Southend-on-Sea Borough Council
Cabinet, Wednesday 2 December 2020 at 2.00pm

Better Queensway Regeneration Project - Progress Update and Consideration of the Final Proposals

Approved Executive 3 papers

Cabinet approved this item on Wednesday 2 December 2020. Below is the council's own wording, with the papers it was decided on.

Item600

Resolved

That the submitted Business Plan (attached to the report to the Shareholder Board), be approved. 2. That the Director of Regeneration and Growth, in consultation with the Leader, be authorised to: (a) agree any non-adverse changes to the Business Plan whereupon any such matters shall be noted for information and reported to the following Shareholder Board; and (b) approve , agree or action any necessary outcome, or product of, or from, the Business Plan necessary to progress the Better Queensway regeneration project. Reasons for decision The review of the Business Plan by Council officers and the Council’s procured advisors concluded that the Plan provides an assurance that the LLP is following the agreed strategic direction and objectives and is delivering its service and financial performance. Delegation of agreement of non-material updates to the Business Plan and progression of actions resulting from the Plan will ensure that the LLP can continue to progress the project at pace and with the necessary agility to meet funding and programme deadlines. Other options Not approving the Business Plan would mean that the Plan approved in November 2019 would remain in place until an amended Plan is approved. This would frustrate the progress of the project. The October 2019 Plan does not reflect the next years’ work on the project. The £15m HIF funding from Homes England has a deadline for spend. Not approving the Business Plan will delay the project as an amended Plan will be required, which could result in non-expenditure by the deadline and therefore a gap in project funding. If the Business Plan is compliant with the Partnership Agreement but is not approved by the Council, there is a risk to the goodwill established between the LLP Partners. This would have a considerably negative impact on the relationship between the LLP Partners. Note: This is an Executive Function Referred direct to: Place Scrutiny Committee Cabinet Member: Cllr Gilbert
Word for word from the decision Southend-on-Sea published for this meeting. Source: democracy.southend.gov.uk

Follow this further

Built from Southend-on-Sea's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1The purpose of this report is to provide an update to Cabinet following the consideration of a report to the Shareholder Board on the 1st December 2020 (“The Shareholder Board Report”).

1.2The Shareholder Board Report specifically considers the submission of the new Business Plan as appended to this report for Porters Place Southend-on-Sea LLP.

1.3The Shareholder Board’s Report’s purpose is to provide the Shareholder Board with clarity and assurance in regard to the progress update and new Business Plan to allow Members to fulfil their responsibilities.

1.4Appendices 2 and 3 of the Shareholder Board Report are confidential appendices and therefore Part 2 Agenda Items.

Recommendations

As detailed in the Shareholder Board Report and considering the minutes of the Shareholder Board attached at Appendix 1. 3 Background

As detailed in the Shareholder Board Report

4 The Business Plan

As detailed in the Shareholder Board Report

5 Assurance

As detailed in the Shareholder Board Report

6 Other Options

As detailed in the Shareholder Board Report

Reasons for recommendations

As detailed in the Shareholder Board Report

8 Corporate Implications

8.1Contribution to the Southend 2050 ambition, outcomes and road map

As detailed in the Shareholder Board Report . 8.2 Financial and value for Money Implications

As detailed in the Shareholder Board Report . 8.3 Legal Implications

As detailed in the Shareholder Board Report

8.4People Implications

As detailed in the Shareholder Board Report

8.5Consultation and Engagement

As detailed in the Shareholder Board Report

8.6Equalities and Diversity Implications

As detailed in the Shareholder Board Report 8.7 Risk Assessment

As detailed in the Shareholder Board Report

8.8Value for Money

As detailed in the Shareholder Board Report

8.9Community Safety Implications

As detailed in the Shareholder Board Report

8.10Environmental Impact

As detailed in the Shareholder Board Report

Background papers

None

Appendices

Appendix 1 Minutes of the Shareholder Board held on the 1st December 2020.

Appendix 2 The Shareholder Board Report and appendices referred to therein of which Appendices 2 and 3 of the Shareholder Board Report are Confidential and not for publication by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Porters Place Business Plan Part 1Appendix 1 434 KB Download
PDF
Better Queensway Regeneration Project: Progress Update and Consideration of the Final ProposalsReport 60 KB DownloadRead as text
PDF
SHB BQ December Part 1 BP Report FINAL 30.11.2020Report 144 KB Download

At this meeting

Whole meeting

Who was there

7 of 20 attended
TS
Trevor SaundersOfficer, expected
MB
Michael BarnesOfficer, expected
LR
Larissa ReedCouncil Staff, expected
TF
Tandra ForsterOfficer, expected
MM
Michael MarksOfficer, expected
SB
Sarah BakerOfficer, expected
AG
Alison GriffinOfficer, expected
JW
John WilliamsOfficer, expected
AL
Andrew LewisOfficer, expected
AA
Andrea AthertonOfficer, expected
JC
Joe ChestertonOfficer, expected
JR
Joanna RuffleOfficer, expected

All 20 on the meeting page

On this subject at Southend-on-Sea

Search all
  1. Better Queensway Regeneration Project - Progress Update and Consideration of the Final ProposalsThis decision
  2. Better Queensway Notice of Motion, Transport Policy & Strategy response reportAgreed
  3. Better Queensway Underpass Closure Impact Assessment UpdateNoted
  4. Better Queensway Project ProgressionApproved
  5. Better Queensway UpdateApproved
  6. Notice of Motion - Better QueenswayDecided

More from Southend-on-Sea Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 Minutes of the Meeting held on Monday, 7 September 2026That the Minutes of the Meeting held on Monday 7 September 2026 be amended to correct the typographical error in minu... Decided Open
12 Oct 2026 Decisions taken by, or in consultation with, Cabinet MembersThat the decisions taken by, or in consultation with, the relevant Cabinet Members since the last Cabinet meeting be ... Noted Open
12 Oct 2026 Official Feed and Food Control Service Plan 2026-27That the achievements delivered against the Official Feed and Food Control Service Plan 2025/26 be noted. 2. That the... Noted Open
12 Oct 2026 Income Contract with Castle Point Borough Council for CCTV System ManagementThat it be agreed to enter into a contract with Castle Point Borough Council for the provision of CCTV Services to Ca... Agreed Open
12 Oct 2026 Procurement of a Stairlift Installation, Maintenance & Removal ServiceThat approval be given to undertake a procurement exercise to establish a Framework Agreement for the provision of a ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies