That the Carriage and Wagon Shed be leased to the new Shoebury Coastal Community Interest Company as detailed in section 4 of the submitted report. 2. That the Corporate Director of Place be authorised to advertise the opportunity to develop and manage the building for the benefit of residents and visitors to the borough if the Shoebury Coastal Community Interest Company is unable to take on the lease of the building by 30th September 2017. 3. That the Corporate Director of Place be authorised to negotiate and agree terms of any lease associated with the Carriage and Wagon Shed in consultation with the Council’s Asset Management and Legal Teams. 4. That the delivery of any fit-out of the Carriage and Wagon Shed, as set out in the Coastal Communities Funding application, be supported. 5. That the financial position, as set out in section 7.2 of the report, be noted. Reasons for Decision Leasing the building to a community interest company whose aims are to benefit the Shoeburyness area should ensure that the Carriage and Wagon Shed is managed for the benefit of the local area. It will help safeguard the Carriage and Wagon Shed for the future and minimise pressures on Council resources. Other Options As set out in the submitted report This is an Executive Function Called-in to Place Scrutiny Committee Executive Councillor – Holland
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1To make Members aware of the options for the future management and operation of the Carriage and Wagon Shed Shoebury Garrison.
1.2To request that Members agree to lease the building to a third party organisation.
Recommendations
2.2That the Carriage and Wagon Shed is leased to the new Shoebury Coastal Community Interest Company as detailed in section 4.
2.3Delegate authority to the Corporate Director of Place to advertise the opportunity to develop and manage the building for the benefit of residents and visitors to the borough if the Shoebury Coastal Community Interest Company is unable to take on the lease of the building by 30th September 2017.
2.4Delegate authority to the Corporate Director of Place to negotiate and agree terms of any lease associated with the Carriage and Wagon Shed in consultation with the Council’s Asset Management and Legal Teams.
2.5Support the delivery of any fit-out of the Carriage and Wagon Shed as set out in the Coastal Communities Funding application.
2.6Note the financial position as set out in section 7.2.
Carriage and Wagon Shed Options Page 1 of 7 Report Number: 16/058 3. Background
3.1As a result of the development of the former Shoebury Garrison site by Avant Homes, (formerly Country and Metropolitan Homes), the developer took on an obligation under the S106 agreement to refurbish one of the listed structures, the Carriage and Wagon Shed, for use as a visitor centre and community facility and to transfer the freehold to the Council on completion of the works (subject to a pre-emption for £1 in favour of the developer in the event of sale within 21 years). The original S106 agreement required the developer to provide a fully fitted out building. However, due to economic pressures, Development Control Committee agreed to vary the S106 in 2015 at the developer’s request. The variation limited the required works to the external shell of the building and the basic internal core and removed the previously agreed commuted sum to assist with the running and maintenance costs of the building. The building is due to transfer to the council in September 2016.
3.2Cabinet received a report in September 2011, and resolved to work with a community group or charity to manage the Gunners Park Heritage Centre once completed.
3.3Following the Cabinet resolution, a group was formed consisting of The Southend Educational Trust, Essex Wildlife Trust, The Shoebury Society and The Shoebury Archive. The aim of the group was to take on the management of the Carriage and Wagon Shed as a heritage centre, once the developer completed the refurbishment of the building. The group constituted itself as the Shoebury Heritage Centre Board.
3.4To provide financial stability for the Shoebury Heritage Centre Board, The Southend Educational Trust agreed to be the accountable body for the group.
3.5However, due to delays in the delivery of the building by the developer and changes within the Southend Educational Trust, in 2015 the Trust had to step down as the accountable body. Later that year, the Shoebury Heritage Centre Board was dis-banded.
3.6In July 2015, the Government asked for expressions of interest in setting up Coastal Community Teams. Local groups, businesses, and residents expressed an interest in setting up a Coastal Community Team for the Shoeburyness area. In October 2015 the Shoeburyness Coastal Community Team was set up.
3.7As a result of the creation of the Shoeburyness Coastal Community Team, a bid for Coastal Revival Funding was possible, allowing for work to be undertaken on option appraisals for the building and detailed internal layout to be undertaken. See Appendix 1 and 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.