Item588
Resolved
That the petitioner be thanked for compiling the petition. 2. That no further action be taken at this time for the reasons detailed in the report. Reason for Decision To reflect the existing practice of a need based work programme. Other Options Resurface the carriageway and footways. Resurfacing and major works are planned under a forward programme. Inclusion in the programme is based on the need for repairs and prioritised according to the condition and to include Ashleigh Drive in the programme prior to that planned will result in planned works for a road with more serious defects being delayed. Budgets are limited and need based prioritisation is a fair and consistent manner by which to manage the required works within these budgets. Note:- This is an Executive Function Referred direct to Place Scrutiny Committee Executive Councillor: Councillor Cox
Word for word from the decision Southend-on-Sea published for this meeting.
Source: democracy.southend.gov.uk