- That ENFORCMENT ACTION be AUTHORISED to secure the removal of the unauthorised dormer windows to the front elevation. The authorised enforcement action to include (if/as necessary) the service of an Enforcement Notice under Section 172 of the Act and the pursuance of proceedings whether by prosecution or injunction to secure compliance with the requirements of the Enforcement Notice. When serving an Enforcement Notice the local planning authority must ensure a reasonable time for compliance. In this case a compliance period of 3 months is considered reasonable for the removal of the existing dormer windows. Taking enforcement action in this case may amount to an interference with the owners’ and/or occupiers’ Human Rights. However, it is necessary for the local planning authority to balance the rights of the owners and/or occupiers against its legitimate aims to regulate and control land within its area. In this particular case it is considered reasonable, expedient, and proportionate and in the public interest to pursue enforcement action on the grounds set out in the formal recommendation.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
3.1In May 2018 following a complaint of unauthorised works it was confirmed that two dormer windows had been partly constructed in the roof of the front elevation. The property owner stated the dormers were repairs to pre-existing dormers.
3.2Enquiries on Google Street View revealed that there were no dormers installed at this location in 2014 and it was considered that the current, partly installed dormers, were unlikely to be repairs to pre-existing dormers.
3.3Staff advised the owner to remove the newly constructed dormers as a retrospective planning application would not likely be approved.
3.4In July 2018 the Local Planning Authority received a retrospective planning application to retain the dormers as built (18/01334/FULH.) In August 2018 that application was refused. See copy of the Officers Report at Appendix ‘A’
3.5In September 2018 an amended planning application was received (18/01745/FULH.) That application was refused. See copy of the Officers Report at Appendix ‘B’
3.6In October 2018 a further amended proposal was received. (18/01997/FULH). In January 2019 that application was refused. See copy of the Officers Report at Appendix ‘C’.
4 Appraisal and Policy Considerations
4.1The appended officer reports for the refused applications and in particular that seeking to retain the dormers (18/01334/FULH) – Appendix ‘A’, set out a full assessment of policy and other material considerations. Development Control Report 4.2 The key issue relevant to this enforcement report is the impact on character
4.3Design and Impact on the Character of the Area:
4.4National Planning Policy Framework (NPPF)(2018), Core Strategy (2007) Policies KP1, KP2 and CP4; Development Management Document Policy DM1 and DM3 and Design and Townscape Guide (2009)
4.5The key element within all relevant policies is that good design should be a fundamental requirement of new development in order to achieve high quality living environments. Its importance is reflected in the NPPF, in Policies KP2 and CP4 of the Core Strategy and also in Policy DM1 of the Development Management Document. The Design and Townscape Guide (2009) also states that “the Borough Council is committed to good design and will seek to create attractive, high-quality living environments.“
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.