Policy and Resources Scrutiny Committee noted this item on Thursday 11 July 2019. Below is the council's own wording, with the papers it was decided on.
That the following decisions of Cabinet be noted: 1. That the work to develop a regeneration framework and pipeline of housing and regeneration projects, including the potential to establish a revolving investment fund to deliver the pipeline, with a report coming forward to Cabinet in September 2019, be agreed. 2. That the process for responding to third party approaches is agreed for implementation. 3. To proceed with the Acquisitions Programme for Council Housing as agreed in the Council’s Housing, Homelessness & Rough Sleeping Strategy. 4. That a capital budget of £4.3M be created within the Housing Revenue Account (HRA) capital programme for 2019/20 to facilitate the Acquisitions Programme, funded 30% from retained Right to Buy Capital receipts and 70% from HRA Capital Investment Reserve.” That the following recommendation of Cabinet be noted: 5. That the delegated authority to the S151 Officer for property acquisitions and disposals for the sign off of the property acquisitions in Part 3, Schedule 3, Section 4 of the Constitution be amended to increase the value from £250,000 to £500,000.” Note: The decisions in 1-4 above constitute an Executive Function. The decision in 5 above constitutes a Council Function. Cabinet Member: Cllr Gilbert
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1This report provides an update on two key elements of the Housing, Homelessness and Rough Sleeping Strategy, namely housing supply and a proposed Acquisitions Programme for Council Housing. This report seeks approval to the funding and governance of the proposed acquisitions programme.
Recommendation
2.1That Cabinet agrees:
a. The work to develop a regeneration framework and pipeline of housing and regeneration projects, including the potential to establish a revolving investment fund to deliver the pipeline, with a report coming forward to Cabinet in September 2019.
b. To proceed with the Acquisitions Programme for Council Housing as agreed in the Council’s Housing, Homelessness & Rough Sleeping Strategy.
c. That a capital budget of £4.3M be created within the Housing Revenue Account (HRA) capital programme for 2019/20 to facilitate the Acquisitions Programme, funded 30% from retained Right to Buy Capital receipts and 70% from HRA Capital Investment Reserve.
d. That the delegated authority to the S151 Officer for property acquisitions and disposals for the sign off of the property acquisitions in Part 3, Schedule 3, Section 4 of the Constitution be amended to increase the value from £250,000 to £500,000.
Page 1 of 9 Report No 3. Background
3.1The need for affordable housing within the borough is greater than ever and is demonstrated by the outcomes of the Strategic Housing Market Assessment (SHMA) and by our own Homes Seeker’s Register data. The Council’s commitment to addressing this housing need is well documented with the Council’s Southend 2050 Vision & the corporate Housing, Homelessness and Rough Sleeping Strategy both reflecting this.
3.2In addition, the preparation of the new Local Plan for Southend will address how to achieve housing growth of all types to address local needs.
3.3The Council can play a number of different roles in increasing housing supply, and sometimes must fulfil these different roles at the same time:
Direct deliverer - as with the Housing Revenue Account funded development managed by the Strategic Housing Team which is now entering Phases 3 and 4. The most recent completion being the houses and flats at Rochford Road.
Landowner and Landlord - enabling new housing through redevelopment and/or disposal of its land and assets for development, or the potential to purchase affordable homes built on larger schemes.
Enabler - using various tools and approaches such as joint delivery arrangements including (but not limited to) the joint venture with Swan for Better Queensway, or development through Public Sector Partnerships (PSP) Southend LLP as used to deliver the developments at the former Hinguar Priimary School and Saxon Lodge in Shoeburyness. The Council can contribute finance or assets as part of enabling these developments, or consider sharing risk, acting as a guarantor or other bespoke options.
Planning authority – this role is relevant for all developments
3.4In light of the limited amount of land available for new development in the borough, work is being undertaken to plan the pipeline of development opportunites, including for new housing and affordable housing of the quality and design we aspire to. The pipeline includes new build, potential acquisitions and leasing opportunities such as a private sector leasing scheme along with the identification of potential estate refurbishment, repurposing and regeneration opportunities. The proposed acquisitions programme for council housing set out in section 3.14 of this report is one such example.
3.5The purpose of creating a planned, pro-active pipeline of regeneration and housing opportunities is twofold:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy and Resources Scrutiny Committee at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.