Draft Capital Programme 2016/17 to 2019/20

Approved Executive 6 papers

Cabinet approved this item on Tuesday 19 January 2016. Below is the council's own wording, with the papers it was decided on.

Item560

Resolved

- 1. That the current approved Programme for 2016/17 to 2018/19 of £129.6m, as set out in Appendix 1 to the submitted report, be noted. 2. That the changes to the approved Programme as set out in Appendix 2 to the report, be noted. 3. That the proposed new schemes and additions to the Capital Programme for the period 2016/17 to 2019/20 totalling £52.7m of which £44.7m is for the General Fund and £8.0m for the Housing Revenue Account, as set out in Appendices 6 and 7 to the report, be endorsed. 4. That it be noted that the proposed new schemes and additions, as set out in Appendices 6 and 7 to the report, and other adjustments, as set out in Appendix 2 to the report, will result in a proposed capital programme of £177.6m for 2016/17 to 2019/20. 5. That it be noted that, of the total programme of £177.6m for the period 2016/17 to 2019/20, the level of external funding supporting this programme is £59.9m. 6. That it be noted that a final review is being undertaken on the 2015/16 projected outturn and that the results will be included in the report to Cabinet on 11 February 2016. Reason for Decision The proposed Capital Programme is compiled from a number of individual projects which either contribute to the delivery of the Council’s objectives and priorities or enhance the Council’s infrastructure. Other Options The proposed Capital Programme is compiled from a number of individual projects, any of which can be agreed or rejected independently of the other projects. Note:- This is an Executive Function, save the approval of the final budget following Cabinet on 11 th February 2016 is a Council Function. Referred direct to all three Scrutiny Committees. Executive Councillor:- Woodley
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1The purpose of this report is for Members to consider a draft programme of capital projects for the period 2016/17 to 2019/20 that can be submitted to Council for approval.

Recommendation

That the Cabinet:

2.1Note the current approved Programme for 2016/17 to 2018/19 of £129.6m (Appendix 1);

2.2Note the changes to the approved Programme as set out in Appendix 2;

2.3Consider and approve the proposed new schemes and additions to the Capital Programme for the period 2016/17 to 2019/20 totalling £52.7m of which £44.7m is for the General Fund and £8.0m for the Housing Revenue Account (Appendices 6 and 7);

2.4Note that the proposed new schemes and additions (Appendices 6 and 7) and other adjustments (Appendix 2) will result in a proposed capital programme of £177.6m for 2016/17 to 2019/20 (Appendix 8);

2.5Note that, of the total programme of £177.6m for the period 2016/17 to 2019/20, the level of external funding supporting this programme is £59.9m (paragraph 7.1).

2.6Note that a final review is being undertaken on the 2015/16 projected outturn and that the results will be included in the report to Cabinet on 11 February 2016;

Draft Capital Programme 2016/17 to 2019/20 Page 1 of 10 Report No: CS28 (ja) 2.7 Refer this report as approved to all Scrutiny Committees and then to Budget Cabinet on 11 February 2016.

Background

3.1Capital expenditure is defined as expenditure incurred on the enhancement, acquisition or creation of assets needed to provide services, such as houses, schools, vehicles etc. This is in contrast to revenue expenditure which is spending on the day to day running costs of services such as employee costs and supplies and services. Capital grants, borrowing and capital receipts can only be spent on capital items and cannot be used to support the revenue budget. However, it should be noted that revenue funding can be used to support capital expenditure.

3.2Under the Local Government Act 2003, from 1 April 2004, each authority can determine how much it can borrow within prudential limits (unsupported borrowing). The Government does have powers to limit the aggregate for authorities for national economic reasons, or for an individual authority.

3.3Unsupported borrowing is not specifically financed by capital grant and no longer as a separate stream in the Government revenue grant. However, the Council has full discretion on how it allocates its formula grant funding. Therefore, any unsupported borrowing undertaken is financed from the total available resources to the Council from both Grant and Council Tax in the setting of its Council tax.

4. Capital Programme 2015/16 to 2018/19 - Movements

4.1The Council’s current agreed capital programme for 2015/16 and future years is attached as Appendix 1 and totals £179.4m.

4.2Movements and proposed new schemes and additions since the agreement of the revised programme in November 2015 have an overall effect of increasing the capital programme by £45.3m and are set out in Appendix 2, with more detail in Appendices 3 to 7.

5. Spending Plans 2016/17 to 2019/20

The proposed additions to the Capital Programme for 2016/17 to 2019/20 of £52.7m are set out in Appendix 6, with the details of each scheme and its funding explained in Appendix 7. The key areas of investment and funding for the Council are identified in the sections below.

Draft Capital Programme 2016/17 to 2019/20 Page 2 of 10 Report No: CS28 (ja) 5.1 Education

5.1.1 In January 2015 the Government confirmed the Education Maintenance Capital allocations, Basic Needs Grant and Devolved Formula Capital (DFC) for 2015/16 and gave an indication that the same level of grant would be available for 2016/17 and 2017/18, subject to downwards adjustments as more schools convert to academy status.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approved Capital Programme November 2015Appendix 1 212 KB Download
PDF
Changes to Approved Capital ProgrammeAppendix 2 13 KB Download
PDF
Virements Between Approved SchemesAppendix 3 11 KB Download
PDF
Re-profiles Between YearsAppendix 4 18 KB Download
PDF
New External FundingAppendix 5 7 KB Download
PDF
Draft Capital Programme 2016/17 to 2019/20Report 127 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 23 attended
RW
Councillor Ron WoodleyChair, present
IG
Councillor Ian GilbertVice-Chair, present
AJ
Councillor Anne JonesCommittee Member, present
JM
Councillor James MoyiesCommittee Member, present
DN
Councillor David Norman MBECommittee Member, present
MB
Councillor Mary BetsonCommittee Member, present
MT
Councillor Martin TerryCommittee Member, apologies
RT
Rob TinlinOfficer, in attendance
JW
John WilliamsOfficer, in attendance
SH
Sally HollandOfficer, in attendance
SL
Simon LeftleyOfficer, in attendance
AL
Andrew LewisOfficer, in attendance

All 23 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Draft Capital Programme 2016/17 to 2019/20This decision
  2. Capital Programme AmendmentApproved
  3. Financial Performance Report for September 2025 (Period 6) - Changes to the Capital Investment ProgrammeApproved
  4. Capital Investment Programme 2019/20 to 2023/24Approved
  5. Draft Capital Investment Programme 2019/20 to 2023/24Noted
  6. Draft Capital Investment Programme 2019/20 to 2023/24Noted

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open