Traffic Regulations Working Party approved this item on Thursday 14 September 2017. Below is the council's own wording, with the papers it was decided on.
That Cabinet Committee be recommended: 1. That, subject to the inclusion of Barnard Road and Eaton Road, the proposal to introduce a Permit Parking Area in the Bailey Road area, Leigh-on-Sea, as based on the streets consulted, be approved. 2. That the Deputy Chief Executive (Place) be authorised to publish the relevant statutory notice and undertake the necessary consultation for a traffic regulation order to introduce permit parking controls in the area around Bailey Road and, subject to there being no objections following statutory advertisement, to arrange for the order to be sealed and the proposals implemented. Any unresolved objections will be referred to a future meeting of the Traffic & Parking Working Party and Cabinet Committee for consideration.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1For the Traffic and Parking Working Party and the Cabinet Committee to consider the results of a consultation led by residents in the Baily Road area.
Recommendation
2.1That the Traffic and Parking Working Party consider the results presented and recommend to the Cabinet Committee to:
(a) Agree to a proposal for a Permit Parking Area to be introduced in the Bailey Road area as based on the streets consulted with the addition of Barnard Road and Eaton Road.
(b) Authorise the advertisement of the proposals and further authorise that in the event of there being no unresolved objections, confirm the Order as necessary and undertake the works.
(c) Note that any unresolved objections will be referred to a future meeting for consideration.
Background
3.1Local residents and the ward Councillors expressed concerns over an increased level of parking around the streets detailed in Appendix 1 to this report and sought advice as to how parking controls could be progressed.
3.2Officers provided information on the level of support required and questions residents should be asked and offered to analyse all results received.
3.3Residents have delivered a questionnaire within the affected area and received responses equating to 46% of those asked. After analysis, the results show 75% of residents responding are in support of parking controls.
3.4As the level of support has reached the set criteria, officers recommend the proposals be formally advertised, but to include Barnard Road and Eaton Road to contain controls within a discreet geographic area. Officers recommend this approach as advertising proposals to include potential Report Title: Bailey Road Area Permit Page 1 of 4 Report No: Parking Request additional streets at this stage allows for flexibility. In the event the additional streets are not in support of proposals, it is simple and cost effective to exclude these from the final proposed areas rather than add them at a later stage.
3.5If agreed, any works will be added to the work programme and progressed in date order according to the date of approval.
Reasons for recommendations
4.1The proposals aim to improve the parking opportunity for residents of the local area leading to improved management of parking.
5 Corporate Implications
5.1Contribution to Council’s Vision and Corporate Priorities.
5.1.1 Ensuring parking is managed to the maximum benefit while also providing areas of waiting restrictions to maintain clear areas at junctions is consistent with the Council’s Vision and Corporate Priorities of Safe, Prosperous and Healthy.
Financial implications
5.2.1 Costs for progression of the works if approved can be met from existing budgets.
Legal implications
5.3.1 The formal statutory consultative process will be completed in accordance with the requirements of the legislation.
5.4People Implications
5.4.1 Works required to progress the proposals and any resulting works will be undertaken by existing staff resources.
5.5Property Implications
5.5.1 None
Consultation
5.6.1 This report provides details of the outcome of the informal consultation process and seeks approval to undertake the statutory consultation.
5.7Equalities and Diversity Implications
5.7.1 Any implications will be taken into account in designing the schemes.
5.8Risk Assessment
5.8.1 The proposals will be designed to improve the operation of the parking scheme while maintaining highway safety and traffic flow and as such, are likely to have a positive impact. Report Title: Bailey Road Area Permit Page 2 of 4 Report No: Parking Request 5.9 Value for Money
5.9.1 Works associated with the proposal will be undertaken by the Council’s term contractors, selected through a competitive tendering process to ensure value for money.
5.10Community Safety Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Traffic Regulations Working Party at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.