Draft Capital Programme 2016/17 to 2019/20

Noted Scrutiny 6 papers

Policy and Resources Scrutiny Committee noted this item on Thursday 28 January 2016. Below is the council's own wording, with the papers it was decided on.

Item613

Resolved

- That the following decisions of Cabinet be noted: “1. That the current approved Programme for 2016/17 to 2018/19 of £129.6m, as set out in Appendix 1 to the submitted report, be noted. 2. That the changes to the approved Programme as set out in Appendix 2 to the report, be noted. 3. That the proposed new schemes and additions to the Capital Programme for the period 2016/17 to 2019/20 totalling £52.7m of which £44.7m is for the General Fund and £8.0m for the Housing Revenue Account, as set out in Appendices 6 and 7 to the report, be endorsed. 4. That it be noted that the proposed new schemes and additions, as set out in Appendices 6 and 7 to the report, and other adjustments, as set out in Appendix 2 to the report, will result in a proposed capital programme of £177.6m for 2016/17 to 2019/20. 5. That it be noted that, of the total programme of £177.6m for the period 2016/17 to 2019/20, the level of external funding supporting this programme is £59.9m. 6. That it be noted that a final review is being undertaken on the 2015/16 projected outturn and that the results will be included in the report to Cabinet on 11 February 2016.” Note:- This is an Executive Function, save the approval of the final budget following Cabinet on 11th February 2016 is a Council Function. Executive Councillor:- Woodley
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Policy and Resources Scrutiny Committee

Purpose of report

1.1The purpose of this report is for Members to consider a draft programme of capital projects for the period 2016/17 to 2019/20 that can be submitted to Council for approval.

Recommendation

That the Cabinet:

2.1Note the current approved Programme for 2016/17 to 2018/19 of £129.6m (Appendix 1);

2.2Note the changes to the approved Programme as set out in Appendix 2;

2.3Consider and approve the proposed new schemes and additions to the Capital Programme for the period 2016/17 to 2019/20 totalling £52.7m of which £44.7m is for the General Fund and £8.0m for the Housing Revenue Account (Appendices 6 and 7);

2.4Note that the proposed new schemes and additions (Appendices 6 and 7) and other adjustments (Appendix 2) will result in a proposed capital programme of £177.6m for 2016/17 to 2019/20 (Appendix 8);

2.5Note that, of the total programme of £177.6m for the period 2016/17 to 2019/20, the level of external funding supporting this programme is £59.9m (paragraph 7.1).

2.6Note that a final review is being undertaken on the 2015/16 projected outturn and that the results will be included in the report to Cabinet on 11 February 2016;

Draft Capital Programme 2016/17 to 2019/20 Page 1 of 10 Report No: 2.7 Refer this report as approved to all Scrutiny Committees and then to Budget Cabinet on 11 February 2016.

Background

3.1Capital expenditure is defined as expenditure incurred on the enhancement, acquisition or creation of assets needed to provide services, such as houses, schools, vehicles etc. This is in contrast to revenue expenditure which is spending on the day to day running costs of services such as employee costs and supplies and services. Capital grants, borrowing and capital receipts can only be spent on capital items and cannot be used to support the revenue budget. However, it should be noted that revenue funding can be used to support capital expenditure.

3.2Under the Local Government Act 2003, from 1 April 2004, each authority can determine how much it can borrow within prudential limits (unsupported borrowing). The Government does have powers to limit the aggregate for authorities for national economic reasons, or for an individual authority.

3.3Unsupported borrowing is not specifically financed by capital grant and no longer as a separate stream in the Government revenue grant. However, the Council has full discretion on how it allocates its formula grant funding. Therefore, any unsupported borrowing undertaken is financed from the total available resources to the Council from both Grant and Council Tax in the setting of its Council tax.

4. Capital Programme 2015/16 to 2018/19 - Movements

4.1The Council’s current agreed capital programme for 2015/16 and future years is attached as Appendix 1 and totals £179.4m.

4.2Movements and proposed new schemes and additions since the agreement of the revised programme in November 2015 have an overall effect of increasing the capital programme by £45.3m and are set out in Appendix 2, with more detail in Appendices 3 to 7.

5. Spending Plans 2016/17 to 2019/20

The proposed additions to the Capital Programme for 2016/17 to 2019/20 of £52.7m are set out in Appendix 6, with the details of each scheme and its funding explained in Appendix 7. The key areas of investment and funding for the Council are identified in the sections below.

Draft Capital Programme 2016/17 to 2019/20 Page 2 of 10 Report No: 5.1 Education

5.1.1 In January 2015 the Government confirmed the Education Maintenance Capital allocations, Basic Needs Grant and Devolved Formula Capital (DFC) for 2015/16 and gave an indication that the same level of grant would be available for 2016/17 and 2017/18, subject to downwards adjustments as more schools convert to academy status.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approved Capital Programme November 2015Appendix 1 212 KB Download
PDF
Changes to Approved Capital ProgrammeAppendix 2 13 KB Download
PDF
Virements Between Approved SchemesAppendix 3 11 KB Download
PDF
Re-profiles Between YearsAppendix 4 18 KB Download
PDF
New External FundingAppendix 5 7 KB Download
PDF
Draft Capital Programme 2016/17 to 2019/20Report 131 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 37 attended
FA
Fiona AbbottSecretary, in attendance
IA
Ian AmbroseCouncil Staff, in attendance
MF
Councillor Mark FlewittChair, present
DG
Councillor David GarstonVice-Chair, present
BA
Councillor Bernard ArscottCommittee Member, present
BA
Councillor Brian AylingCommittee Member, present
MB
Councillor Margaret BortonCommittee Member, present
TB
Councillor Trevor ByfordCommittee Member, apologies, sent representative
DA
Councillor Dr. Alan CrystallCommittee Member, apologies, sent representative
LD
Councillor Lawrence DaviesCommittee Member, apologies
JG
Councillor Jonathan GarstonCommittee Member, apologies, sent representative
AH
Councillor Ann HollandCommittee Member, present

All 37 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Draft Capital Programme 2016/17 to 2019/20This decision
  2. Capital Programme AmendmentApproved
  3. Financial Performance Report for September 2025 (Period 6) - Changes to the Capital Investment ProgrammeApproved
  4. Capital Investment Programme 2019/20 to 2023/24Approved
  5. Draft Capital Investment Programme 2019/20 to 2023/24Noted
  6. Draft Capital Investment Programme 2019/20 to 2023/24Noted

More from Southend-on-Sea Policy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Minutes of the Meeting held on Thursday, 13th February 2025That the minutes of the meeting of the Committee held on Thursday, 13 th February 2025 be confirmed as a correct reco... Decided Open
31 Mar 2025 Additional Budget Considerations - 2025/26That the report to Cabinet be noted. Note: This is an Executive Function Cabinet Member: Councillor D Cowan (Leader o... Noted Open
13 Feb 2025 Minutes of the Meeting held on Thursday, 30th January 2025That the minutes of the meeting of the Committee held on Thursday, 30 th January 2025 be confirmed as a correct recor... Decided Open
13 Feb 2025 Corporate Performance Report Q3 2024/25 (October to December 2024) including Corporate Delivery Plan Actions update Q3 2024/25That the report to Cabinet be noted. Note: This is an Executive function Cabinet Member: Councillor D Cowan (Leader o... Noted Open
13 Feb 2025 Approval of the Annual Procurement Plan for 2025/26That the report to Cabinet be noted. Note: This is an Executive Function Cabinet Member: Councillor P Collins (Portfo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies