- That Minute 285 be referred back to Cabinet for reconsideration, for the following reason – need for Cabinet to proceed with the original plan, as previously agreed by the Council. Note:- This is an Executive Function. Executive Councillor:- Salter [Note – During consideration of this agenda item, in accordance with Standing Order 44, the hour of 10 pm having been reached, the Committee agreed to continue with the remaining items of business on the agenda].
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
To present to Cabinet the outcome of the consideration of potential options for the capital re-development of Priory and Delaware Residential Care homes and the Viking Day Centre for people with a learning disability and determine preferred option(s) to take forward.
Recommendations
2.1To note that the Strategic Outline Case (SOC) at Appendix 1 has found that the preferred option is the re-development of the Viking Learning Disability Day Centre and the New Build of a 60 bed dual registered dementia care home on a single site (Priory).
2.2To agree the preferred option(s) identified above should be subjected to a fully costed Outline Business Case (OBC) to be presented to Cabinet in February 2017.
2.3To note that the Scheme will be financed by the Council with the Local Authority Trading Company, Southend Care, operating any new facility under a long term commercial lease from the Council.
3. Strategic Context and Background
3.1The future of Priory and Delaware residential Care homes and the Viking Day Centre for People with a Learning Disability and their potential capital re- development has been the subject of debate and consideration for a number of years, during that time a variety of potential options have been considered
3.2In July 2015 the architects ADP were appointed and completed their Feasibility Review. The preferred option identified was the redevelopment of Priory site. This option provided for a 60 bed dementia residential care home, Learning
Capital Re-development of Delaware, Priory and Viking 1 Disability Day Care Centre (45 places) plus the provision of 52 Extra Care apartments. The preferred option was on the Priory House site plus the adjoining school site and allows for the existing care home to remain operational until the new facilities come on-stream. This development would take place in two phases with the care home, Day Care Centre and 16 Extra Care flats in the first phase and the remaining 36 Extra care Flats in Phase 2.
3.3The Cabinet meeting held on 19 January 2016 agreed:
That a fully costed proposal be developed for the creation of new care facilities on the Priory site to be operated by the LATC, including full details of funding and financing implications, given that the independent Site Feasibility Study, as set out in Appendix 4 of the report, has established there is a clear Business Case
That the site Feasibility Study, which has demonstrated the feasibility of developing a dedicated dementia facility and re-provision of a learning disability day centre on the Priory House site, be noted and that officers be requested to develop fully costed proposals for submission to Cabinet later in the year.
3.4These decisions were confirmed by Council on 25 February 2016.
3.5The new political administration at a Member Briefing session held on 26 July 2016 agreed the following:
Take the opportunity to reappraise / ‘sense check’ potential options;
Consider potential alternative solution(s) to ensure: o Strategic fit o Meet future needs / demands o VFM / affordability
Strategic Outline case (SOC) to September Cabinet o Identifies preferred option(s) – to be subject to Outline Business Case (OBC)
This Cabinet Report considers those potential options that should be taken forward for more detailed consideration.
4. Findings & Conclusions of Strategic Outline Case (SOC)
4.1The SOC, following consideration of the existing facilities, need, demand and supply for these services, concluded the following:
It is acknowledged that Viking is beyond its useful life and requires replacement for which capital finds have been identified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.