The Cabinet considered a report of report of the Deputy Chief Executive and Executive Director (Growth & Housing) providing an update on the delivery of Forum 2 in the context of the economic impacts of the Covid-19 pandemic, and to seek agreement to the closure of the project in its current form.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
The purpose of the report is to update Cabinet on the delivery of Forum 2 in the context of the economic impacts of the Covid-19 pandemic, and to seek Cabinet’s agreement to the closure of the project in its current form, with the associated financial implications, as part of a joint decision with the College. The report also seeks agreement to the exploration of other routes to deliver the identified outcomes.
Recommendations
2.1That the financial impact of the Covid-19 pandemic on project viability for Forum 2 is noted and that as a result, the project as is currently planned is brought to a conclusion;
2.2That as a result of this, the associated capital expenditure budgets and their financing are removed from the current Capital Investment Programme;
2.3That the £6m Local Growth Fund (LGF) money secured for the project is released back to South East Local Enterprise Partnership (SELEP) for re- investment across the SELEP area and the costs incurred to date (c£1.4m) are borne on a 50:50 basis by the Council General Fund and by South Essex College (the College) and that the Council’s share of circa £700k is funded from the Business Transformation Reserve;
2.4That the outcomes identified for delivery through the project are noted and officers are requested to undertake an options appraisal as to how these could be still delivered in an alternative way, and that £50,000 is set aside in the Business Transformation Reserve to support this work. Future of Forum 2 Page | 1 Report Number 20/033 3. Background
3.1The Forum development was always intended as a two phase project to deliver educational, cultural and wellbeing benefits to residents, visitors, students and businesses while adding vibrancy to the town centre. Forum 2 is a 2050 roadmap project (as set out in section 6.1), is identified in the Southend Central Area Action Plan (SCAAP) and is an anchor for Southend in the Thames Estuary Production Corridor proposition as part of the Thames Estuary. It is a project that both the Council and the College have been committed to for a considerable length of time.
3.2Outcomes to be enabled through the delivery of Forum 2 can be summarised as: Support the Southend economy, and particularly the cultural and creative sector, through skills development and provision of performance and workspace; Increase the opportunities for residents, visitors and businesses to engage with the cultural sector thereby improving quality of life; Investment in, and activation of, space in the town centre Anchoring Southend in the Thames Estuary Production Corridor1.
3.3The scheme received planning consent in November 2019 for a four storey development plus a basement. It was due to start on site summer 2020 with a view to opening for the September 2021 academic year and was to deliver a mix of teaching, commercial and gallery space including new creative and digital ‘start-up’/co-working space for artists and local creative/digital businesses; contemporary and community art gallery; performing arts and music studios; computer music suites and a post-production room; commercial restaurant with associated professional kitchen; and general teaching rooms.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.