- That the contents of the report be noted, including that the project to replace the ageing social care case management would move forward on the basis of the amended ‘go live’ dates of October 2017 for Children’s Services and January 2018 for Adults Services (phase 1).
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1The purpose of this report is to update Members of Audit Committee on the nature and status of the project to fundamentally re-provide the Children & Adults Social Case Management systems. Care First will cease to be used in favour of the new Liquid Logic system.
Recommendation
2.1That Committee Members note the contents of this report. Namely, that the project to replace the ageing social care case management continues with ‘go live’ dates of October 2017 for Children’s Services and January 2018 for Adults Services.
Background
3.1The Department for People is in the process of a fundamental reposition of its case management system across both children’s and adult services. The chosen case management system is provided by Liquid Logic (LL).
Phase 1 of the project will see the transfer of all current CareFirst case recording activity to LL but critically include the automation of ‘end to end’ financial processes which are currently undertaken manually.
Automation will take place through the integration of two products:
- The Liquid Logic case management system - The Oxford Computer Consultants ContrOCC finance system
3.2The Project commenced in Dec 2014 when the department began a comprehensive review of alternative products available, the construction of the detailed requirement specification, the decision to go to market and, ultimately the procurement process.
Once the chosen provider was identified the cost of the software and the team to drive delivery was calculated to by £2.2m. The move from Care First to the Liquid Logic Case Management System in Social Care Page 1 of 5 The implementation phase began in March 2016.
3.3A Project Team came into being to drive the project forward and a Board established
3.4Overall, this is an ambitious project with Phase 1 not simply representing a like for like replacement of the existing CareFirst functionality but the introduction of 5 inter-related systems:
Children’s case management Adult’s case management Early Help Integrated finance children Integrated finance adults
3.5In October / November 2016 an internal audit was conducted by externally commissioned auditors from PWC entitled ‘Project Implementation Health Check’ and this assigned a rating of ‘partial’ in respect of the robustness of the project assurance citing the following areas as being in need of improvement:
Routine and systematic reporting to the Board of Progress against the project plans needed to be more robust to prevent project drift. Things could occur which could impact the overall delivery date. Risks and issues were not discussed by the Board on a routine basis. Benefits realisation resulting from the Project was not owned, overtly tracked and delivery monitored by the Board. Migration and testing identified as being crucial to the success of the project so roles and responsibilities needed to be clearly defined. Given the magnitude of the project there would be a need to identify going forward the ‘business readiness’ to adapt to the changes that were coming including the readiness of the support functions put in place post ‘go live’. Business readiness criteria would need to be defined and agreed. There was a recognition that there was a limited budget contingency, circa £30K unallocated against a budget of £2.2m.
The audit report was produced in October 2016 and steps taken to address the actions for improvement began.
3.6In December 2016 the Project Team was reconfigured as follows:
1 x dedicated PM 1 x dedicated Adult configuration expert 1 x dedicated Children’s configuration expert 1 x dedicated finance configuration expert 2 x trainers
The team continues to be supplemented by in-house resources via secondment.
3.7In simplistic terms the process of switching from one system to another involves
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.