mean for businesses, people and places in South Yorkshire?
The ISOF will be included in our Corporate Plan and our Assurance Framework and will be published by Government. The ISOF will guide investment decisions and allow people to hold us to account for delivery against the Integrated Settlement.
The Integrated Settlement readiness assessment provides independent assurance to people in South Yorkshire that SYMCA is ready to receive the Integrated Settlement and has suitable processes in place to deliver value for money.
Recommendations
1. That the Board approves the contents of the Integrated Settlement Outcomes Framework in its near-final draft, attached.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mayoral Combined Authority Board at South Yorkshire Mayoral Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
National Housing Development FundRESOLVED that the Board: 1. Welcome the £118,270,000 National Housing Delivery Fund (NHDF) award to SYMCA as part of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.