The Cabinet Committee received a report of the Executive Director (Neighbourhoods and Environment) regarding the commencement of consultation and implementation of the Traffic Regulation Orders in respect of various junction protection schemes across the Borough. The list of proposed schemes was attached at Appendix 1 to the submitted report.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1To inform the Traffic Regulations Working Party and the Cabinet Committee of the commencement of consultation and implementation of the Traffic Regulation Orders in respect of various Junction Protection schemes across the Borough.
1.2The Junction Protection Scheme is a 2 year capital funded scheme. This report is the second of a number of reports that will be presented in 2020/21 and 2021/22.
Recommendation
For information only.
Background
3.1The junction locations referred to in the attached appendix 1 were the subject of requests received from Councillors and members of the public. All the proposed locations have been surveyed by officers and meet the current criteria for the implementation of the no waiting at any time restriction to provide the appropriate junction protection at these sites. All other junctions without protection have been surveyed and no waiting at any time restrictions will be implemented in a Boroughwide roll out in 2021/22.
4. Reasons for Implementation of Junction Protection
4.1The proposals aim to improve the operation of the existing parking controls to contribute to highway safety, improve sightlines and accessibility and to reduce congestion. 5. Corporate Implications
5.1Contribution to the Southend 2050 Road Map.
5.1.1 Ensuring parking and traffic is managed while maintaining adequate access for emergency vehicles, general traffic flow and improved sightlines at junctions. This is consistent with the Council’s Vision and Corporate Priorities of Safe, Prosperous and Healthy.
Financial implications
5.2.1 Costs for implementation of the Order in Appendix 1, will be met from the capital funding that has been agreed for the Junction Protection project.
Legal implications
5.3.1 The statutory consultative process for Traffic Regulation Orders will be followed. Any objections received will be responded to by the service area. Members will be included in the circulation of the notice and any comments received will be considered in the consultation process.
5.4People Implications
5.4.1 Works required to implement the agreed scheme will be undertaken by existing staff resources.
5.5Property Implications
5.5.1 None
5.6Equalities and Diversity Implications
5.6.1 Any implications have been taken into account in designing the schemes.
5.8Risk Assessment
5.8.1 The proposals are designed to improve highway safety and traffic flow and as such, is likely to have a positive impact.
5.9Value for Money
5.9.1 Works associated with the schemes listed in Appendix 1 will be undertaken by the Council’s term contractors, selected through a competitive tendering process to ensure value for money.
5.10Community Safety Implications
5.10.1 The proposals in Appendix 1 if implemented is likely to lead to improved community safety. 5.11 Environmental Impact
5.11.1 There is no significant environmental impact as a result of introducing the Traffic Regulation Order.
Background papers
6.1None
Appendices
7.1Appendix 1 – The draft Traffic Regulation Order advertisement. . Appendix 1
To introduce No Waiting at Any Time
Road Name Side of Description Road From its junction with Medway Crescent westwards for approx.12m North From its junction with Medway Crescent eastwards for approx.12m Western Road From approx 12m east of its junction with Medway Crescent South westwards to a point approx opposite the western flank wall of No 198 Western Road
Middlesex From its junction with Surrey Avenue northwards for approx 10m West Avenue From its junction with Surrey Avenue southwards for approx 10m
Surrey Avenue Both From its junction with Middlesex Avenue westwards for 10m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.