- That the following decision of Cabinet be noted: “1. That the work undertaken by the Council and South Essex Homes with respect to Fire Safety, be noted and endorsed. 2. That the Council’s initial response to the Independent Review of Building Regulations and Fire Safety, be noted and endorsed. 3. That a further update be submitted to a future meeting of the Cabinet (Spring 2019).” Note: This is an Executive Function Cabinet Member: Cllrs Courtenay, Cox and Flewitt
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
This report sets out progress in delivering the Council’s Fire Safety Review, which was established following the Grenfell Tower fire on the 14th June 2017.
This is a further interim report as the Grenfell Tower Inquiry will not conclude their findings until later in 2018 (or beyond) and whilst the Independent Review of Building Regulations and Fire Safety has been completed the Government has yet to publish its response.
Recommendations
2.1Note and endorse the work undertaken by the Council and South Essex Homes in respect to Fire Safety.
2.2Note and endorse the Council’s initial response to the Independent Review of Building Regulations and Fire Safety.
2.3Request that a further update be provided to Cabinet to spring 2019.
Background
3.1The Council immediately commissioned a Fire Safety Review following the tragedy, which occurred as a result of the fire at Grenfell Tower. The Review Group comprises representatives of the Council, South Essex Homes and Essex County Fire and Rescue Service. In addition, the Council established an internal Fire Safety Meeting Group, chaired by the Deputy Chief Executive (Place) to examine any Council-specific actions identified as a result of the Review and to co-ordinate responses sought by Government Departments.
Fire Safety Report Page 1 of 8 18/037 3.2 The Council and South Essex Homes have already confirmed their commitment to progressively bring their properties in line with current Building Regulations, where appropriate, particularly in respect to fire safety and accessibility.
Capital Investments
3.3All of the Council’s operational buildings, alongside those managed by South Essex Homes, meet the regulatory standards in place when they were constructed, extended or altered and have up to date and reviewed Fire Risk Assessments in place. Where appropriate these risk assessments are undertaken in liaison with Essex Fire and Rescue Service.
3.4South Essex Homes has completed a number of fire safety works in addition to those set out in the Fire Safety Report considered by Cabinet at its meeting on the 13th March 2018 including:
Installation of new ‘Gerda’ Fire doors and screens to ‘Riverstone’ and ‘Barringtons’. Works have been tendered and the submissions are currently being evaluated. Given the ‘lead in’ time for the new specialist doors and screens is it anticipated that works will commence in November 2018 with a completion date of March 2019.
Upgrading of fire doors and screens to ‘sheltered’ properties. Works have been tendered and the contract awarded. It is expected that works will commence by October 2018 and the upgrade works will be completed late 2019.
Installation of Sprinklers to Hostels. Work is programmed to be completed in August 2018.
Smoke vents to Tower Blocks. Works are currently out to tender and works are expected to be completed by December 2018.
Mornington House fire stopping. These works are to be undertaken in conjunction with the fire upgrade works in the sheltered properties and works will be undertaken towards the front of the programme, so works are programmed to commence in September 2018
3.5South Essex Homes continues to work with Essex Fire and Rescue in relation to the role of sprinklers in its high rise buildings and reviews this position on a regular basis as part of its programme of Fire Risk Assessments.
Fire Safety Report Page 2 of 8 18/037 3.6 The Council is taking forward a range of fire safety works across its operational property estate initially focused on buildings identified as high priority and on improving fire compartmentation, means of escape, fire information and alarm systems. Works currently in progress include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.