The Cabinet considered a report of the Strategic Director (Finance & Resources) recommending in-year amendments to the approved Capital Programme for 2018/19 to 2021/22. Recommended: 1. That the current approved Programme for 2018/19 to 2021/22 of £215.0m, as set out in Appendix 1 to the submitted report, be noted. 2. That the changes to the approved Programme set out in Appendix 2, be approved. 3. That the proposed new schemes and additions to the Capital Programme for 2018/19 to 2021/22 totalling £1.4m (Appendices 6 and 7), be approved. 4. That it be noted that the proposed new schemes and additions (Appendices 6 and 7) and other adjustments (Appendix 2) will result in a proposed capital programme of £213.6m for 2018/19 to 2021/22 (Appendix 8). 5. That it be noted that of the total programme of £213.6m for the period 2018/19 to 2021/22, the level of external funding supporting this programme is £98.9m. 6. That it be noted that a mid-year review has been undertaken on the 2018/19 projected outturn and that the results have been included in the report. 7. That the revised Capital Programme for 2018/19 to 2021/22 that results from these changes (Appendix 8), be approved. Reasons for decision: To approve proposed changes to the Capital Programme since the last Cabinet meeting on 19 th June 2018. Other options: The proposed Capital Programme is made up from a number of individual projects, any of which can be agreed or rejected independently of the other projects. Note: This is a Council Function Eligible for call-in to: Policy & Resources Scrutiny Committee Cabinet Member: Cllr Lamb
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1The purpose of this report is to recommend in-year amendments to the approved Capital Programme for 2018/19 to 2021/22.
Recommendations
That the Cabinet recommend to Council that it;
2.1Note the current approved Programme for 2018/19 to 2021/22 of £215.0m (Appendix 1);
2.2Approve the changes to the approved Programme (Appendix 2);
2.3Consider and approve the proposed new schemes and additions to the Capital Programme for 2018/19 to 2021/22 totalling £1.4m (Appendices 6 and 7);
2.4Note that the proposed new schemes and additions (Appendices 6 and 7) and other adjustments (Appendix 2) will result in a proposed capital programme of £213.6m for 2018/19 to 2021/22 (Appendix 8);
2.5Note that, of the total programme of £213.6m for the period 2018/19 to 2021/22, the level of external funding supporting this programme is £98.9m (paragraph 5.1);
2.6Note that a mid-year review has been undertaken on the 2018/19 projected outturn and that the results have been included in this report;
2.7Approve the revised Capital Programme for 2018/19 to 2021/22 that results from these changes (Appendix 8). Capital Programme 2018/19 to 2021/22 – Mid Year Page 1 of 7 Report No: SSxx (number to be allocated by Karen Review Blows)followed by the initials of the PA/person who has typed this in brackets e.g.(kb) 3. Introduction and Background
3.1In February 2018 the Council approved a Capital Programme for 2018/19 to 2021/22 totalling £210.957million.
3.2The Capital Outturn report (June 2018) agreed a number of schemes where there were budget under-spends but financial commitments in 2018/19. In addition, due to the Council’s improved ability to deliver capital schemes, some capital expenditure due in 2018/19 was delivered early in 2017/18. These revisions were agreed at the Cabinet meeting on 19 June 2018 resulting in a total programme for 2018/19 to 2021/22 of £214.971million.
3.3Throughout the year changes to the approved capital programme are put forward to Cabinet for approval and also members review the latest spending position of the programme on a monthly basis. A mid-year review of the programme has also been carried out which included capital challenge sessions with each Deputy Chief Executive, led by the Leader and supported by the Strategic Director (Finance and Resources). This review was to re-align the budgets as necessary, to reflect the latest view on the delivery and funding timescales of the projects and to delete/amend schemes as necessary to assist with the financing of the overall programme.
3.4This report sets out the in-year amendments to the approved Capital Programme for 2018/19 to 2021/22 with the following appendices:
Appendix 1 – Approved Capital Programme June 2018 Appendix 2 – Changes to Approved Capital Programme; Appendix 3 - Virements Between Approved Schemes; Appendix 4 - Re-profiles Between Years; Appendix 5 – New External Funding; Appendix 6 – Proposed New Schemes and Additions to the Capital Programme; Appendix 7 – Proposed New Schemes and Additions - descriptions Appendix 8 – Amended Capital Programme 2018/19 to 2021/22.
4 Capital Programme 2018/19 to 2021/22 - Movements
4.1The Council’s current agreed capital programme for 2018/19 to 2021/22 is attached as Appendix 1 and totals £215.0m.
4.2In line with the revised approach to updates to the capital programme, new schemes and additions for urgent or service critical schemes will be added throughout the year as appropriate. The details of the new schemes and additions being put forward for inclusion at this Cabinet are set out in Appendices 6 and 7.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.