Southend-on-Sea Borough Council
Cabinet, Thursday 19 January 2017 at 2.00pm

Draft Capital Programme 2017/18 to 2020/21

Approved Executive 6 papers

Cabinet approved this item on Thursday 19 January 2017. Below is the council's own wording, with the papers it was decided on.

Item648

Resolved

- 1. That the current approved Programme for 2017/18 to 2019/20 of £125.4m, as set out in Appendix 1 to the submitted report, be noted. 2. That the changes to the approved Programme , as set out in Appendix 2 to the report, be noted. 3. That the proposed new schemes and additions to the Capital Programme for the period 2017/18 to 2020/21 totalling £59.1m of which £52.9m is for the General Fund and £6.2m for the Housing Revenue Account, as set out in Appendices 6 and 7 to the report, be endorsed. 4. That the proposed schemes subject to external funding approval for the period 2017/18 to 2020/21 totalling £42.6m as set out in Appendices 2 and 7 to the report, be endorsed. 5. That it be noted that the proposed new schemes and additions, as set out in Appendices 6 and 7 to the report, and other adjustments as set out in Appendix 2 to the report, will result in a proposed capital programme (excluding schemes subject to external funding approval) of £185.8m for 2017/18 to 2020/21. 6. That it be noted that of the total programme of £185.8m for the period 2017/18 to 2020/21, the level of external funding supporting this programme is £58.2m. 7. That it be noted that a final review is being undertaken on the 2016/17 outturn and that the results will be included in the report to Cabinet on 14 th February 2017. Reason for Decision The proposed Capital Programme is compiled from a number of individual projects which either contribute to the delivery of the Council’s objectives and priorities or enhance the Council’s infrastructure. Other Options The proposed Capital Programme is compiled from a number of individual projects, any of which can be agreed or rejected independently of the other projects Note :- This is an Executive Function save that approval of the final budget following Cabinet on 14th February 2017 is a Council Function. Referred direct to all three Scrutiny Committees. Executive Councillor :- Lamb
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1The purpose of this report is for Members to consider a draft programme of capital projects for the period 2017/18 to 2020/21 that can be submitted to Council for approval.

Recommendation

That the Cabinet:

2.1Note the current approved Programme for 2017/18 to 2019/20 of £125.4m (Appendix 1);

2.2Note the changes to the approved Programme as set out in Appendix 2;

2.3Consider and approve the proposed new schemes and additions to the Capital Programme for the period 2017/18 to 2020/21 totalling £59.1m of which £52.9m is for the General Fund and £6.2m for the Housing Revenue Account (Appendices 6 and 7);

2.4Consider and approve the proposed schemes subject to external funding approval for the period 2017/18 to 2020/21 totalling £42.6m (Appendices 2 and 7);

2.5Note that the proposed new schemes and additions (Appendices 6 and 7) and other adjustments (Appendix 2) will result in a proposed capital programme (excluding schemes subject to external funding approval) of £185.8m for 2017/18 to 2020/21 (Appendix 8);

2.6Note that, of the total programme of £185.8m for the period 2017/18 to 2020/21, the level of external funding supporting this programme is £58.2m (paragraph 7.1). Draft Capital Programme 2017/18 to 2020/21 Page 1 of 10 Report No: CE19 (ja) 2.7 Note that a final review is being undertaken on the 2016/17 projected outturn and that the results will be included in the report to Cabinet on 14 February 2017;

2.8Refer this report as approved to all Scrutiny Committees and then to Budget Cabinet on 14 February 2017.

Background

3.1Capital expenditure is defined as expenditure incurred on the enhancement, acquisition or creation of assets needed to provide services, such as houses, schools, vehicles etc. This is in contrast to revenue expenditure which is spending on the day to day running costs of services such as employee costs and supplies and services. Capital grants, borrowing and capital receipts can only be spent on capital items and cannot be used to support the revenue budget. However, it should be noted that revenue funding can be used to support capital expenditure.

3.2Under the Local Government Act 2003, from 1 April 2004, each authority can determine how much it can borrow within prudential limits (unsupported borrowing). The Government does have powers to limit the aggregate for authorities for national economic reasons, or for an individual authority.

3.3Unsupported borrowing is not specifically financed by capital grant and no longer as a separate stream in the Government revenue grant. However, the Council has full discretion on how it allocates its formula grant funding. Therefore, any unsupported borrowing undertaken is financed from the total available resources to the Council from both Grant and Council Tax.

4. Capital Programme 2016/17 to 2019/20 - Movements

4.1The Council’s current agreed capital programme for 2016/17 and future years is attached as Appendix 1 and totals £191.2m.

4.2Movements and proposed new schemes and additions since the agreement of the revised programme in November 2016 have an overall effect of increasing the capital programme by £55.8m and are set out in Appendix 2, with more detail in Appendices 3 to 7.

5. Spending Plans 2017/18 to 2020/21

The proposed additions to the Capital Programme for 2017/18 to 2020/21 of £59.1m are set out in Appendix 6, with the details of each scheme and its funding explained in Appendix 7. The key areas of investment and funding for the Council are identified in the sections below.

Draft Capital Programme 2017/18 to 2020/21 Page 2 of 10 Report No: CE19 (ja) 5.1 Education

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CE19-Appendix 1: Approved Capital Programme: November 16Appendix 146 KB Download
PDF
CE19-Appendix 2: Changes to Approved Capital ProgrammeAppendix 14 KB Download
PDF
CE19-Appendix 3: Virements Between Approved SchemesAppendix 12 KB Download
PDF
CE19-Appendix 4: Re-profiles Between YearsAppendix 19 KB Download
PDF
CE19-Appendix 5: New External FundingAppendix 13 KB Download
PDF
Draft Capital Programme 2017/18 to 2020/21Report 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
JL
Councillor John LambChair, present
AH
Councillor Ann HollandVice-Chair, present
AM
Councillor Andrew MoringCommittee Member, present
RT
Rob TinlinOfficer, in attendance
LS
Councillor Lesley SalterCommittee Member, present
JW
John WilliamsOfficer, in attendance
MF
Councillor Mark FlewittCommittee Member, apologies
TC
Councillor Tony CoxCommittee Member, present
SL
Simon LeftleyOfficer, in attendance
JC
Councillor James CourtenayCommittee Member, present
AL
Andrew LewisOfficer, in attendance
TB
Councillor Trevor ByfordCommittee Member, present

All 21 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Draft Capital Programme 2017/18 to 2020/21This decision
  2. Capital Programme AmendmentApproved
  3. Financial Performance Report for September 2025 (Period 6) - Changes to the Capital Investment ProgrammeApproved
  4. Capital Investment Programme 2019/20 to 2023/24Approved
  5. Draft Capital Investment Programme 2019/20 to 2023/24Noted
  6. Draft Capital Investment Programme 2019/20 to 2023/24Noted

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies