Resolved
That the context and the actions being taken to address the issues arising from the Internal Audit Report, be noted.
Audit Committee noted this item on Wednesday 28 June 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the context and the actions being taken to address the issues arising from the Internal Audit Report, be noted.
1.1To update the Audit Committee on progress made in delivering the actions agreed in the Internal Audit Report issued in March 2017.
2.1The Audit Committee notes the context and the actions being taken to address the issues arising from this Internal Audit Report.
3. Audit Objective
3.1To assess whether the actions agreed in the original audit issued December 2014, have been implemented and are now effectively embedded into the day-to- day operation of the service.
4. Audit Recommendations
4.1The revisited report is included in Appendix 1.
5. Background or Operational Context
5.1The Forum is an innovative partnership between the Council, the University of Essex and South Essex College. Since it opened in 2013 it has been a great success, improving library provision for the public and students, underpinning academic opportunity in Southend and creating a new public square in the town centre.
The Library’s performance at the Forum since 2013 shows increased usage and the following key performance indicators support this position
Footfall has more than doubled since the move from Victoria Avenue. Focal Point Gallery has extended its range of exhibitions and activities and increased its profile and that of Southend internationally.
Report Title- The Forum Governance Arrangements Page 1 of 3 Report Number – 17/059 Elmer Square has become a new venue in the town, bringing live opera to Southend. Together, the Forum and Elmer Square have created a new quarter in Southend, unrecognisable by anyone who knew the old Farringdon car park. Both the College and University have seen increased student satisfaction, moving them to best in class and attracting more students to study in Southend.
5.2The Forum is leased and run by the Forum Management Company. This is a special purpose vehicle set up by the three partners. Each partner has equal voting rights. The Board of the Management Company meets quarterly. The Council has two directors on the board of the Management Company, who are always Council Members (currently Cllr Holland and Cllr Jarvis appointed through the council’s annual process). Council Officers also attend Board meetings.
5.2The SBC audit recommendations are clearly seeking to ensure the Council’s best interests. It should be acknowledged that the Forum Management Company is not bound by SBC or any other single partner, though has due regard to the points raised.
5.3The library at the Forum is run by the Council on behalf of the partners and is fully integrated into the Council’s Public Library Service.
6. Current position
6.1There are three recommendations in the audit report that have been identified as not implemented: R4 Governance arrangements should one of the partners withdraw, R5 reporting on benefits of the Library relocation at the Forum and R7 Updating financial regulations of the Forum Management Company. There are two partially implemented recommendations, R2 reporting progress to Council and R3 apportionment of costs.
6.2R4 - The partners signed up to a 99 year lease for the respective sections of the building. All three partners are large public sector organisations for all of whom The Forum is a strategic priority, and so they are unlikely to withdraw in the medium to long term. The partners have acknowledged that in the event of one partner leaving the partnership, all three would need to work towards delivering a smooth transition. This matter was covered in the last board meeting and will be revisited.
6.3R5 – The Forum library has demonstrated its benefits over the past 3.5 years since moving from Victoria Avenue. Performance is now monitored as part of business as usual within the Library service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 82 KB | Download |
PDF |
The Forum Governance ArrangementsReport | 94 KB | DownloadRead as text |
Follow Audit Committee at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2025 | Minutes of the Meeting held on Monday 27 January 2025That the Minutes of the Meeting held on Monday, 27 January 2025 be confirmed as a correct record and signed. | Decided | Open |
| 23 Apr 2025 | Minutes of the meeting held on Tuesday 25 February 2025That the Minutes of the Meeting held on Tuesday, 25 February 2025 be confirmed as a correct record and signed. | Decided | Open |
| 23 Apr 2025 | CIPFA Financial Management Code Action Plan Progress ReportThat the Council’s annual review against the expectations of CIPFA’s Financial Management Code and the assurance that... | Noted | Open |
| 23 Apr 2025 | Counter Fraud and Investigation Team Quarterly Performance ReportThat the performance of the Counter Fraud and Investigation Team over the last three months, be noted. Reasons for de... | Noted | Open |
| 23 Apr 2025 | Internal Audit Service Quarterly Performance ReportThat the progress made in delivering the 2024/25 Internal Audit Strategy and Plan, be noted. Reasons for decision: In... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.