Policy and Resources Scrutiny Committee, Thursday 29 November 2018 at 6.30pm

Capital Programme - Mid Year Review

Noted Scrutiny 6 papers

Policy and Resources Scrutiny Committee noted this item on Thursday 29 November 2018. Below is the council's own wording, with the papers it was decided on.

Item503

Resolved

- That the following recommendations of cabinet be noted:- “1. That the current approved Programme for 2018/19 to 2021/22 of £215.0m, as set out in Appendix 1 to the submitted report, be noted. 2. That the changes to the approved Programme set out in Appendix 2, be approved. 3. That the proposed new schemes and additions to the Capital Programme for 2018/19 to 2021/22 totalling £1.4m (Appendices 6 and 7), be approved. 4. That it be noted that the proposed new schemes and additions (Appendices 6 and 7) and other adjustments (Appendix 2) will result in a proposed capital programme of £213.6m for 2018/19 to 2021/22 (Appendix 8). 5. That it be noted that of the total programme of £213.6m for the period 2018/19 to 2021/22, the level of external funding supporting this programme is £98.9m. 6. That it be noted that a mid-year review has been undertaken on the 2018/19 projected outturn and that the results have been included in the report. 7. That the revised Capital Programme for 2018/19 to 2021/22 that results from these changes (Appendix 8), be approved.” Note: This is a Council Function Cabinet Member: Cllr Lamb
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Policy and Resources Scrutiny Committee

Purpose of report

1.1The purpose of this report is to recommend in-year amendments to the approved Capital Programme for 2018/19 to 2021/22.

Recommendations

That the Cabinet recommend to Council that it;

2.1Note the current approved Programme for 2018/19 to 2021/22 of £215.0m (Appendix 1);

2.2Approve the changes to the approved Programme (Appendix 2);

2.3Consider and approve the proposed new schemes and additions to the Capital Programme for 2018/19 to 2021/22 totalling £1.4m (Appendices 6 and 7);

2.4Note that the proposed new schemes and additions (Appendices 6 and 7) and other adjustments (Appendix 2) will result in a proposed capital programme of £213.6m for 2018/19 to 2021/22 (Appendix 8);

2.5Note that, of the total programme of £213.6m for the period 2018/19 to 2021/22, the level of external funding supporting this programme is £98.9m (paragraph 5.1);

2.6Note that a mid-year review has been undertaken on the 2018/19 projected outturn and that the results have been included in this report;

2.7Approve the revised Capital Programme for 2018/19 to 2021/22 that results from these changes (Appendix 8). Capital Programme 2018/19 to 2021/22 – Mid Year Page 1 of 7 Report No: SSxx (number to be allocated by Karen Review Blows)followed by the initials of the PA/person who has typed this in brackets e.g.(kb) 3. Introduction and Background

3.1In February 2018 the Council approved a Capital Programme for 2018/19 to 2021/22 totalling £210.957million.

3.2The Capital Outturn report (June 2018) agreed a number of schemes where there were budget under-spends but financial commitments in 2018/19. In addition, due to the Council’s improved ability to deliver capital schemes, some capital expenditure due in 2018/19 was delivered early in 2017/18. These revisions were agreed at the Cabinet meeting on 19 June 2018 resulting in a total programme for 2018/19 to 2021/22 of £214.971million.

3.3Throughout the year changes to the approved capital programme are put forward to Cabinet for approval and also members review the latest spending position of the programme on a monthly basis. A mid-year review of the programme has also been carried out which included capital challenge sessions with each Deputy Chief Executive, led by the Leader and supported by the Strategic Director (Finance and Resources). This review was to re-align the budgets as necessary, to reflect the latest view on the delivery and funding timescales of the projects and to delete/amend schemes as necessary to assist with the financing of the overall programme.

3.4This report sets out the in-year amendments to the approved Capital Programme for 2018/19 to 2021/22 with the following appendices:

 Appendix 1 – Approved Capital Programme June 2018  Appendix 2 – Changes to Approved Capital Programme;  Appendix 3 - Virements Between Approved Schemes;  Appendix 4 - Re-profiles Between Years;  Appendix 5 – New External Funding;  Appendix 6 – Proposed New Schemes and Additions to the Capital Programme;  Appendix 7 – Proposed New Schemes and Additions - descriptions  Appendix 8 – Amended Capital Programme 2018/19 to 2021/22.

4 Capital Programme 2018/19 to 2021/22 - Movements

4.1The Council’s current agreed capital programme for 2018/19 to 2021/22 is attached as Appendix 1 and totals £215.0m.

4.2In line with the revised approach to updates to the capital programme, new schemes and additions for urgent or service critical schemes will be added throughout the year as appropriate. The details of the new schemes and additions being put forward for inclusion at this Cabinet are set out in Appendices 6 and 7.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 151 KB Download
PDF
Appendix 2Appendix 2 14 KB Download
PDF
Appendix 3Appendix 3 79 KB Download
PDF
Appendix 4Appendix 4 31 KB Download
PDF
Appendix 5Appendix 5 71 KB Download
PDF
Capital Programme: Mid Year ReviewReport 115 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 36 attended
BA
Councillor Brian AylingChair, present
CM
Councillor Carole MulroneyVice-Chair, present
BA
Councillor Bernard ArscottCommittee Member, apologies, sent representative
MB
Councillor Margaret BortonCouncillor, present as substitute
KB
Councillor Kevin BuckCouncillor, present
LB
Councillor Laurie BurtonCouncillor, present
DB
Councillor David BurzottaCommittee Member, present
FE
Councillor Fay EvansCommittee Member, apologies, sent representative
NF
Councillor Nigel FolkardCommittee Member, present
DG
Councillor David GarstonCommittee Member, present
JG
Councillor Jonathan GarstonCouncillor, present as substitute
IG
Councillor Ian GilbertCommittee Member, present

All 36 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Capital Programme - Mid Year ReviewThis decision
  2. Capital Programme AmendmentApproved
  3. Financial Performance Report for September 2025 (Period 6) - Changes to the Capital Investment ProgrammeApproved
  4. Capital Investment Programme 2019/20 to 2023/24Approved
  5. Draft Capital Investment Programme 2019/20 to 2023/24Noted
  6. Draft Capital Investment Programme 2019/20 to 2023/24Noted

More from Southend-on-Sea Policy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Minutes of the Meeting held on Thursday, 13th February 2025That the minutes of the meeting of the Committee held on Thursday, 13 th February 2025 be confirmed as a correct reco... Decided Open
31 Mar 2025 Additional Budget Considerations - 2025/26That the report to Cabinet be noted. Note: This is an Executive Function Cabinet Member: Councillor D Cowan (Leader o... Noted Open
13 Feb 2025 Minutes of the Meeting held on Thursday, 30th January 2025That the minutes of the meeting of the Committee held on Thursday, 30 th January 2025 be confirmed as a correct recor... Decided Open
13 Feb 2025 Corporate Performance Report Q3 2024/25 (October to December 2024) including Corporate Delivery Plan Actions update Q3 2024/25That the report to Cabinet be noted. Note: This is an Executive function Cabinet Member: Councillor D Cowan (Leader o... Noted Open
13 Feb 2025 Approval of the Annual Procurement Plan for 2025/26That the report to Cabinet be noted. Note: This is an Executive Function Cabinet Member: Councillor P Collins (Portfo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies