That Cabinet Committee be recommended: 1. That the Executive Director (Neighbourhoods and Environment) be authorised to commence the statutory consultation on the proposed waiting restriction at the junctions illustrated in the plans attached to the submitted report at Appendix 1 and, subject to there being no representations following statutory advertisement, to arrange for the relevant traffic regulation order(s) to be confirmed and the proposals implemented. 2. That, in the event formal objections are received following statutory consultation, any unresolved objections be submitted to the Traffic Regulations Working Party and Cabinet Committee for consideration.
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
1.1This Report is to identify locations where additional waiting restrictions are needed to manage and maintain access at various junctions throughout the Borough. The objective is to improve access and safety by improving visibility at junctions.
Recommendations
2.1It is recommended that Cabinet; -
Junction Protection Proposals
2.2Approves the following proposals regarding junction protection waiting restrictions for formal consultation (Ward plans displaying the extent of the proposed waiting restrictions can be seen in Appendix 1).
a) Confirm authorisation for formal consultation of the Traffic regulation Order (TRO) on the proposals identified in Appendix 1. b) If there are no specific objections to proposed junctions that they be introduced without further reference to the Traffic Regulation Working Party or Council Committee. c) If specific junctions do receive formal objections, then the affected proposals be subject toa follow on report to address the reasons for the objections and for Officers to include appropriate recommendations to resolve the objection details. d) Revise proposals where appropriate to comply with request from residents without compromising the pay and display restrictions.
Background
3.1The Council in response to concerns and complaints regarding obstruction to junctions through inconsiderate parking are looking to address this issue throughout the borough.
1 3.2 The proposal is to introduce no waiting at any time (NWAAT) as the default on each junction that currently does not have any protection. In addition, where single yellow lines are in use these will be upgraded to double yellow lines. (NWAAT).
3.3To provide detailed proposals, the Council commissioned the review of each junction to produce suitable proposals to be considered and implemented subject to the Council Traffic Regulation Order policy.
3.4There are approximately 450 junctions within the borough that needed this appraisal, and the details of these recommendations can be seen in the plans attached in Appendix 1 to this report.
3.5It is anticipated that the proposals set out in this Report will improve the traffic flow for all vehicles and improve visibility and safety at junctions with minimal impact on parking capacity.
Reasons for recommendations
4.1Junction protection aims to reduce congestion and to improve safety for all road users.
5. Further Implications
5.1Corporate Implications to the Southend 2050 Road Map 5.1.1 Ensuring parking and traffic is managed while maintaining adequate access for emergency vehicles and general traffic flow and improved sightlines at the various junctions. This is consistent with the Council’s Vision and Corporate Priorities of Safe, Prosperous and Healthy.
5.2Financial Implications 5.2.1 Costs for implementation of these Orders will be met from the capital funding that has been agreed for this project.
5.3Legal Implications 5.3.1 The formal statutory consultative process for Traffic Regulation Orders has been followed.
5.4People Implications 5.4.1 Works required to implement the agreed scheme will be undertaken by existing staff resources.
5.5Property Implications 5.5.1 None
5.6Equalities and Diversity Implications 5.6.1 Any implications have been considered in designing these schemes.
5.7Risk Assessment 5.7.1 The proposals are designed to improve highway safety and traffic flow and as such, are likely to have a positive impact.
5.8Value for Money 5.8.1 All works resulting from the scheme design are to be undertaken by term contractors appointed through a competitive tendering process ensuring value for money.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Traffic Regulations Working Party at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.