South Yorkshire Mayoral Combined Authority
Audit, Standards and Risk Committee, Thursday 9 July 2026 at 10.30am

Assurance of the Capital Programme (focus on delivery)

Noted Finance 2 papers

AI summarySYMCA Audit Committee notes £273m capital programme assurance, with over 200 schemes in delivery and improvement actions from a PwC readiness review.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted the capital programme presentation
Money£273m capital programmeLargest ever, includes Integrated Settlement for first time
What happens nextImplement improvement actionsFrom PwC IS Readiness Assessment, short to longer term
Who it affectsSouth Yorkshire regionOver 200 schemes in delivery, 90 in development

What was decided

The committee noted the contents of the presentation on capital programme delivery assurance. Report P6, P38

Why

The 2026/27 capital programme is the largest ever at £273m and, for the first time, includes the Integrated Settlement alongside existing programmes such as Brownfield Housing Fund and Gainshare. Report P2, 1.2

Large cash balances are held because government funding does not always match profiled delivery, and there are inherent risks in large-scale capital investment that need careful management. Report 2.1, 2.2

What happens next

The Performance Board will continue to identify emerging risks, work with delivery partners on mitigations, and drive delivery of the capital programme. Report 2.3

SYMCA will implement the short, medium and longer term improvement actions identified in the PwC IS Readiness Assessment via an Improvement Plan that is being resourced. Report 2.4

The money

  • £273m 2026/27 capital programme value, the largest ever for SYMCA Report P2, 1.2

Implications

  • Risk: Inflationary pressures, exacerbated by supply chain issues linked to global events such as conflict in the Middle East and Ukraine. Report P15
  • Risk: Capacity and capability constraints among partner organisations and contractors may cause cost increases or delivery delays as many schemes enter delivery. Report P15
  • Risk: Statutory undertakings dependent on third parties, such as energy providers or Network Rail, can slow scheme delivery. Report P15
  • Risk: Outcomes of public consultation can change project scope, causing delays and cost changes. Report P15
  • Financial: Holding large cash balances during high interest rate periods can generate treasury management income that is reinvested into the region. Report 2.1

Who and where

  • Delivery partners and contractors across South Yorkshire Report P15
  • Statutory undertakers such as energy providers and Network Rail Report P15
  • Residents and businesses in South Yorkshire who may respond to public consultations on projects Report P15
  • Recipients of existing programmes including Brownfield Housing Fund and Gainshare Report P2, 1.2

Timeline

  • Financial year 2026/27: Capital programme value stands at £273m, including Integrated Settlement for the first time Report 1.2

Plain English for the jargon

  • SYMCA: South Yorkshire Mayoral Combined Authority
  • IS: Integrated Settlement, a form of government capital funding included in the programme for the first time in 2026/27
  • Gainshare: An existing SYMCA funding programme already in active delivery
  • Brownfield Housing Fund: An existing government-funded programme for housing on previously developed land, in active delivery
  • Performance Board: The SYMCA body that identifies risks, works with delivery partners on mitigations, and drives delivery of the capital programme
  • IS Readiness Assessment: An assessment by PwC of SYMCA against financial and performance management criteria, with a series of improvement actions
  • Development gateways: Stages through which project ideas move into the investment pipeline before entering delivery
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the report be noted.
Word for word from the decision South Yorkshire Mayoral Combined Authority published for this meeting. Source: governance.southyorkshire-ca.gov.uk

Follow this further

Built from South Yorkshire Mayoral Combined Authority's papers

What the report saysPro

Report to Audit, Standards and Risk Committee

Executive summary

The purpose of the presentation is to provide assurance to Audit Standards and Risk Committee on the delivery of the capital programme.

The 2026/27 capital programme is the largest ever for SYMCA at a value of £273m. For the first time it includes the Integrated Settlement (IS) as well as the wide range of existing programmes already in active delivery such as Brownfield Housing Fund and Gainshare.

There are currently over 200 schemes in delivery and over 90 in development gateways.

The presentation at appendix 1 provides an overview of: • how we receive funding into the capital programme, • how project ideas are generated and enter the investment pipeline, • examples of delivery challenges, • how we monitor and manage programme performance, including the role of Performance Board.

The presentation concludes with details of the improvement actions recommended in the IS Readiness Assessment Report in relation to financial and performance management.

Recommendations

That the Committee: 1. Notes the content of the presentation

Consideration by any other Board, Committee, Assurance or Advisory Panel N/A

1. Background and Purpose

1.1The capital programme is the means by which we can deliver investment into capital assets such as roads, buildings, equipment and infrastructure to ensure that the region has the right tools to tackle productivity challenges and provide the right platform to give people and businesses a chance to thrive in South Yorkshire.

1.2SYMCA receives significant capital funding directly from government, in financial year 2026/27 the capital programme value stands at £273m. This includes for the first time the Integrated Settlement (IS) as well as the wide range of existing programmes already in active delivery across the region, such as Brownfield Housing Fund and Gainshare. There are over 200 projects in delivery and more than 90 in development gateways.

1.3The purpose of the presentation is to provide assurance to Audit, Standards and Risk Committee on the delivery of the capital programme. The presentation focuses on the following: • How we receive funding into the capital programme, • How project ideas are generated and enter the investment pipeline, • Examples of delivery challenges, • How we monitor and manage programme performance, including the role of Performance Board.

2. Key Issues

2.1The scale of the capital programme investment and the way in which it is paid by government means that SYMCA holds large cash balances as the receipt of funding does not necessarily reflect profiled or planned delivery. This has benefits in that during periods of high interest rates increased income from treasury management can be reinvested into the region.

2.2There are however inevitable challenges in the delivery of large-scale capital investment and these risks need to be carefully managed across the programme. Examples of these are outlined in Appendix 1 and include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
12.i. Appendix 1: Assurance on the Capital ProgrammeAppendix 353 KB Download
PDF
Assurance of the Capital Programme (focus on delivery)Report 216 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 19 attended
JB
Councillor Jamie Baggaley LAB Rotherham MBCCommittee Member, present
SB
Councillor Sam Burdett REF Barnsley Metropolitan Borough CouncilCommittee Member, present
JC
Councillor Jason Charity REF City of Doncaster CouncilCommittee Member, apologies, sent representative
ML
Councillor Mike Levery LIBDEM Sheffield City CouncilCommittee Member, present
DP
David Phillips Independent MemberCommittee Member, present
PS
Paul Schofield Independent MemberCommittee Member, present
SW
Steve Wragg Chair of Joint Independent Audit CommitteeCommittee Member, present
SC
Councillor Simon Clement-Jones LIBDEM Sheffield City CouncilReserve
FJ
Councillor Frank Jackson REF City of Doncaster CouncilReserve, present as substitute
IB
Ian BagshawOfficer, in attendance
FD
Francesca DrydalePublic, in attendance
LT
Laurie ThomasOfficer, in attendance

All 19 on the meeting page

More from South Yorkshire Mayoral Combined Authority Audit, Standards and Risk Committee

All decisions
MeetingDecisionOutcome
9 Jul 2026 Appointment of Chair and Vice-Chair, appointments to Transport Risk Working GroupThat Councillor Mike Levery be appointed Chair and David Phillips be appointed Vice-Chair of the Audit, Standards and... Decided Open
9 Jul 2026 Questions from Members of the PublicThat the questions and responses be noted. Noted Open
9 Jul 2026 Terms of ReferenceThat the report be noted. Noted Open
9 Jul 2026 Health and Safety UpdateThat the report be noted. Noted Open
9 Jul 2026 Bus Franchising UpdateThat the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies