Policy and Resources Scrutiny Committee decided this item on Thursday 2 September 2021. Below is the council's own wording, with the papers it was decided on.
That the matter be referred back to the Cabinet for reconsideration, as the Committee felt that further review should be undertaken with regard to the Thorpedene Campus site proposed to be conditionally opted into PSP Southend LLP for delivery. 2. That in accordance with Council Procedure Rule 39, the matter be referred to full Council for consideration. Note: This is an Executive Function Cabinet Member: Councillor R Woodley
Word for word from the decision Southend-on-Sea published for this meeting.Source: democracy.southend.gov.uk
To recommend 4 sites are conditionally opted into PSP Southend LLP for delivery.
Recommendations
2.1That Cabinet notes that the high-level business plan, future updates to it and progress against it will be presented to Shareholder Board in due course together with the financial performance of PSP Southend LLP (the LLP).
2.2That the sites listed in section 3.4 of this report are conditionally opted into the LLP for delivery in line with the objectives set out subject to the completion of all relevant due diligence required through PSP Stages e2 and e3 (including completion of the best value review by CIPFA). Operational decisions on the development of the sites going forward will be taken by the LLP Partnership Board (through the Council’s LLP Representatives).
2.3That officers continue to engage with the partnership through regular liaison meetings on the future pipeline of development opportunities to ensure that the business plan can be serviced and there is a continuous pipeline of delivery to optimise and support the viability of the LLP.
2.4That Cabinet note that the £5m identified for the delivery of Ilfracombe Avenue will no longer be required and can be released form the Capital Programme and that officers and the LLP are pursuing potential funding via the Homes England ASELA fund to assist with viability and delivery.
Report Title PSP Southend LLP Report Number 3. Background
3.1Partnership Arrangements
The report to Cabinet on 25 February 2020 set out the background to the Council’s PSP Southend LLP partnership and the proposed changes to it, principally to align it to the Council’s other companies which now report into Shareholder Board. Cabinet minute 857 refers.
3.2Business Plan
It has been identified that the Council and the LLP would benefit from a business plan to bring together the strategic objectives of the partnership with the operational objectives for individual projects.
The business plan is being developed. At recommendation 2.1 of this report, Cabinet is asked to note that it will be presented to Shareholder Board in due course once it has been agreed by the LLP Partnership Board.
3.3Delivery to date and the 4e’s model
To date, the Council has delivered the developments at the Former Hinguar Primary School, Saxon Lodge and the nursery and housing at Constable Way, all in Shoeburyness through the PSP model with a good degree of success.
Sites progress through the LLP in a structured way through the following stages:
These stages take opportunities from their earliest stages through to delivery in a manner that is compliant with all relevant finance, governance, statutory and procurement rules.
Sites can be looked at for e1 and into e2 before Cabinet approval is required for them to progress. At the point when Cabinet is asked to agree sites to be progressed through the LLP, high level objectives for the site will be set out and then incorporated into the business plan. All further decisions will then be made within the LLP provided that they are aligned to the agreed objectives and the LLP will report to Shareholder Board on performance against the agreed objectives.
3.4Sites recommended to be delivered by the LLP.
Following initial due diligence, and work through the Housing & Development Pipeline project, it is recommended that the following sites are now opted into the LLP for further work.
Land at (formerly) Futures High School Ilfracombe Avenue Car Park (previously agreed but delivery method to change) Thorpedene Campus Land East of Brendon Way
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy and Resources Scrutiny Committee at Southend-on-Sea and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.