Resolved
The Cabinet considered a report of the Deputy Chief Executive (Place) providing an update on the progress of the ‘Southend Central Area Transport Scheme (S-CATS).
Cabinet decided this item on Tuesday 19 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet considered a report of the Deputy Chief Executive (Place) providing an update on the progress of the ‘Southend Central Area Transport Scheme (S-CATS).
1.1To provide Cabinet with an update on the progress of the ‘Southend Central Area Transport Scheme (S-CATS)’.
1.2To advise Cabinet that two design options have been developed for S-CATS Phase 2 - London Road (between Queensway and College Way, refer to Appendix 1 for scheme extents) based on “concept design and vision statements” which were included in the S-CATS cabinet paper submitted on 15 March 2016 (Appendix 2). These design options were submitted with the Business Case application to the South Essex LEP for Local Growth Funding (refer to Appendix 3 for design options).
1.3To advise Cabinet that Design Option A has emerged as the preferred option as it scored higher on the scheme options matrix (refer to Appendix 4). However, Design Option B also meets all the project objectives and the final selection between the two options will be made upon conclusion of on-going stakeholder and public consultation.
2.1That Cabinet considers the proposed design options for London Road (between Queensway and College Way) and confirm that either of the two options can be taken forward to construction. This confirmation will allow selection of final design to be carried out in consultation with stakeholders and public.
2.2That Cabinet approves that drainage works can be started along London Road in September 2017 in preparation for the scheme construction to start in October 2017.
Report Title – Southend Central Area Transport Scheme – Page 1 of 7 Report Number – 17/069 Phase 2 2.3 That delegated authority be given to the Chief Executive and Deputy Chief Executive (Place), in consultation with the Leader of the Council and the Executive Councillor for Transport, Waste and Regulatory Services, to agree the final design option, Option A or Option B, selected after stakeholder and public consultation, be taken forward to implementation with a programmed commencement in October 2017, together with the advertisement of any necessary Traffic Regulation Orders.
3.1The Southend Central Area Transport Scheme (S-CATS) is a Local Growth Fund Scheme that has an allocation of £7m. The purpose of the scheme is to take forward aspects of transport and public realm infrastructure that are seen as necessary to support both housing and employment growth in the Town Centre.
The scheme is being developed in four phase:
S-CATS Phase 1: Phase 2: Phase 3: Phase 4: Victoria London Stud end Victoria Avenue Road Area of London Circus Improvements (between Road Area Queensway- (between London College Road Way and roundabout Victoria and College Circus) Way)
Financial 2016-2017 2017-2018 2018-2019 2019- Year 2020 Local £1m £2m £2m £2m Growth Fund
Phase 1 included a series of junction improvements along Victoria Avenue that better manages traffic into and out of the town centre. Access and public realm improvements along London Road, College Way, Queens Road and Elmer Avenue are the next steps to encourage more residents and tourists to visit and spend time in the Town Centre and for local businesses to flourish.
Therefore, Phase 2 focuses on London Road (between Queensway and College Way), which is the key western approach for pedestrians and cyclists into the town centre. Phase 2 also includes streetscape works on the College Way / Queens Road / Elmer Avenue route between London Road and The Forum / South Essex College.
The scheme supports and compliments the improvements made to A127/A13 Victoria Gateway and links to the junction improvement works along Victoria
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
C10702-102-SBC-LR-C-0017-A: SCATS ReportAppendix 1 | 457 KB | Download |
PDF |
Appendix 2Appendix 2 | 264 KB | Download |
PDF |
Appendix 3aAppendix 3a | 1.7 MB | Download |
PDF |
Appendix 3bAppendix 3b | 1.7 MB | Download |
PDF |
S-CATS Phase 2- Key Benefits Scheme option matrixAppendix 4 | 5.5 MB | Download |
PDF |
S-CATS (London Road Projects)Report | 102 KB | DownloadRead as text |
Follow Cabinet at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... | Decided | Open |
| 12 Oct 2026 | Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... | Noted | Open |
| 12 Oct 2026 | Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... | Noted | Open |
| 12 Oct 2026 | Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... | Agreed | Open |
| 12 Oct 2026 | Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.