The Cabinet considered a joint report of the Chief Executive and Executive Director (Growth and Housing) setting out a programme of structural and improvement works required at the Balmoral Tower blocks (Grampian, Brecon and Blackdown) and to sought agreement to utilise HRA funds for these works.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1To advise Cabinet on a programme of structural and improvements work required at the Balmoral Tower blocks (Grampian, Brecon and Blackdown) and to seek agreement to utilise HRA funds for these works.
Recommendations
2.1To agree to progress with a programme of works to the Balmoral tower blocks to include both structural and improvement works (structural insulation and heating upgrades)
2.2To agree for the Council and South Essex Homes to undertake full consultation and engagement with affected residents.
2.3To agree a budget of £2.325m to be added to the HRA capital investment programme to be funded from the HRA Capital Investment Reserve.
Background
3.1Following routine planned structural surveys of the Council’s housing stock, an external consultant (Michael Dyson and Associates Ltd) advised that although the Balmoral tower blocks can be preserved for at least 30 years if usual repairs and maintenance are continued, given the construction of the blocks (Large Panel System) and recent guidance issued by DCLG in September 2017 further intrusive tests should be carried out to check whether the blocks could be modified to improve panel fixity and floor/wall resilience in the unlikely event of an explosion. It should be noted that the original structural surveys were not instigated because of any concerns in the buildings and the consultants did not advise that the blocks are unsafe and require immediate decant of the
Balmoral Major Works Update July Cabinet Report Number 20/025 residents. The blocks have electric heating and cooking facilities and not gas supplies, which lowers any potential risks to the properties.
3.2SEH procured Curtins Consulting Ltd for the required further structural investigations. Curtins produced a report following these intrusive structural checks which advised that the buildings do not comply with Building Regulations or the current Eurocode for concrete design. The buildings can however comply with the Building Research Establishment’s (BRE) LPS Criterion 2 with strengthening measures to the top 3 storeys which would limit the effects of gas explosion and therefore meet current recommendations. It should be noted that this only affects the Balmoral estate tower blocks not the other ten tower blocks in the borough and is not in any way connected to the post Grenfell Tower recommendations and is only concerned with the structure of the buildings themselves.
3.3A pilot project was undertaken to a void property in order to better understand the potential levels of disruption and timescales to carry out any works. The structural works recommended are as follows:
Fitting steel angle cleats to tie the base of certain wails to the floors throughout the flats and drying rooms. Reinstatement of wall and floor finishes and install larger skirting boards Remedial works to fitted bathrooms and kitchen units
3.4In addition to the structural works there would be a need for enabling works such as asbestos removal which would be included in the overall project costs.
3.5Additional works have also been identified that would be beneficial to be undertaken whilst the structural works are being carried out. This includes namely improvement to the structural insulation and also upgrades to the heating system (change from electric storage systems to oil filled panel heaters) which will improve the energy efficiency of the buildings. The blocks identified require major works so have not been identified for sprinkler inclusion at this
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.